Ames-Ennis, Inc. v. Midlothian Ltd. Partnership

469 F. Supp. 939, 1979 U.S. Dist. LEXIS 12874
CourtDistrict Court, D. Maryland
DecidedApril 23, 1979
DocketCiv. B-76-1358
StatusPublished
Cited by14 cases

This text of 469 F. Supp. 939 (Ames-Ennis, Inc. v. Midlothian Ltd. Partnership) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ames-Ennis, Inc. v. Midlothian Ltd. Partnership, 469 F. Supp. 939, 1979 U.S. Dist. LEXIS 12874 (D. Md. 1979).

Opinion

MEMORANDUM AND ORDER

BLAIR, District Judge.

This is an action by a building contractor to recover damages from the Secretary of Housing and Urban Development (HUD) and from the owner-developer of a “Section 236” 1 housing project constructed by the plaintiff. The facts pleaded are essentially as follows: The owner, Midlothian Limited Partnership (Midlothian), undertook to develop a lower-income housing project in Richmond, Virginia. The project was FHA-insured and financed by Maryland National Bank (MNB), an FHA-approved mortgagee. Midlothian engaged the plaintiff, Ames-Ennis, Inc. (Ames-Ennis), to build the project. The various agreements among the parties are evidenced by, inter alia, the Regulatory Agreement between Midlothian and the Secretary (acting through the Federal Housing Commissioner) which governs most aspects of the management of the project; a Commitment for Insurance of Advances, entered into by MNB and the Commissioner; a Mortgagor’s Certificate entered into by the Commissioner and Midlothian; and a Cost Plus Construction Contract (with amendments) between Ames-Ennis and Midlothian. A clause of the Mortgagor’s Certificate specifies that “. . . upon completion of the Project there will not be outstanding any unpaid obligations contracted in connection with the purchase of the property, construction of the Project, or the mortgage transaction except such obligations as may be approved by [the Commissioner] as to terms, form and amount.” Exhibit 5 to Amended Complaint. The plaintiff contends that it substantially completed construction of the project, but that Midlothian still owes Ames-Ennis the sum of $465,623 under the contract and that the Secretary refused to authorize release of and MNB wrongfully refused to release to Ames-Ennis a 10% retainage representing some $360,000. Midlothian filed a counterclaim alleging that Ames-Ennis failed to perform its obligations under the contract.

The amended complaint is in four counts. The first alleges that HUD and Midlothian, having agreed that upon completion of the project there would remain no outstanding obligations except those approved by HUD, acted tortiously “in symbiotic concert” to withhold the retainage allegedly due Ames-Ennis. The second count asserts that Ames-Ennis is the third-party beneficiary of various contracts between HUD and Midlothian assuring payment in full of the construction loan funds. The two remaining counts assert pendent claims: Count III alleges that Ames-Ennis is third-party ben *942 eficiary of various contracts between Midlothian and Maryland National Bank (MNB) which contemplate full payment of construction funds, and Count IV is a simple contract claim for monies due.

Both Midlothian and the Secretary have moved to dismiss for, inter alia, lack of subject matter jurisdiction. It is asserted that Count I must be dismissed for failure of the plaintiff to comply with the requirement of the Federal Tort Claims Act, 28 U.S.C. § 2671, § 2675(a), that a claim first be presented to the defendant agency and that Count II must be dismissed since it presents a contract claim in excess of $10,-000 which falls under the exclusive jurisdiction of the Court of Claims. 28 U.S.C. § 1346(a)(2) and § 1491. It is agreed that if it be found that this court lacks jurisdiction over the federal defendant in Counts I and II, then the case in its entirety must be dismissed. 2 That is precisely the conclusion reached by the court.

While conceding that it never presented its Count I claim to HUD in compliance with the Federal Tort Claims Act and that Count II seeks to recover more than $10,000 on a contract, Ames-Ennis nevertheless asserts several alternative bases for federal jurisdiction. The court will treat these seriatim.

12 U.S.C. § 1702

The plaintiff asserts that this court has jurisdiction over Counts I and II under 12 U.S.C. § 1702, that section of the National Housing Act which permits the Secretary of HUD in her official capacity “to sue and be sued in any court of competent jurisdiction, State or Federal.” The question is whether this is an affirmative grant of jurisdiction or merely a waiver of sovereign immunity.

The Fourth Circuit ruled in 1942 that the “sue and be sued” language of § 1702 was an affirmative grant of jurisdiction and that the jurisdiction of the District Courts to hear suits against federal agencies was not limited by the Tucker Act. Ferguson v. Union National Bank of Clarksburg, W. Va., 126 F.2d 753, 756-57 (4th Cir. 1942). This decision was followed early by the Third Circuit, George H. Evans & Co. v. United States, 169 F.2d 500, 502 (3d Cir. 1948), and later by the Tenth Circuit, Mar v. Kleppe, 520 F.2d 867, 870-71 (10th Cir. 1975), and by at least one district court. See, e. g., Travelers’ Indemnity Co. v. First National Bank of New Jersey, 328 F.Supp. 208, 211-12 (D.N.J.1971).

While ordinarily this court would consider itself conclusively bound by the holding of the Fourth Circuit, in this case, recent developments in the law as well as a number of well-reasoned opinions in other circuits compel the conclusion that § 1702 is not an independent basis of jurisdiction. The Third Circuit (in a more recent case), as well as the Eighth and Ninth Circuits have held that the “sue and be sued” language of § 1702 is not jurisdictional but is merely a waiver of sovereign immunity. Lindy v. Lynn, 501 F.2d 1367, 1369 (3d Cir. 1974); Bor-Son Building Corporation v. Heller, 572 F.2d 174, 181 (8th Cir. 1978); DSI Corporation v. Secretary, 594 F.2d 177 (9th Cir. 1979). Several district courts are in accord: Harms v. FHA, 256 F.Supp. 757, 760 (D.Md. 1966); Ghent v. Lynn, 392 F.Supp. 879, 880-81 (D.Conn.1975); Trans-Bay Engineers & Builders, Inc. v. Lynn, 396 F.Supp. 265, 268 (D.D.C.1975), affirmed in part, vacated in part and remanded on other grounds, 179 U.S.App.D.C. 184, 190, 551 F.2d 370, 376 (1976).

This court is in agreement with those cases which hold that 12 U.S.C. § 1702 is not an affirmative grant of jurisdiction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Knuckles v. RBMG, INC.
481 F. Supp. 2d 559 (S.D. West Virginia, 2007)
Reynolds Associates v. Kemp
974 F.2d 1331 (Fourth Circuit, 1992)
1610 CORP. v. Kemp
753 F. Supp. 1026 (D. Massachusetts, 1991)
Lavapies v. Bowen
687 F. Supp. 1193 (S.D. Ohio, 1988)
CH v. American Red Cross
684 F. Supp. 1018 (E.D. Missouri, 1988)
Baskes v. Federal Sav. and Loan Ins. Corp.
649 F. Supp. 1358 (N.D. Illinois, 1986)
Tempo, Inc. v. City of Gladstone Housing Commission
635 F. Supp. 879 (W.D. Michigan, 1984)
Mundo Developers, Ltd. v. Wicklow Associates
585 F. Supp. 1324 (S.D. New York, 1984)
Giannetti Bros. Construction Corp. v. Lee County
585 F. Supp. 1214 (M.D. Florida, 1984)
Chase v. Theodore Mayer Bros.
592 F. Supp. 90 (S.D. Ohio, 1983)
Berks Products Corp. v. Landreau
523 F. Supp. 304 (E.D. Pennsylvania, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
469 F. Supp. 939, 1979 U.S. Dist. LEXIS 12874, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ames-ennis-inc-v-midlothian-ltd-partnership-mdd-1979.