Fort Pierce Utility Authority v. Federal Power Commission

526 F.2d 993, 13 P.U.R.4th 321, 1976 U.S. App. LEXIS 12928
CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 9, 1976
DocketNo. 75-1397
StatusPublished
Cited by11 cases

This text of 526 F.2d 993 (Fort Pierce Utility Authority v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fort Pierce Utility Authority v. Federal Power Commission, 526 F.2d 993, 13 P.U.R.4th 321, 1976 U.S. App. LEXIS 12928 (5th Cir. 1976).

Opinion

MORGAN, Circuit Judge:

In this case we review an order of the Federal Power Commission issued on December 9, 1974 which granted petitions for extraordinary relief1 from an existing curtailment plan2 of Florida Gas Transmission Company (Florida Gas). Florida Gas, due to the present gas shortage, is delivering gas to its customers pursuant to a curtailment plan filed with the FPC. Four customers, Basic Magnesia, Inc., Wenczel Tile Company, Borden Inc., and Gardinier, Inc., (the applicants) filed applications with the FPC for extraordinary relief from the curtailment plan alleging that their particular need for gas entitled them to a preference over Florida Gas’ other customers. The main opponent to these applications was a group of municipally owned utilities in Florida (the Cities). The Cities argue that (1) the Commission lacked jurisdiction to grant any relief, (2) if relief was granted, the Cities were entitled to financial compensation from the applicants, and (3) not only gas that the Cities purchased from Florida Gas’ own supply be allocated to the applicants, but also gas transported but not owned by Florida Gas be included in any order. The Commission rejected these arguments and granted some relief to each of the applicants. The Cities appeal. We agree that the Commission properly rejected the Cities’ first and third contentions; however, we reverse the Commission on the second point and remand.

Florida Gas Transmission Company operates a gas transmission line from Texas to Central and Northern Florida. In 1959, due to expected shortages in its supply of gas, Florida Gas filed a curtailment plan as part of its tariff with the Commission. Under this plan, the customers of Florida Gas were divided into groups of firm and interruptible customers. A firm customer was one as to whom Florida Gas was bound by contract to deliver a stated amount of gas. An interruptible customer was one who had purchased gas under contract which allowed Florida Gas, under certain conditions, to temporarily cease delivery or “interrupt” the supply of gas. All firm customers were given a preference over interruptible customers. Thus, during the shortage Florida Gas would supply firm customers with gas first. The interruptible customers were further divided into two sub-groups, resale customers and direct sale customers. Resale customers were those customers who do not use gas for their own purposes but “resell” it. In contradistinction, a direct sale customer was one who purchased the gas primarily for his own needs. Within the interruptible category of customers, the resale customers were given preference over direct sale customers.

[996]*996The net result was that under Florida Gas’ curtailment plan, the direct sale interruptible customers were to be curtailed first during a period of shortages. Within a group, the gas would be curtailed ratably.

Under the tariff that Florida Gas filed, the only gas which would be affected by the curtailment plan was gas which was owned by Florida Gas. Unaffected by the curtailment plan was gas which Florida Gas transported for the two major Florida utilities, Florida Power Company and Florida Power and Light Company. This gas was purchased by the utilities in Texas at the well head and transported by Florida Gas to their facilities in Florida. Although Florida Gas acted as a conduit for the gas owned by the two power companies, while the gas was in the transmission line, it was necessarily co-mingled with the gas owned by Florida Gas. The power companies would simply remove the same volume of gas in Florida as they had put in the system in Texas.

While Florida Gas operated under its curtailment plan, shortages continued to become more severe, and eventually several customers sought a special preference from the Commission by filing applications for extraordinary relief. As pointed out above, it is the granting by the Commission of four of these applications which constitute the subject matter of the present appeal. The four successful applicants argued that they needed special treatment primarily because they use gas in processes for which no reasonable substitute is available. Since the applicants are all direct sale interruptible customers, they were among the first users to be curtailed, and they alleged severe economic harm unless special relief was granted. The Cities, also direct sale interruptible customers, do not contend before this court that the applicants do not have a special need for extra gas supplies. The Cities do contend that the Commission did not have jurisdiction to grant the relief. They argue, furthermore, if the Commission did have such jurisdiction, the terms and conditions of the relief were in violation of the Natural Gas Act.

I.

The first question is whether the Commission had jurisdiction to grant the relief sought by the applicants. Here, the Cities rely on § 1(b) of the Natural Gas Act, 15 U.S.C. § 717(b). That section provides in relevant part:

The provisions of this act shall apply to the transportation of natural gas in interstate commerce, the sale in interstate commerce of natural gas for resale for ultimate public consumption for domestic, commercial, industrial, or for any other use, . . . but shall not apply to any other transportation or sale of natural gas . . 15 U.S.C. § 717(b).

The Cities begin their argument by pointing out that both they and the applicants are direct sale customers. Therefore, the sales involved in the FPC’s order were not sales in interstate commerce of natural gas for resale. In short, the Cities argue that the transactions involved here are the “other” transportation or sale of natural gas to which the statute does not apply.

In FPC v. Louisiana Power and Light, 406 U.S. 621, 92 S.Ct. 1827, 32 L.Ed.2d 369 (1973), the Supreme Court delineated the limits of the Federal Power Commission’s jurisdiction. The Court held that the FPC had jurisdiction to promulgate curtailment plans which allocated gas among customers of interstate gas transportation companies. Such curtailment plans, similar to the one instituted by Florida Gas, established priorities among all customers, both direct sale and resale, who made purchases of interstate gas. The Court came to its conclusion by pointing out the need for a national regulatory approach in curtailment problems and cautioning that Congress wished to avoid a situation where state authorities could not practicably regulate' but where the Commission would be void of jurisdiction. Id. at 631, 92 S.Ct. 1827. See also, FPC v. Transcontinental Gas [997]*997Pipeline Corp., 365 U.S. 1, 19 — 20, 81 S.Ct. 435, 5 L.Ed.2d 377 (1961). The FPC’s jurisdiction to implement curtailment plans was grounded, according to the Court, in the grant of jurisdiction over the “transportation of natural gas in interstate commerce” in § 1(b) of the Act. We find Louisiana Power and Light Co. controlling in this case.

First, the national scope of the gas shortage problem is evident.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matter of Gardinier, Inc.
55 B.R. 601 (M.D. Florida, 1985)
State of North Carolina and North Carolina Utilities Commission v. Federal Energy Regulatory Commission, Brooklyn Union Gas Company, Philadelphia Gas Works, Gas Section, Georgia Municipal Ass'n, Washington Gas Light Company, Transcontinental Gas Pipe Line Corp., Piedmont Natural Gas Company, Inc., North Carolina Natural Gas Corp., Commissioners of Public Works of Greenwood, South Carolina, Consolidated Edison Company of New York, Inc., Carolina Pipeline Company Public Service Electric and Gas Company, Delmarva Power and Light Company, Pennsylvania Gas and Water Company, and North Penn Gas Company, Public Service Commission of the State of New York, Philadelphia Electric Company, American Textile Manufacturers Institute, Inc., Long Island Lighting Company, Owens-Illinois, Inc., Farmers Chemical Association, Inc., General Motors Corporation, South Carolina Public Service Commission, Columbia Gas Transmission Corp., Owens-Corning Fiberglass Corp., Eastern Shore Natural Gas Company, Cng Transmission Company, United Cities Gas Company, Intervenors. Piedmont Natural Gas Company, Inc. v. Federal Energy Regulatory Commission, Carolina Pipeline Company, Intervenors. Elizabethtown Gas Company v. Federal Energy Regulatory Commission, Delmarva Power & Light Company, Intervenors. Public Service Company of North Carolina, Inc. v. Federal Energy Regulatory Commission, Carolina Pipeline Co., Intervenors. Atlanta Gas Light Company v. Federal Energy Regulatory Commission, Piedmont Natural Gas Co., Inc., Intervenors. Consolidated Edison Company of New York, Inc. v. Federal Energy Regulatory Commission, Transcontinental Gas Pipe Line Corp., Intervenors. South Jersey Gas Company v. Federal Energy Regulatory Commission, Pennsylvania Gas and Water Company and North Penn Gas Company, Intervenors
584 F.2d 1003 (D.C. Circuit, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
526 F.2d 993, 13 P.U.R.4th 321, 1976 U.S. App. LEXIS 12928, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fort-pierce-utility-authority-v-federal-power-commission-ca5-1976.