JOHN R. BROWN, Chief Judge:
The Federal Energy Regulatory Commission (FERC) issued several opinions and orders
in which it (1) found Florida Gas Transmission Company’s (FGT) gas curtailment plan to be unduly discriminatory and (2) disclaimed jurisdiction to order curtailment of gas FGT merely transports. In this case, several parties —
aligning themselves in different camps on different issues — seek review of those opinions. While some argue that substantial evidence does not support the Commission’s holdings, others insist that the Commission has erred in not immediately implementing its orders. Finding that it has struck a proper balance, we affirm the Commission on all points.
FGT operates a natural gas pipeline that serves several areas of Florida. It sells both to distributors (who in turn sell to residential, commercial, and industrial customers) and directly to some large industrial concerns.
It also transports gas for two major electric generating companies, Florida Power Corporation (FP) and Florida Power and Light (FPL), both of which buy large amounts of gas in Texas.
FGT has fixed various rate schedules and degrees of reliability of service in its sales contracts. Wholesale distributors may purchase gas under the G schedule, which provides firm general service, and the I schedule,
which offers gas for resale to preferred interruptible resale customers. Direct customers may also purchase either
interruptible
or firm service.
Under FGT’s tariff,
in case of gas shortages, it will curtail deliveries to its customers in the following order:
(1) primary interruptible direct customers, (2) preferred interruptible direct, (3) distributors purchasing under schedule I, (4) firm direct industrial, (5) distributors purchasing under schedule G (for resale to firm customers).
Prior to 1972, FGT contemplated — and experienced — only relatively short term curtailments of its interruptible customers. Because it did not foresee any gas supply shortage, it expected to deliver substantially all of its contract volumes. In 1973, however, FGT curtailed its direct interruptible customers twice as many days as it had in 1972. In 1974, that figure almost doubled again.
On March 21, 1975 Lehigh Portland Cement Company,
a direct interruptible customer of FGT, filed a complaint under Section 5(a) of the Natural Gas Act
(the Act), asserting that FGT’s curtailment plan unlawfully discriminates against direct industrials in favor of indirect industrials purchasing from distributors. It argued that because the plan curtails gas without re
gard to end-use,
it should be found unjust, unreasonable, unduly discriminatory, and preferential. The Commission set the matter for formal hearing on its own motion, and on August 5, 1976, the Presiding Administrative Law Judge issued a decision dismissing the complaint.
The Commission, however, reversed the ALJ in its Opinion No. 807. Announcing that “those who are similarly entitled must be treated equally regardless of their ability to survive otherwise,” it found FGT’s plan unduly discriminatory and ordered it to file a new plan that would provide equal treatment of direct and indirect customers who make similar use of the gas.
The Commission further ordered that FP and FPL be joined as parties so that all gas transported by FGT could be made part of the new plan.
After several parties petitioned for rehearing, the Commission issued Opinion No. 807-A, which affirmed its previous holding that FGT’s curtailment plan was no longer just and reasonable, but rescinded its order that the pipeline file a new plan. It instead determined that the existing curtailment should remain in effect until the § 5 hearing was completed or pending further Commission order. In addition, 807-A summarily reversed the Commission’s prior decision to include the FP and FPL transportation gas in any new plan.
Numerous interested parties filed petitions for review in this Court.
On January 18, 1977, in an independent proceeding, the Fort Pierce Utilities Authority of the City of Fort Pierce filed a petition and complaint. It requested (1) that the Commission order curtailments of the transportation gas on FGT’s system, and (2) that the Commission condition further transportation upon FGT’s curtailing the transportation volumes proportionately with those to which preferred interruptible customers would be otherwise entitled.
The Commission issued an order dismissing the claim on August 3, 1977, and denied rehearing on September 30, 1977. In both orders it found that it lacked the authority to grant the requested relief. It reasoned that because FGT does not own the transportation gas, it cannot allocate it. Moreover, legal title passes before the gas flows interstate. Again, several parties peti
tioned this Court for review of the Commission orders.
Undue
Discrimination
In attacking the Commission’s finding, that FGT’s plan is unduly discriminatory, petitioners
first contend that FERC evaluated FGT’s curtailment plan against an incorrect standard, and that it improperly shifted the burden of proof in its proceedings. They cite the Commission’s statement in Opinion 807, that “there is a heavy burden to show that a non-end-use plan is superior,” and contend that it demonstrates that the Commission elevated its statement of policy — as announced in Order 467, favoring end-use considerations
— to a legal presumption. Moreover, it compelled the supporters of the status quo to prove that the plan met the standard rather than imposing the burden of proving violation on those seeking to change the curtailment.
Such arbitrary action,
they insist, merits reversal of the Commission’s decision.
We cannot agree. We think the Commission correctly applied the § 4(b) standard as it interpreted it.
An examination of Opinions 807 and 807-A reveals that the Commission initially found a preference unsupported by a reasonable basis for distinction, and
then
determined that an end-use plan would be appropriate for rem
edying the discrimination.
In 807 it examined the similarities between two cement plants — one an indirect customer of FGT, the other a direct — and found no statutorily acceptable reason for the indirect customer’s receiving almost twice as much FGT gas as the direct.
It made this finding before discussing “the necessity for an end-use plan.”
In 807-A the Commission, apparently trying to clear up any confusion caused by Opinion 807, carefully delineated its two findings:
. the Commission said [(1)] that the [FGT curtailment plan] discriminates against its direct sale customers in favor of indirect customers, who receive gas on resale from distributing companies, and [(2)] that FGT must file a curtailment plan based on end-use of the gas providing equal treatment for direct and indirect customers making similar use of the gas.
Regarding the contention that the above-quoted sentence shows that the Commission shifted the burden of proving violation of the Act, we first emphasize that it made this statement while discussing the sort of plan FGT should submit in place of the present one. It had
already
found a violation of the Act. Next, we point to the Commission’s answer to this very claim in Opinion 807-A, in which it said that
[w]e recognize that the complainant has the burden of proof and that Order No. 467-B merely states our policy. We think, however, that the
complainants have met their burden
of showing that while they operate in like manner as the indirect customers they receive a smaller share of gas.
Op. 807-A, slip op. at 7, emphasis added.
Petitioners level their second attack against Opinions 807 and 807-A by arguing that, contrary to the Commission’s findings, a reasonable basis did support the admitted discrimination.
They point to the history of the pipeline and the unique economic difficulties involved in supplying gas to Florida, contending that these factors militate against a change in the present system.
Because Florida experiences generally mild weather conditions with occasional drastic changes in temperature, temperature sensitive loads may swing annually as much as about 800%. In order to serve these loads efficiently, therefore, FGT distributors had to sell to customers who would accept interruptible service. In other words, in order to maintain dependable deliveries to those serving residential and other high priority users, the pipeline had to develop an industrial market that would use large amounts of available gas but could be curtailed during gas shortages.
Thus, say
petitioners, the plan does work to protect high priority users.
While we recognize — as does the Commission — that the present plan may favor some high-priority users,
we do not agree that discrimination against direct customers is necessary to secure this protection.
And although we accept the contention that industrial loads may be necessary to enable the pipeline and its distributor-customers efficiently to offer residential and commercial service, we cannot make the leap necessary to conclude that this necessity requires favoring distributor-supplied industrials over those who buy directly.
Petitioners offer the argument that many of the distributors would face bankruptcy if they were curtailed to the extent that their industrial customers received gas supplies on an equal basis with direct industrials. Here, again, we agree with the Commission that there is now insufficient basis for such a contention. Until the FERC holds hearings specifically to study possible plans and their effects, assertions of adverse impact on particular distributors is speculation.
Moreover to the limited
extent that the record reflects the effect of the Commission’s decision, it indicates that a 467 priority plan would provide to over seventy-five percent of the distributors on FGT’s system more gas than they would have under the present tariff.
Petitioners finally contend that Opinions 807 and 807-A are unlawful because direct and indirect customers — between which the Commission found undue discrimination — are not in the same class for the purposes of the Act. They are thus not legally comparable. Labeling the indirect industrials “non-customers,” petitioners contend that the Commission should compare curtailment only between “customers” —i. e., direct industrials and wholesale distributors. Since the
distributors
determine the extent of curtailment after
they
receive the gas, FGT’s tariff does not determine the extent of curtailment to resale users.
We have no trouble dispensing with these contentions. First of all, the Supreme Court has recognized Commission authority over curtailments of both direct and indirect customers.
FPC v. Louisiana Power and Light Co.,
1972, 406 U.S. 621, 92 S.Ct. 1827, 32 L.Ed.2d 369. FGT’s particular system of distribution has divided a group of similarly entitled
consumers into categories based on rates and dependability of service. It has also determined
when
indirect industrials will be served by creating a special rate schedule for indirect interruptible customers (most of which are industrial) and making it part of its curtailment priority order. Thus, by establishing the schedule I and G rates, the pipeline took an affirmative part in determining the flow of gas to indirect industrials. In such a situation, we cannot say that the Commission was unreasonable in making the comparison it did.
Immediate Implementation
Gardinier, Inc., a direct interruptible customer of FGT, also seeks review of Opinions 807 and 807-A, but with a different approach. While supporting the Commission’s finding of an undue preference, it challenges the FERC’s failure immediately to implement a substitute plan. It argues that § 5 mandates such immediate action and insists that both §§ 5 and 4 offer the procedures. We will address the § 5 and § 4 arguments separately.
Before going further, however, we must point out that a “reasonableness” standard governs our consideration of this issue. If the Commission has acted reasonably — in light of the basic fact findings and record evidence — in ordering the existing plan to remain in effect pending § 5 hearings,
we must sustain its decision.
American Smelting, noted supra,
161 U.S.App.D.C. at 22, 494 F.2d at 941.
Section 5’s mechanism for remedying discrimination in allocation of gas begins with the Commission’s lawfully finding a § 4(b) violation. Upon such determination, the Commission will then impose its own plan, but only after a hearing and an administrative determination that the plan implemented is just and reasonable.
See Southern Natural Gas v. FPC,
5 Cir., 1977, 547 F.2d 826, 832. While, as Gardinier asserts, the Commission would have emergency authority — even when conducting a § 5 hearing — to prescribe an interim plan,
it can do so only after a full hearing.
This hearing requirement, along with the lack of record evidence on various curtailment plans, marks the source of the Commission’s reluctance to impose an interim plan. Since the structure of the fact finding proceedings before the ALJ effectively precluded presentation of data regarding possible alternative curtailment plans, the Commission maintains that it must develop a record before it can reasonably enforce compliance with any new system, end-use or otherwise. Speedy action without the benefit of data on costs and effects, says the Commission, might result in the implementation of a plan more discriminatory than that now in existence.
The FERC agrees that it must remedy the discrimination (and denies petitioner’s assertion that it is withholding relief). According to the Commission, the relief
Is
forthcoming, but in accordance with the procedural requirements of § 5.
Gardinier asserts that the record does contain sufficient evidence to support temporary relief
and insists that § 5 absolutely requires such immediate action.
It points to decisions of several courts that have recognized the Commission’s authority to issue interim curtailment orders
We do not think, though, that these acknowledgments of authority necessarily mean that the Commission has an affirmative duty to fashion interim relief in all cases. Indeed, the opinions petitioner cites all recognize the Commission’s discretion in determining whether such relief is necessary.
The
Consolidated Edison
cases,
cited by Gardinier, do not support its position. They
instead reinforce our finding that the Commission
may
formulate an interim plan under § 5. In
Consolidated Edison I
the District of Columbia Circuit found that a 467-type curtailment plan — submitted by Transcontinental Pipeline (Transco) — would have an extremely harsh impact on certain customers. It therefore temporarily replaced the submission with a settlement agreement, previously rejected by the Commission, negotiated between Transco and its customers. After having discussed the reasons for its action, the court added that “[o]ur present action . . . in no way precludes the Commission from modifying the settlement or taking other action based on the information which it has generated . . ..***. . .the Commission asserts, and we agree, that it has residual emergency powers to impose an interim plan where there is no alternative.” Warning that “[sjuch powers must be carefully confined,” it nevertheless found that the Commission — faced with an emergency shortage of gas and little possibility of formulating a permanent curtailment plan before winter — could effect such a plan.
By acknowledging the Commission’s authority to act, while at the same time providing for the possibility that it would not institute interim measures, the court clearly recognized the Commission’s
discretion
to fashion such relief.
Similarly, in
Consolidated Edison II
the court reiterated its statement that “the FPC
might
issue interim curtailment orders
based on evidence compiled in hearings on a permanent plan.”
(Emphasis added). It cautioned, however, that once the Commission instituted such relief, it “has a responsibility to monitor whatever interim plan may be in effect pending a final decision, and to make such adjustments as may appear warranted. * * * Our decision today places heavy reliance on the Commission’s conscientious discharge of its oversight function.” 168 U.S.App.D.C. at 103, 512 F.2d at 1343. Thus, contrary to Gardinier’s assertion that the Commission’s oversight function compels it to institute interim relief, that function arises
with
the implementation of interim measures.
Having found that the Commission indeed has discretion to impose an interim curtailment plan, we must now consider the question whether it has reasonably exercised this discretion. Gardinier, maintaining that the Commission has been unreasonable, attacks its stated reasons for not fashioning interim relief as “frivolous.” The first of these reasons is the Commission’s fear that a plan submitted in accordance with Opinion 807’s order would be construed as a § 4 filing. Desiring to avoid the summary procedures involved with such filings
the Commission ordered that FGT submit a “case in chief” rather than an actual curtailment plan.
Gardinier criticizes this action, accusing the Commission of suffering from a basic misunderstanding of § 5. A plan so ordered, according to petitioner, would be a § 5
compliance
filing. We agree that only § 5 allows the Commission to impose a particular plan.
Southern Natural Gas Co. v. FPC,
5 Cir., 1977, 547 F.2d 826, 832. We further acknowledge that if a pipeline files under coercion rather than voluntarily, the plan is invalid unless § 5 procedural requirements have been satisfied.
Consolidated Edison I, supra.
But we fail to see how this renders the Commission’s action unreasonable. Even under the 807 order, the Commission was not going to put FGT’s proposal immediately into effect. It was going to conduct extensive hearings and supervise a detailed study in order to produce a just and reasonable final product. Assuming without deciding
that the Commission misapprehended the effect of an ordered filing, we nevertheless find that that mistake would not necessarily have prejudiced petitioner. There is no indication.that FGT’s proposal would have taken effect before the plan that FGT and the Commission will ultimately produce.
The Commission also stated that it wished to avoid causing undue harm to schedule I customers of FGT-supplied distributors:
To impose a 467-B plan on their system and its distributors with their heavy dependence on the industrial load without adequate consideration of its effects at a hearing would in our opinion be reckless. Likewise we cannot properly take the half-step of requiring equal treatment of the direct preferred interruptible customers and the I customers because the record is not sufficient on the entitlements of the various customers or the impact on any but a few. Therefore, we shall not prescribe an interim plan at this time but will allow the present plan to remain in effect pending further Commission order.
Gardinier attacks this reasoning with the observation that all end-use plans, however implemented, necessarily curtail low-priority users most heavily. It further contends that the Commission’s refusal immediately to impose such a plan is inconsistent with its stated policy of ensuring priority of delivery to residential and commercial consumers during gas shortages.
If the Commission were truly concerned about possible economic harm to particular customers, continues Gardinier, it would have ordered expedited proceedings or have prescribed a plan with an invitation to seek special relief. Despite petitioner’s concerns, we think that the Commission acted reasonably. The District of Columbia Circuit has recognized that a 467-type curtailment can have an unduly harsh impact on certain customers.
And the Commission
has
granted special relief to several parties claiming harm as a result of discrimination in allocation. By refusing to impose such a new plan without a sufficient record, the Commission is not shirking its § 5 remedial duties. It has merely determined that the (known) effects of the existing plan may be less severe than those of a plan prescribed without adequate study.
We now turn to Gardinier’s claim that the Commission should have required the pipeline to shoulder its § 4
burden of
unilaterally filing a proposed curtailment system. In our discussion of § 5 remedial procedures, we explained one of our objections to this position. If FGT were persuasively to claim that it had filed only under coercion from the Commission, and § 5 procedures had not been observed, the filings would be invalid.
If, on the other hand, FGT voluntarily filed, only
guided
by the 807 order, the § 4 mechanism would be set in motion. As we explained in
Southern Natural Gas Co., supra
at 832,
[ujnder section 4, a regulatee can file its own plan, and, after 30 days, that plan will take effect unless the FPC suspends its operation. In no event can the FPC suspend a proffered plan for longer than five months.
Courts have recognized that § 4 allows “greater celerity and flexibility,”
Southern Natural Gas Co., supra
at 832, and for that reason have often deemed it appropriate to proceed thereunder in emergency situations.
FPC v. Louisiana Power and Light Co., supra.
But as we have observed, the authority to do so is discretionary. The Commission stated specifically its reasons for not wanting any plan to become effective before the completion of a hearing and Commission action. Since we have found its rationale reasonably adequate in our discussion of § 5, we find it unnecessary to review it further. We thus reject Gardinier’s claim.
Transportation Gas
We finally turn to the contention of several of the petitioners
that the Commission should order curtailment of the FP and FPL-owned gas that FGT merely transports.
When considering this claim in the Fort Pierce proceeding, the Commission said
[w]e do not concur with Cities in curtailing the T-gas under any of the contracts because such gas is not owned by Florida Gas and does not form a part of the system’s gas supply from which gas can be allocated to its various customers.
* # * sfc * *
Since legal title to the gas has vested in the two power companies prior to its interstate transportation, we do not believe that the
Louisiana Power and Light
and
Lo-Vaca Gathering Company
cases are applicable herein for purposes of Cities’ request.
The Commission adopted this position in Opinion 807-A, in which it revoked joinder of FP and FPL and excluded transportation gas from the curtailment proceeding.
Petitioners advance several arguments in support of their attack on the Commission’s order. The first is that § 1
of the Act grants the Commission the jurisdiction to curtail any gas that is transported in interstate commerce, regardless of who owns it. As authority for this statement, it cites two Supreme Court opinions,
FPC v. Louisiana Power & Light, supra,
and
California v. Lo-Vaca Gathering Co.,
1965, 379 U.S. 366, 85 S.Ct. 486, 13 L.Ed.2d 357. We think both cases distinguishable.
In
Louisiana Power & Light
the Commission had imposed an interim curtailment plan to cover all sales customers of United Gas Pipe Line Company, both direct and resale. In rejecting the direct customers’ objection that their sales were not jurisdictional and, therefore, could not be curtailed,
the Court said that “the Act applies to interstate ‘transportation’ regardless of whether the gas transported is ultimately sold retail or wholesale.” 406 U.S. at 636, 92 S.Ct. at 1836.
Petitioners would have us find that just as it was unnecessary in
Louisiana Power & Light
to find direct sales jurisdictional for rate purposes, it is unnecessary to deal with the
ownership
of transportation gas. We cannot make the logical connection necessary to reach such a conclusion. The Supreme Court dealt only with the issue of whether the Commission could, independently of its sales jurisdiction, supervise curtailment of gas
owned
by a natural gas company.
It made this clear when it explained that
[ujnder LP&L’s argument, this volume would be wholly exempt from any curtailment plan approved by the FPC and thus United’s resale customers would be forced to accept the entire burden of sharply reduced volumes while direct-sales customers received full contract service .
Id.
at 632, 92 S.Ct. at 1834. We cannot extend the Court’s holding to allow Commission-ordered allocation of gas owned by two companies that are not subject to Commission jurisdiction.
Similarly, we do not agree with petitioners that
Lo-Vaca
provides a basis for including FGT’s transportation gas within the Commission’s jurisdiction. In that case El Paso Natural Gas Company purchased gas produced in Texas by Lo-Vaca and Houston Pipe Line Company. Pursuant to its various contracts with Lo-Vaca, El Paso bought gas both for resale (jurisdictional) and for its own use (non-jurisdictional). El Paso’s contract with Houston restricted the gas to intrastate uses (non-jurisdictional). The Commission held that the commingling of the three supplies established FPC rate jurisdiction over the entire amount owned by El Paso.
The Supreme Court affirmed the holding, but we think that it made clear that the particular facts of the situation dictated the result.
Expressing fear that a contrary holding would allow pipelines to discriminate between producers by “immuniz[ing] [some] from the reach of federal regulation,” 379 U.S. at 370, 85 S.Ct. at 488, the Court found that “the fact that a substantial part of the gas will be resold, in our view, invokes federal jurisdiction over the entire transaction.”
Id.
at 369, 85 S.Ct. at 488. The Court has never extended this holding beyond the facts of this case — petitioners have not convinced us that we should.
Trying a slightly different tack, petitioners claim that the Commission has recognized its jurisdiction in at least two specific situations, in the
Sea Robin
proceedings
and in
Fort Pierce Utility Authority, supra.
We disagree. In
Fort Pierce
several of the petitioners before us today had applied for special relief from FGT’s curtailment plan. They contended that transportation gas
should be curtailed to help relieve the burden on FGT’s sales customers. The Commission found that a special relief proceeding was an inappropriate forum for consideration of the question. It neither admitted nor denied jurisdiction. It simply ruled that the parties would have to reassert their claim pursuant to § 1.6 of the Commission’s Rules of Practice and Procedure, 18 CFR § 1.6 (1975).
In
Sea Robin
the Commission granted certification for the transportation of new deliveries of offshore gas by Sea Robin Pipeline to Amoco for sale to FGT. It conditioned the certificate upon the requirement that “the gas involved shall be delivered to FGT only in satisfaction of the Amoco-FGT . . . sale and none . to [FPL].” The Commission acted upon the authority expressly granted to it in § 7(e)
of the Act to “lay down conditions precedent to the entry of natural gas into interstate commerce.” It did not purport to assert curtailment authority over transportation gas. It did not force the pipeline to reallocate gas it did not own — Sea Robin would still deliver all the gas to Amoco, a natural gas company, over which the Commission has jurisdiction. The situation is clearly distinguishable from that presented here.
A recent case from the District of Columbia Circuit,
American Public Gas Association (APGA) v. FERC,
1978, 190 U.S.App.D.C. 192, 587 F.2d 1089, lends support to the result we reach today.
In rejecting a claim that certain transportation gas had to be included in pipeline curtailment plans, the Court said that
the purpose of a curtailment plan is to prescribe the manner in which a pipeline that cannot meet its contractual commitments will curtail deliveries of its
own
gas.
190 U.S.App.D.C. at 201, 587 F.2d at 1098.
The excerpt from
APGA
describes the situation before us. FGT stands in the
position of a bailee in relation to FP and FPL. We think that the Commission correctly determined that because FGT never owned the gas, it could not be compelled to allocate it to others. The transportation gas has never been a part of the supply available to FGT for satisfaction of its sales contracts. We see no authority for making it so now.
Having determined that the Commission correctly found that it had no jurisdiction over the transportation gas, we find it unnecessary to address fully petitioners’ other arguments. We merely point out that the Commission’s legal conclusion did not constitute a factual determination that the curtailment of transportation gas would not result in greater availability to some higher-priority users. Neither did it implicitly approve undue discrimination in allocation of supplies. Finding that the Commission acted reasonably, we affirm.
ENFORCED.