American Gas Ass'n v. Federal Energy Regulatory Commission

888 F.2d 136, 281 U.S. App. D.C. 123, 109 Oil & Gas Rep. 384, 1989 U.S. App. LEXIS 15774
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 16, 1989
DocketNos. 87-1588, 87-1336 to 87-1346, 87-1595, 87-1604, 87-1613, 87-1614, 87-1638, 87-1649, 87-1650, 87-1652, 87-1655, 87-1667, 87-1678, 87-1710, 87-1732, 87-1763, 87-1766 to 87-1768, 87-1772 and 87-1773
StatusPublished
Cited by29 cases

This text of 888 F.2d 136 (American Gas Ass'n v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Gas Ass'n v. Federal Energy Regulatory Commission, 888 F.2d 136, 281 U.S. App. D.C. 123, 109 Oil & Gas Rep. 384, 1989 U.S. App. LEXIS 15774 (D.C. Cir. 1989).

Opinion

Opinion for the Court filed by Circuit Judge D.H. GINSBURG.

D.H. GINSBURG, Circuit Judge:

The Federal Energy Regulatory Commission embarked in the early 1980s on an ambitious program to restructure the natural gas industry along lines more competitive than it had traditionally followed. One of the major components of this program, the encouragement of natural gas pipelines to adopt an “open access” transportation policy, failed to pass muster when we reviewed it, because the Commission failed to show either that it had authority to impose, or that it could rationalize the imposition of, a few of its components. Associated Gas Distributors v. FERC, 824 F.2d 981 (1987) (AGD). Because these components were inseparable from the whole, we vacat[129]*129ed and remanded the Commission’s Order No. 436 for the agency to cure the defects we had identified. The Commission promptly, in Order No. 500, issued an “interim rule,” and undertook to issue a final rule when it had collected and analyzed certain information that it deemed essential.

Numerous natural gas pipeline companies, producers, local distribution companies (LDCs), and industrial end users petitioned for review of the interim rule, and three States (Texas Railroad Commission, Kansas Corporation Commission, and the State of Louisiana) have intervened, in this court. We now hold that the interim rule does not comply with the mandate in AGD. Therefore, we retain jurisdiction of this matter and remand the record for the Commission to issue a final rule within 60 days.

I. Background

The background against which the Commission adopted its open-access transportation policy is described in detail in this court’s opinion in AGD. Therefore, we shall only briefly summarize here those elements relevant to the petitions to review now before us.

A. From Order No. 436 to AGD.

On October 9, 1985, the Federal Energy Regulatory Commission issued Order No. 436, 50 Fed.Reg. 42,408 (1985) (codified at scattered sections of 18 C.F.R.), in an effort to promote competition in the sale of gas to consumers. The Commission had concluded that, notwithstanding increasing competition at the wellhead, pipelines continued to have market power in gas transportation; that they generally refused to transport gas for producers with which they competed in their role as gas merchants; and that this discrimination prevented customers from receiving gas at prevailing market prices. 824 F.2d at 996. It therefore sought to “unbundle” the merchant and transportation roles of the pipelines.

The central feature of Order No. 436 required “a pipeline seeking] to take advantage of ‘blanket certification’ of transportation (i.e., a certificate authorizing transportation services generically and thus obviating the need for unwieldy individual certification), [to] commit itself to provide transportation on a nondiscriminatory basis (and thus become an “open-access” pipeline).” Id. As we described in AGD, the Order also sought to reduce the obligations of LDCs to purchase gas from pipelines:

Any open-access pipeline, by applying for certification, agrees to allow its LDC customers to convert their “contract demand” (“CD”) (i.e., contract commitment to purchase gas) from an obligation to purchase gas to an obligation to use (or pay for) transportation services. The point of the option is to make open access a reality for the pipeline’s LDC customers despite long-term contractual service arrangements previously certified by the Commission. The Order also requires an open-access pipeline to give its LDC customers the option to reduce contract demand.

Id. The Order did not, however, relieve pipelines from the burden of their take-or-pay contracts with producers, although those contracts generally contain price levels “well above current competitive levels.” Id.

In AGD, we vacated Order No. 436 in its entirety, despite approving much of its substance, because of a few problems that could not be isolated from the overall balance struck by the agency:

The CD adjustment conditions suffer from a want of both legal authority and reasoned decisionmaking. The problem with the legal authority stems from the Commission’s misplaced reliance on § 7(e); the lack of reasoned decisionmaking lies in its failure to trace the path that led it from the statutory authority and the facts to its adoption of the CD reduction option. On remand, FERC is free to attempt to remedy these problems. If, however, it elects to go forward with the Order without CD conversion, it must, of course, explain why it feels that such a condition is no longer necessary.
[130]*130The Commission’s decision not to take any affirmative action to solve the problems posed by the uneconomic producer-pipeline contracts also fails to meet the standards of reasoned decisionmaking. On remand, FERC must more convincingly address the magnitude of the problem and the adverse consequences likely to result from the nondiscriminatory access and CD adjustment conditions. It is not our place to say whether FERC should take measures to shift those losses from where they now lie; we ask only that it explain its course.

Id. at 1044.

In particular, we found the Commission’s justifications for rejecting two proposed solutions to the take-or-pay problem insufficient. First, the Commission had decided not to take direct action by using its power under § 5 of the Natural Gas Act, 15 U.S.C. § 717d, to set aside jurisdictional contracts with excessive take-or-pay clauses. The Commission believed that such action would be “inequitable and inefficacious” because it would address only jurisdictional contracts. 824 F.2d at 1027. We were unconvinced by this argument because of FERC’s failure to indicate “the extent to which contracts for jurisdictional gas account for the basic economic problem.” Id. at 1028. We therefore ordered the Commission to “reassess its refusal to act under § 5.” Id. We made it perfectly clear, however, that we were rejecting only the Commission’s reasoning, not requiring it to act under § 5. Id. at 1028 & n. 31.

We also addressed the Commission’s refusal to condition producers’ right of access to pipeline transportation services on their helping to solve the take-or-pay crisis, and concluded that the Commission had failed to explain why pipelines should have to provide access to producers that refused to renegotiate unreasonable contracts. We required the Commission either to make the case against, or to consider implementing, some form of access-conditioning with whatever “procedural and substantive limits” might be necessary in order to prevent pipelines from discriminating unduly against some producers and customers. Id. at 1028-29. We repeated, however, that we did “not require that FERC reach any particular conclusion; we merely’ mandate[d] that it reach its conclusion by reasoned decisionmaking.” Id. at 1030.

We concluded AGD by explaining why we were vacating the entire Order:

The parts of Order No. 436 are interdependent. The nondiscriminatory access and CD adjustment provisions aggravate the pipelines’ jeopardy from take-or-pay liability.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Inter Nat Gas Assn v. FERC
D.C. Circuit, 2002
Caterpillar, Inc. v. National Labor Relations Board
138 F.3d 1105 (Seventh Circuit, 1998)
General Motors Corp. v. Public Service Commission
589 A.2d 982 (Court of Special Appeals of Maryland, 1991)
City of Chanute, Kan. v. Williams Natural Gas Co.
743 F. Supp. 1437 (D. Kansas, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
888 F.2d 136, 281 U.S. App. D.C. 123, 109 Oil & Gas Rep. 384, 1989 U.S. App. LEXIS 15774, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-gas-assn-v-federal-energy-regulatory-commission-cadc-1989.