Algonquin Gas Transmission Co. v. Federal Energy Regulatory Commission

948 F.2d 1305, 292 U.S. App. D.C. 197
CourtCourt of Appeals for the D.C. Circuit
DecidedNovember 1, 1991
DocketNos. 89-1634, 89-1668, 89-1693, 89-1709, 89-1736, 89-1744
StatusPublished
Cited by1 cases

This text of 948 F.2d 1305 (Algonquin Gas Transmission Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Algonquin Gas Transmission Co. v. Federal Energy Regulatory Commission, 948 F.2d 1305, 292 U.S. App. D.C. 197 (D.C. Cir. 1991).

Opinion

HENDERSON, Circuit Judge:

Under review in this action are several portions of an order issued by the Federal Energy Regulatory Commission (FERC or the Commission). In accepting and modifying a contested settlement agreement between a natural gas pipeline and its customers, the Commission altered the gas cost and facilities cost recovery method [200]*200provided in the agreement. The Commission also modified the fuel retention rate and the short-haul transportation rate reflected in the agreement. Under the relevant statute, before altering a settlement agreement, FERC must establish, first, that the agreement, as written, is unjust, unreasonable or unduly discriminatory and, second, that the proposed changes make it just and reasonable. Our review of the record establishes that the Commission failed to carry this statutory burden with respect to its alterations. We therefore grant the petitions for review and remand the proceeding for further action by the Commission.

I.

Algonquin Gas Transmission Co. operates a natural gas transmission pipeline stretching from New Jersey, through New York, Connecticut and Rhode Island, to Massachusetts. Until 1981, Algonquin offered gas for sale to its local distribution customers under two “basic” rate schedules, F-l and WS-1.1 Under these rate schedules, Algonquin allocated the cost of the facilities necessary to provide its services on a “rolled-in” basis. That is, the costs of all of the transmission facilities were rolled in together and then recovered from each customer in proportion to the amount of gas each received. See ANR Pipeline

Co. v. FERC, 771 F.2d 507, 510-11 (D.C.Cir.1985) (per curiam). Under rolled-in pricing, the amount of facilities costs the pipeline recovers from a particular customer depends on the volume of gas the customer purchases, not the service to which the customer subscribes.2 On the other hand, Algonquin recovered the cost of the gas it sold under the F-l and WS-1 schedules on an “incremental” basis. This method passed through to the customer, based on the service to which the customer subscribed, the cost that Algonquin itself incurred in purchasing gas from its supplier for sale under the two rate schedules.3 The gas for Algonquin’s two basic sales services, F-l and WS-1, came from its supplier under different rate schedules. For this reason, the gas costs associated with Algonquin’s two services varied independently of each other and in direct relation to the price under the supplier’s applicable rate schedule. 47 FERC at 61,145.

At different times in the 1980s, the pipeline sought and received Commission approval to offer new services. Before 1981 Algonquin had offered a gas storage service under schedule STB but it had contracted with another gas company for the necessary facilities. In 1981, the pipeline spent $45 million on additional facilities that permitted it to offer the STB service relying exclusively on its own plant.4 Be[201]*201ginning in 1986, Algonquin offered a second storage service under schedule SS — III. The pipeline constructed no new facilities before offering this service; it relied only on the facilities constructed for the STB service. For both of these storage services, Algonquin, with the Commission’s approval, allocated the facilities costs on an incremental basis: it recovered the cost of constructing the new facilities only from those customers who subscribed to the services. See ANR Pipeline, 771 F.2d at 511; see generally Battle Creek Gas Co. v. FPC, 281 F.2d 42, 46-47 (D.C.Cir.1960).

In 1984 and 1985, Algonquin also began offering three new firm5 sales services, F-2, F-3 and F-4. Under these new rate schedules, the subscribing customers purchase gas that Algonquin receives from three suppliers6 who, under new agreements, supplement the pipeline’s previous supply of gas. Algonquin constructed new transmission facilities in order to offer the new services.7 For the three new services, Algonquin obtained Commission authorization to recover both the facilities costs and the gas costs incrementally rather than rolling the costs into the schedules for its other services.

Also at issue in this proceeding is Algonquin’s short haul, T-l rate schedule. Since 1967, Algonquin has offered a short haul, firm transportation service to customers near the origin of the pipeline. This service covers hauls with an average distance of only 25 miles. The T-l rate schedule was designed on a mileage-sensitive basis so that customers under this schedule would bear only a portion of the facilities costs borne by other customers farther from the head of the pipeline. The rationale behind the T-l schedule was that it was unnecessary for the short haul schedule to reflect the cost of all of the pipeline’s facilities because the service under this schedule involved only a small portion of those facilities. The T-l schedule also excluded from the rate base the cost of the facilities constructed for Algonquin’s “incremental” sales and storage services (the F-2, F-3 and F-4 sales services and the STB and SS — III storage services).

This proceeding began in January 1986 when Algonquin filed with the Commission an application for a rate increase under docket number RP86-41.8 The Commission accepted the filing, suspended the new rates for the statutory five-month period [202]*202and then permitted them to go into effect subject to refund. See 15 U.S.C. § 717c(e); Algonquin Gas Transmission Co., 34 FERC 1161,278 (Feb. 28, 1986). At the hearing on Algonquin’s proposed rates, the Commission staff argued against the continued incremental allocation of some of the pipeline’s costs. The staff recommended that the facilities costs for all of the new or “incremental” services should be rolled in and recovered from all pipeline customers, including the T-l customers, instead of from only the customers subscribing to those services. It recommended that the gas costs associated with the basic services, F-l and WS-1, as well as with the F-4 service should be recovered on a rolled-in basis.9 The staff also recommended abolishing the distance-sensitive nature of the T-l schedule so that customers under the T-l schedule would pay a fully allocated share of the pipeline’s facilities costs. After a hearing on the rate proposal, the Administrative Law Judge (ALJ) concluded that the staff had failed to show that the incremental rate structure was unjust or unreasonable and therefore declined to order the roll-in the staff advocated. The AU also rejected the staff’s recommendation to alter the distance-sensitive nature of the T-l schedule. See Algonquin Gas Transmission Co., 39 FERC ¶ 63,023 (May 12, 1987).

After the AU’s initial decision, the parties attempted to negotiate a settlement. After negotiating an agreement, Algonquin filed it with the Commission as a contested settlement. It provided for the continuation of the incremental pricing structure for Algonquin’s new services and continued in place the lower T-l rate schedule for short-haul transportation. Before approving the agreement the Commission substantially modified it in several respects. It ordered the roll-in of all of the costs the pipeline had theretofore recovered on an incremental basis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Algonquin Gas Transmission Company v. Federal Energy Regulatory Commission, Central Hudson Gas & Electric Corporation, Boston Gas Company, New Jersey Natural Gas Company, the City of Norwich, Connecticut, Colonial Gas Company, Orange and Rockland Utilities, Inc., Bay State Gas Company, Consolidated Edison Company of New York, Inc., New England Power Company, Intervenors. Central Hudson Gas and Electric Company v. Federal Energy Regulatory Commission, the City of Norwich, Connecticut, Colonial Gas Company, Consolidated Edison Company of New York, Inc., Bay State Gas Company, Algonquin Gas Transmission Company, Boston Gas Company, New England Power Company, New Jersey Natural Gas Company, Orange and Rockland Utilities, Inc., Intervenors. Orange and Rockland Utilities, Inc. v. Federal Energy Regulatory Commission, New Jersey Natural Gas Company, Colonial Gas Company, Bay State Gas Company, Boston Gas Company, Central Hudson Gas & Electric Corporation, Consolidated Edison Company of New York, Inc., New England Power Company, Orange and Rockland Utilities, Inc., the City of Norwich, Connecticut, Algonquin Gas Transmission Company, Intervenors. City of Norwich, Connecticut, Department of Public Utilities, and the Town of Middleborough, Massachusetts, Municipal Gas and Electric Department v. Federal Energy Regulatory Commission, Algonquin Gas Transmission Company, New Jersey Natural Gas Company, Colonial Gas Company, Bay State Gas Company, Boston Gas Company, Central Hudson Gas & Electric Corporation, Consolidated Edison Company of New York, Inc., New England Power Company, Orange and Rockland Utilities, Inc., Intervenors. New Jersey Natural Gas Company v. Federal Energy Regulatory Commission, Algonquin Gas Transmission Company, Boston Gas Company, Bay State Gas Company, Central Hudson Gas & Electric Corporation, Colonial Gas Company, Consolidated Edison Company of New York, Inc., New England Power Company, Orange and Rockland Utilities, Inc., the City of Norwich, Connecticut, Intervenors. Boston Gas Company v. Federal Energy Regulatory Commission, Algonquin Gas Transmission Company, Bay State Gas Company, Central Hudson Gas & Electric Corporation, Colonial Gas Company, Consolidated Edison Company of New York, Inc., New England Power Company, New Jersey Natural Gas Company, Orange and Rockland Utilities, Inc., the City of Norwich, Connecticut, National Helium Corporation, Intervenors
948 F.2d 1305 (D.C. Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
948 F.2d 1305, 292 U.S. App. D.C. 197, Counsel Stack Legal Research, https://law.counselstack.com/opinion/algonquin-gas-transmission-co-v-federal-energy-regulatory-commission-cadc-1991.