Kehoe v. Mayor of Rutherford

27 A. 912, 56 N.J.L. 23, 27 Vroom 23, 1893 N.J. Sup. Ct. LEXIS 37
CourtSupreme Court of New Jersey
DecidedNovember 15, 1893
StatusPublished
Cited by12 cases

This text of 27 A. 912 (Kehoe v. Mayor of Rutherford) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kehoe v. Mayor of Rutherford, 27 A. 912, 56 N.J.L. 23, 27 Vroom 23, 1893 N.J. Sup. Ct. LEXIS 37 (N.J. 1893).

Opinion

The opinion of the court was delivered by

Dixon, J.

On October 15th, 1888, the plaintiff and defendant entered into a written contract, under seal, by which the plaintiff became bound to grade, work, shape, level, smooth and roll Montrose avenue, in the borough of Eutherford, to its entire width, according to the established grade, commencing at Washington avenue and ending at Pierpont avenue, and the defendant became bound to pay him therefor sixty-five cents per lineal or running foot.

Soon afterwards the plaintiff began the work, and continued until it was discovered that some of the land to be graded under the contract was private property. Then, being forbidden by the owners to enter upon this property, the plaintiff stopped the work by direction of the borough authorities and concluded to abandon it. In the meantime he had been paid $1,850 of the contract price.

On this state of facts he brought suit against the defendant, relying, in one count of his declaration, upon the breach of the special contract, and in another on the quantum meruit for the work done.

At the trial in the Bergen Circuit, the plaintiff’s evidence tended to prove that the length of the whole work required by the contract was four thousand two hundred and twenty [25]*25feet, which, at the contract rate, sixty-five cents per lineal foot, made the aggregate price $2,743.; that about three thousand five hundred feet in length had been substantially graded, but still needed trimming up and finishing; that in doing this work he had1 excavated about eight thousand cubic yards of earth and had put in about one thousand three hundred cubic yards of filling; that, to complete the job,^ about fourteen thousand cubic yards of filling were still necessary, besides the trimming up and finishing of the entire length of the street. His evidence further indicated that the fair cost of the work done was—

8.000 cubic yards of excavation, at 35 cents............$2,800

900 cubic yards of filling, at 21 cents.................... 189

400 cubic yards of filling, at 41 cents..................... 164

Making a total of....................................$3,153

And that the fair cost of the work remaining to be done in completely performing the contract was—

14.000 cubic yards of filling, at 12 cents.................$1,680

4,220 feet of finishing, at 5 cents........................... 211

Making a total of....................................$1,891

Thus showing the fair cost of the whole work required by the contract to be $5,044.

These calculations are, in every instance, based upon the testimony most favorable to the plaintiff, allowing him the highest estimates for what he had done, and reckoning the residue at the lowest. If his own estimates or those of any single witness were taken throughout, the result would be more to his disadvantage.

Upon the evidence thus presented, the plaintiff was non-suited and a rule. alU’"ed that the defendant show cause why a new trial should not be awarded.

The.nonsuit was ordered upon the theory that the plaintiff could recover, for the work done, only such a proportion of [26]*26the contract price as the fair cost of that work bore to the fair cost, of the whole work required, and, in respect of the work not done, only such profit (if any) as he might have made by doing it for the unpaid balance of the contract price. Under this theory, his recovery for the work done was to be limited to such a proportion of $2,743 as three thousand one hundred and fifty-three bears to five thousand and forty-four, viz., $1,715; and as to the work not done, since it would cost him $1,891 to do it, while the unpaid balance of the price was only $893, no profit could be earned by doing it. Hence it was considered that he had been overpaid to the extent of the difference between $1,850 and $1,715. ^

But the contention of the plaintiff was and is that, as he was prevented from completing the contract without fault on his part, he is entitled to the reasonable value of the work done, without reference to the contract price; and if this be the correct rule, undoubtedly the case should have gone to the jury. But at the very threshold we are confronted with this possible result of the application of the rule contended for, that the plaintiff might recover $3,153 for doing about three-fifths of the work, while if he had done it all he could have recovered only $2,743. The absurdity of the result condemns the application of such a rule.

Circumstances may exist in which, for work done under a special contract, the plaintiff will recover its fair value. Thus, if the contract be within the prohibition of the statute of frauds (McElroy v. Ludlum, 5 Stew. Eq. 828), or if, the work being only partly done, that which is done or that which is left undone cannot be measured so as to ascertain its price at the rate specified in the contract (Derby v. Johnson, 21 Vt. 17), or, in the absence of evidence to the contrary, it may be assumed that the rate specified is a reasonable one. United States v. Behan, 110 U. S. 338.

But .generally, when it can be determined what, according to the contract, the plaintiff would receive tor that which he has done and what profit he would have realized by doing that which, without fault, he has been prevented from doing, [27]*27then these sums become the legal, as they are the just, meas- » u re_pf h i sdam a ge s. He is to lose nothing, but, on the other hand, he is to gain nothing, by the breach of the contract, except as the abrogation of a losinguargain may save him from additional loss.

This is the rule applied in the case of Masterton v. Mayor, &c., of Brooklyn, 7 Hill 61, where the plaintiff was to receive $271,600 for eighty-eight thousand eight hundred and nineteen feet of marble, and after he had delivered fourteen thousand seven hundred and seventy-nine feet, the defendant stopped him. He was awarded the contract price for the fourteen thousand seven hundred and seventy-nine feet, and the profit which he would have made by delivering the balance. The same principle was declared by this court in Boyd v. Meighan, 19 Vroom 404, and accords with the fundamental doctrines laid down by Mr. Sedgwick (1 Sedgw. Dam. [200] 432)—fir^thak the plaintiff must show himself to have sustained damage, or, in _other words, that actual compensation will only be given for actual loss; and, second, that the contract itself furnishes the measure of damages.

Sometimes it has been held that if the contract binds the defendant'"to pay otherwise than in money, and he refuses, then the plaintiff may recover the cash value of what he has done or delivered (Ankeny v. Clark, 148 U. S. 345); butjn New Jersey the rule is that he shall recover the cash value of what he was to receive (Hinchman v. Rutan, 2 Vroom 496), thus maintaining the standard fixed by the contract.

Some of the obscurity surrounding this subject springs, I think, from a failure to distinguish between the right to sue upon the quantum meruit when the contract remains uncompleted through the fault of the defendant and the measure of damages in such a state of facts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JL Davis & Associates v. Heidler
622 A.2d 923 (New Jersey Superior Court App Division, 1993)
Princeton Montessori Soc., Inc. v. Leff
591 A.2d 685 (New Jersey Superior Court App Division, 1991)
Westmount Country Club v. Kameny
197 A.2d 379 (New Jersey Superior Court App Division, 1964)
Wilkins v. Bailey Engineering Co., Inc.
91 A.2d 98 (New Jersey Superior Court App Division, 1952)
De Ponte v. Mutual Contracting Co.
86 A.2d 785 (New Jersey Superior Court App Division, 1952)
Goldman v. Shapiro
84 A.2d 628 (New Jersey Superior Court App Division, 1951)
Westlecraft v. Barry
83 A. 501 (Supreme Court of New Jersey, 1912)
Calumet Construction Co. v. Board of Education
76 A. 970 (Supreme Court of New Jersey, 1910)
Harrison v. Clarke
73 A. 43 (Supreme Court of New Jersey, 1909)
Sullivan v. Moffatt
56 A. 304 (Supreme Court of New Jersey, 1903)
Wentink v. Board of Chosen Freeholders
48 A. 609 (Supreme Court of New Jersey, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
27 A. 912, 56 N.J.L. 23, 27 Vroom 23, 1893 N.J. Sup. Ct. LEXIS 37, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kehoe-v-mayor-of-rutherford-nj-1893.