Colorado Interstate Gas Company v. Federal Energy Regulatory Commission

904 F.2d 1456, 1990 U.S. App. LEXIS 8700
CourtCourt of Appeals for the Tenth Circuit
DecidedMay 31, 1990
Docket88-1932
StatusPublished

This text of 904 F.2d 1456 (Colorado Interstate Gas Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colorado Interstate Gas Company v. Federal Energy Regulatory Commission, 904 F.2d 1456, 1990 U.S. App. LEXIS 8700 (10th Cir. 1990).

Opinion

904 F.2d 1456

COLORADO INTERSTATE GAS COMPANY, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
The Gates Rubber Company; Questar Pipeline Company; K N
Energy, Inc.; City of Colorado Springs; Natural
Gas Pipeline Company of America, Intervenors.

No. 88-1932.

United States Court of Appeals,
Tenth Circuit.

May 31, 1990.

William W. Brackett (Rebecca N. Noecker, Vice President and Asst. Gen. Counsel, Colorado Interstate Gas Co., Colorado Springs, Colo.; Daniel F. Collins, Sr. Vice President, Donald C. Shepler, Gen. Atty., and Kathrine L. Henry, Sr. Atty., Colorado Interstate Gas Co., Washington, D.C., with him on the briefs), Washington, D.C., for petitioner.

Robert H. Solomon, Atty. (Catherine C. Cook, Gen. Counsel, and Jerome M. Feit, Sol., with him on the briefs), Federal Energy Regulatory Com'n, Washington, D.C., for respondent.

Paul Korman (Paul W. Mallory, Paul E. Goldstein, and Joseph M. Wells, Lombard, Ill.; and J. Curtis Moffatt of Gardner, Carton & Douglas, Washington, D.C., with him on the briefs) Washington, D.C., for intervenor.

Before LOGAN and BRORBY, Circuit Judges, and BRATTON,* District Judge.

BRORBY, Circuit Judge.

Petitioner Colorado Interstate Gas Co. (CIG) appeals two final administrative orders of the Federal Energy Regulatory Commission (FERC, or Commission) relating to the rates CIG may charge for the sale and transportation of natural gas. Specifically, CIG asserts FERC erred in ordering the elimination of the fixed-cost minimum commodity bill provision in CIG's service agreement with Natural Gas Pipeline Co. of America (NGPL) and in rejecting CIG's proposed transportation rate for "on-system" service.1 We affirm the challenged portions of the FERC orders.

This proceeding originated when CIG, an interstate natural gas pipeline company subject to the Natural Gas Act, 15 U.S.C. Secs. 717-717w, filed with FERC a rate increase request under section 4 of the Act, 15 U.S.C. Sec. 717c. FERC ordered a hearing on the lawfulness of the proposed rates, which was conducted by a FERC administrative law judge (ALJ). The Commission subsequently affirmed in substantial part the ALJ's initial decision in Opinion No. 290, Colorado Interstate Gas Co., 41 FERC p 61,179 (1987), and then denied rehearing in Opinion No. 290-A, Colorado Interstate Gas Co., 43 FERC p 61,089 (1988). At issue in this appeal are FERC's holdings that the fixed-cost minimum commodity bill in CIG's service agreement with NGPL was anticompetitive and must be eliminated and that CIG's proposed on-system transportation rate is unjust and unreasonable.2

Under CIG's contract with NGPL, NGPL is entitled to buy a specified quantity of natural gas (currently 47 billion cubic feet (Bcf) per year) from CIG, and CIG must stand ready to deliver that quantity. The first issue in dispute is the contract's minimum bill provision, which requires NGPL to pay the commodity costs associated with ninety percent of its annual entitlement, even if it takes delivery of no gas from CIG.3 CIG recovers from NGPL approximately $15 million annually in production and gathering costs via the minimum bill and $9 million annually collected through a demand charge. FERC ruled that the minimum bill is anticompetitive, and thus unjust and unreasonable, and ordered that it be eliminated. This would limit to the demand charge alone CIG's guaranteed recovery from NGPL of fixed costs incurred on NGPL's behalf. FERC also ruled that CIG failed to bear its burden of proving the justness and reasonableness of its proposed rate increase for on-system transportation. The agency accordingly rejected CIG's request and ordered refunds for the period the proposed rate had been in effect.

We review these decisions pursuant to 15 U.S.C. Sec. 717r. The factual findings of FERC, if supported by substantial evidence, are conclusive. Section 717r(b); Colorado Interstate Gas Co. v. FERC, 791 F.2d 803, 807 (10th Cir.1986), cert. denied, 479 U.S. 1043, 107 S.Ct. 907, 93 L.Ed.2d 857 (1987) (CIG I ). Moreover, under the Administrative Procedure Act, a court can set aside an agency action only if it is "arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law." 5 U.S.C. Sec. 706(2)(A); cf. In re Permian Basin Area Rate Cases, 390 U.S. 747, 790, 88 S.Ct. 1344, 1372, 20 L.Ed.2d 312 (1968) (FERC's orders "may not be overturned if they produce 'no arbitrary result' "). The "substantial evidence" test has been equated with the "arbitrary and capricious" standard of review. East Tenn. Natural Gas Co. v. FERC, 863 F.2d 932, 937 (D.C.Cir.1988) (East Tennessee ) (quoting Maryland People's Counsel v. FERC, 761 F.2d 768, 774 (D.C.Cir.1985)).

The burden of proving that a rate change is "just and reasonable," 15 U.S.C. Secs. 717c-717d, is on the party proposing the change. CIG I, 791 F.2d at 806; East Tennessee, 863 F.2d at 937. When FERC initiates review of an existing rate structure, it bears the burden of proving that the existing rates are unjust and unreasonable and that those it orders in replacement are just and reasonable. 15 U.S.C. Sec. 717d(a); East Tennessee, 863 F.2d at 937. Once it makes these prima facie showings, the burden shifts to the opposing party to rebut them. E.g., Transwestern Pipeline Co. v. FERC, 820 F.2d 733, 746 (5th Cir.1987), cert. denied 484 U.S. 1005, 108 S.Ct. 696, 98 L.Ed.2d 648 (1988).

We find it unnecessary to detail much of the background of this case--the purposes of the Natural Gas Act, the procedural history of this action, and the nature and workings of CIG's rate structure and the elements thereof--as these exercises have been performed adequately by this court or others on various occasions. See, e.g., CIG I, 791 F.2d at 805 (describing the early procedural history of this case and CIG's minimum bill provision); Associated Gas Distributors v. FERC, 824 F.2d 981, 995-96 (D.C.Cir.1987), cert. denied 485 U.S. 1006, 108 S.Ct. 1468, 99 L.Ed.2d 698 (1988) (describing purposes of the Act and the evolving regulatory climate); Wisconsin Gas Co. v. FERC, 770 F.2d 1144, 1149-53 (D.C.Cir.1985), cert. denied, 476 U.S. 1114, 106 S.Ct. 1968, 90 L.Ed.2d 653 (1986) (discussing the operation of minimum bills generally, how FERC policy with respect to minimum bills has evolved in response to changes in the gas industry, and FERC's statutory authority); Mississippi River Transmission Corp. v. FERC, 759 F.2d 945, 947-50 (D.C.1985) (discussing minimum bills). Thus we proceed with our discussion of the issues.

I. The Minimum Bill

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
904 F.2d 1456, 1990 U.S. App. LEXIS 8700, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colorado-interstate-gas-company-v-federal-energy-regulatory-commission-ca10-1990.