Transwestern Pipeline Company v. Federal Energy Regulatory Commission

820 F.2d 733, 1987 U.S. App. LEXIS 8893
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 7, 1987
Docket85-4597, 86-4550
StatusPublished
Cited by16 cases

This text of 820 F.2d 733 (Transwestern Pipeline Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transwestern Pipeline Company v. Federal Energy Regulatory Commission, 820 F.2d 733, 1987 U.S. App. LEXIS 8893 (5th Cir. 1987).

Opinion

CLARK, Chief Judge:

Petitioner Transwestern Pipeline Company (Transwestern) seeks review of Opinion Nos. 238 and 238-A and other related orders of the Federal Energy Regulatory Commission (the Commission). See Transwestern Pipeline Company, Opinion No. 238, 32 FERC 1161,009 (1985), reh. denied, Opinion 238-A, 36 FERC 1161,175 (1986); see also Pacific Gas Transmission Company, 28 FERC 1161,217 (1984), reh. denied, 32 FERC 1161,001 (1985), reh. denied, 36 FERC It 61,176 (1986).

In generic Order No. 380, 1 the Commission eliminated interstate natural gas pipelines’ minimum commodity bills to the extent these provisions permitted the recovery of variable costs. The Commission reasoned that such variable-cost minimum bills inhibited competition without justification by forcing a pipeline’s customers to buy its gas rather than less costly gas from other sources. This order and its rationale were approved by the District of Columbia Circuit in Wisconsin Gas Co. v. Federal Energy Regulatory Commission (FERC), 770 F.2d 1144 (D.C.Cir.1985), cert. denied, — U.S.-, 106 S.Ct. 1968, 90 L.Ed.2d 653 (1986).

Questions of the lawfulness of the fixed-cost portion of minimum bills were left to be resolved in individual pipeline proceedings. This is such a proceeding. Transwestern petitions this court to review orders of the Commission which eliminated its fixed-cost minimum bills as applied to its two principal customers and terminated the Commission’s investigation into the minimum bill practices of other interstate pipelines supplying California. The Commission’s conclusion that Transwestern’s fixed-cost minimum bills were unjust and unreasonable because the practice constituted an unreasonable restraint of trade was based on substantial evidence. The remedy imposed was a proper exercise of the Commission’s authority under the Natural Gas Act (NGA) and was neither arbitrary nor capricious. It was within the Commission’s discretion to terminate its investigation of the other pipelines and determine the lawfulness of Transwestern’s fixed-cost minimum bills on the record before it. We affirm.

I. Background

A. Facts

Transwestern owns and operates an interstate natural gas pipeline subject to the jurisdiction of the Commission. It provides firm service to two partial requirements *736 customers, Southern California Gas Company (SoGal) and Northwest Central Pipeline Company (Northwest), which account for more than 99.5 percent of Transwestem’s gas sales. SoCal is a local distribution company which sells gas both for resale and for ultimate consumption within the State of California. Transwestem competes for natural gas sales to SoCal with other interstate pipelines and various other sources, including gas sold on the spot market. The largest interstate pipeline serving California and Transwestem’s primary competitor there is El Paso Natural Gas Company (El Paso). Northwest is an interstate pipeline which sells primarily to local distribution companies in the Midwest. The majority of its sales are to Kansas Power and Light Company serving the Kansas City, Missouri area.

The Commission first authorized Transwestem to provide service to SoCal’s affilliate, Pacific Lighting Gas Supply Company (Pacific), 2 in 1959, when it issued Transwestem a certificate of public convenience and necessity pursuant to § 7 of the NGA, 15 U.S.C. § 717f, to construct an interstate pipeline and sell up to 350 million cubic feet (MMcf) of gas per day. Additional certificates have been issued over the years to Transwestem to expand facilities and sell 750 MMcf per day to SoCal.

The 1959 certificate was conditioned upon Transwestern’s filing an initial rate schedule based on the Seaboard method 3 of cost classification, cost allocation, and rate design. Under this method, 50 percent of Transwestem’s fixed transmission costs and all its “as billed” fixed costs are treated as parts of the demand charge component of the rate and the remaining fixed transmission costs plus all fixed production costs and all its variable costs are classified as parts of the commodity charge. The demand charge is calculated based on the contract demand quantity, which in SoCal’s case is 750 MMcf of gas per day. This charge is paid by the customer regardless of how much gas is taken. The commodity charge calculation is based on the number of units of gas sold.

The schedule also included a 91 percent minimum annual commodity bill provision based on the annual contract quantity, which is calculated by multiplying SoCal’s contract demand quantity of 750 MMcf per day times 365 days a year. In effect, the minimum bills obligated SoCal to take gas pursuant to the rate schedule or pay Transwestern as if it had taken an average of 682.5 MMcf per day (91 percent of the contract demand quantity) or such lesser amount as Transwestern tendered. 4

In 1965, the Commission authorized Transwestern to sell 100 MMcf per day to Northwest’s predecessor, Cities Services Gas Company. This amount has since been increased to 250 MMcf per day. While the rates in the initial schedules for Northwest were developed using a method different from that used for SoCal, Transwestem’s rate design for both principal customers now uses the same method. At the time of Transwestern’s rate filing this was the Seaboard method. The rates applicable to Northwest also included a 90 percent minimum annual commodity bill.

There is a significant difference, however, between the minimum bills applicable to SoCal and those applicable to Northwest due to a “ratchet” provision in the Northwest agreements. The contract demand quantity which the Northwest contracts specified was to be used in calculating the annual contract quantity did not equal the 250 MMcf per day that Transwestern is authorized to deliver. Transwestem’s agreements with Northwest provided that if Transwestern was unable to deliver the daily contract demand quantity, the average daily quantity actually delivered would become the new contract demand quantity *737 in calculating the minimum bill for that year and for every year thereafter. During the 1970’s, Transwestern was in severe curtailment and could not deliver 250 MMcf per day to Northwest. Thus, the contract demand quantity used in calculating Northwest’s minimum bills was permanently reduced. The ratchet provision in Northwest’s minimum bill obligation eventually reduced its take-or-pay requirement to only 59 percent of the 250 MMcf Transwestern is authorized to deliver.

For years neither SoCal nor Northwest had any complaints about the effect of Transwestern’s minimum bills. In fact, if the two customers had any complaints it was due to curtailment of natural gas supply rather than any surplus which may have been forced upon them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Transwestern Pipeline Company v. Federal Energy Regulatory Commission, the Public Utilities Commission of the State of California, Process Gas Consumers Group, Southern California Gas Company, El Paso Natural Gas Company, Pacific Gas and Electric Company, Texas Eastern Transmission Corporation, the Kansas Power and Light Company, Southwest Gas Corporation, Williams Natural Gas Company, Intervenors. Transwestern Pipeline Company v. Federal Energy Regulatory Commission, Southern California Gas Company, Southwest Gas Corporation, Pacific Gas and Electric Company, Williams Natural Gas Company, Public Utilities Commission of the State of California, El Paso Natural Gas Company, Citizens Energy Corporation, Intervenors. Transwestern Pipeline Company v. Federal Energy Regulatory Commission, Williams Natural Gas Company, Southern California Gas Company, Public Utilities Commission of the State of California, Intervenors. Transwestern Pipeline Company v. Federal Energy Regulatory Commission, Kansas Power & Light Company, Natural Gas Clearinghouse, Inc., Williams Natural Gas Company, Southern California Gas Company, Public Utilities Commission of the State of California, Pacific Gas & Electric Company, Psi, Inc., Texas Eastern Transmission Corp., Southwest Gas Corp., Intervenors. Public Utilities Commission of the State of California v. Federal Energy Regulatory Commission, Kansas Power & Light Company, Natural Gas Clearinghouse, Inc., Williams Natural Gas Company, Southern California Gas Company, Pacific Gas & Electric Company, Psi, Inc., Southwest Gas Corp., Transwestern Pipeline Company, Intervenors. Kansas Power & Light Company v. Federal Energy Regulatory Commission, Natural Gas Clearinghouse, Inc., Williams Natural Gas Company, Pacific Gas & Electric Company, Public Utilities Commission of the State of California, Southern California Gas Company, Psi, Inc., Transwestern Pipeline Company, Intervenors
897 F.2d 570 (D.C. Circuit, 1990)
Tennessee Gas Pipeline Company v. Federal Energy Regulatory Commission, Orange and Rockland Utilities, Inc., the Berkshire Gas Co., the Peoples Gas Light & Coke Co., National Fuel Gas Supply Corporation, Columbia Gas Distribution Companies, the Tennessee Small General Service Customer Group, Northern Illinois Gas Co., Pennsylvania Gas and Water Co., Consolidated Gas Transmission Corp., the Inland Gas Co., Inc., the Cities of Clarksville Alabama-Tennessee Natural Gas Co., Consolidated Edison Company of New York, Inc., Shell Offshore Inc., Long Island Lighting Co., Process Gas Consumers Group, Conoco Inc., Columbia Gas Transmission Corporation, Texaco, Inc., Equitable Gas Co., Intervenors. Columbia Gas Transmission Corporation v. Federal Energy Regulatory Commission, Orange and Rockland Utilities, Inc., the Berkshire Gas Co., the Public Service Commission of the State of New York, Tennessee Gas Pipeline Co., Columbia Gas Distribution Companies, National Fuel Gas Supply Corporation, the Tennessee Small General Service Customer Group, Northern Illinois Gas Co., Pennsylvania Gas and Water Co., the Inland Gas Co., Inc., the Cities of Clarksville, Texaco Inc., Alabama-Tennessee Natural Gas Co., Conoco Inc., Shell Offshore Inc., Consolidated Gas Transmission Corp., Union Oil Co. Of California, Intervenors. Tennessee Gas Pipeline Company v. Federal Energy Regulatory Commission, Orange and Rockland Utilities, Inc., the Berkshire Gas Co., the Public Service Electric and Gas Co., the Peoples Gas Light and Coke Co., Equitable Gas Company, Long Island Lighting Company, Consolidated Edison Company of New York, Inc., Process Gas Consumers Group, Intervenors
871 F.2d 1099 (D.C. Circuit, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
820 F.2d 733, 1987 U.S. App. LEXIS 8893, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transwestern-pipeline-company-v-federal-energy-regulatory-commission-ca5-1987.