Tennessee Gas Pipeline Company v. Federal Energy Regulatory Commission, United Gas Pipe Line Company, Intervenors

969 F.2d 1141, 297 U.S. App. D.C. 141, 133 P.U.R.4th 608, 1992 U.S. App. LEXIS 15700
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 14, 1992
Docket90-1618
StatusPublished
Cited by34 cases

This text of 969 F.2d 1141 (Tennessee Gas Pipeline Company v. Federal Energy Regulatory Commission, United Gas Pipe Line Company, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Gas Pipeline Company v. Federal Energy Regulatory Commission, United Gas Pipe Line Company, Intervenors, 969 F.2d 1141, 297 U.S. App. D.C. 141, 133 P.U.R.4th 608, 1992 U.S. App. LEXIS 15700 (D.C. Cir. 1992).

Opinion

Opinion for the court filed by Circuit Judge BUCKLEY.

BUCKLEY, Circuit Judge:

This case concerns an interim rule issued by the Federal Energy Regulatory Commission requiring advance notice and disclosure by natural gas pipeline companies of the construction of new facilities or the replacement of existing ones. The Com *1143 mission promulgated the interim rule without the notice and opportunity for comment required by the Administrative Procedure Act. It claimed that the rule fell within the “good cause” exception of the Act because (1) it is an interim measure, and (2) it is needed in order to avoid the environmental damage that might otherwise occur if pipelines accelerated construction and replacement activities to avoid the requirements of a final rule. Despite the minimal reach of the interim rule, we conclude that the Commission failed to provide a sufficient basis for invoking the good cause exception.

I. Background

Section 2.55(b) of the Federal Energy Regulatory Commission’s regulations permits a natural gas pipeline company to replace existing facilities without prior authorization pursuant to section 7(c) of the Natural Gas Act, 15 U.S.C. § 717f(c) (1988). See 18 C.F.R. § 2.55(b) (1991). Section 284.3(c) of the regulations provides automatic authorization for the construction of facilities to be used for the transportation of natural gas pursuant to section 311 of the Natural Gas Policy Act of 1978, 15 U.S.C. § 3371 (1988). See 18 C.F.R. § 284.-3(c) (1991).

On August 2, 1990, the Commission issued an interim rule as well as a Notice of Proposed Rulemaking (“NOPR”) for a final rule. See Interim Revisions to Regulations Governing Construction of Facilities Pursuant to NGPA Section 311 and Replacement of Facilities, 55 Fed.Reg. 33,011 (1990). The interim rule requires interstate natural gas pipelines to provide the Commission with thirty days’ advance notice of any replacement of existing facilities under section 2.55(b) and of the construction of new facilities pursuant to section 284.3(c). In the case of new construction, the rule requires that the notification include: (1) a brief description of the facilities; (2) evidence of compliance with the environmental conditions of 18 C.F.R. § 157.206(d); (3) a map showing the location of the facilities; and (4) a description of the procedures to be used for erosion control, revegetation and maintenance, and stream and wetland crossings. See 55 Fed. Reg. 33,013-14. When existing facilities are to be replaced, the rule requires the notification to include items (1), (3), and (4) above. Id. at 33,014. The agency estimated that compilation of this information would take approximately four hours per notice. Id. at 33,013.

The Commission explained that it was issuing the interim rule without notice and comment or prepublication but was instead invoking the good cause exception of the APA, 5 U.S.C. § 553(b)(B) (1988), which permits an agency to dispense with those requirements under certain circumstances. See 55 Fed.Reg. 33,012. In support of this decision, the Commission emphasized the interim nature of the rule, the fact that the notification requirements were not unduly burdensome, and the public interest in oversight during the period before a final rule could be issued. Id. at 33,012-13. The agency was particularly

concerned that construction activities may take place during the period of time between issuance of the NOPR and adoption of a final rule without the opportunity for Commission intervention. Once the NOPR is issued, pipelines may respond to the proposed changes in the regulations by commencing construction in order to avoid either the inherent uncertainty associated with proposed changes to existing regulations or application of the proposed changes, if adopted, to a particular project.

Id. at 33,014. To ensure that the establishment of a procedure to review construction and replacement activities for potential environmental damage would not itself be the source of such damage, the Commission concluded that “it is imperative that the opportunity for some form of oversight on an interim basis be provided immediately.” Id.

On August 17,1990, petitioner Tennessee Gas Pipeline Company moved for clarification of the interim rule. Tennessee asked whether the description of facilities to be replaced could consist of a general description of the segment of pipeline that is scheduled for inspection, as the specific *1144 facilities requiring replacement can only be identified in the course of field testing. At the same time, Tennessee argued that the Commission’s finding of good cause was flawed, as the Commission had focused on the interim nature of the measure and had otherwise failed to justify its invocation of the exception. Before any agency could rule on the motion, Tennessee moved for rehearing, again claiming that good cause had not been established. Tennessee further argued that the interim rule, if not properly interpreted, would conflict with Department of Transportation regulations requiring immediate replacement of damaged pipe that creates a safety hazard. See 49 C.F.R. §§ 192.465 and 192.703 (1991).

On September 13, 1990, the Commission issued an Order Addressing Requests for Clarification, 52 FERC ¶ 61,252 (1990). It agreed that the interim rule would be satisfied by the identification of the portions of pipelines scheduled for inspection and a listing of the repairs that might be required. Id. at 61,876. The Commission also made it clear that the rule did not conflict with the Department of Transportation’s regulations, as the Commission’s own regulations take precedence over the interim rule and allow for immediate replacement of facilities that constitute a safety hazard, subject to a subsequent reporting requirement. Id. at 61,877 (citing 18 C.F.R. § 284.262(a)(l)(iii)).

In a later Order Denying Requests for Rehearing and Granting Requests for Clarification, 53 FERC ¶ 61,140 (1990) (“Order Denying Requests”), the agency rejected Tennessee’s challenge to the immediate application of the interim rule.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jorge Lujan v. FMCSA
D.C. Circuit, 2025
Tri-County Telephone Association, Inc. v. FCC
999 F.3d 714 (D.C. Circuit, 2021)
Stellar It v. Scalia
District of Columbia, 2020
I.A. v. Barr
District of Columbia, 2020
Nat'l Venture Capital Ass'n v. Duke
291 F. Supp. 3d 5 (D.C. Circuit, 2017)
United States v. Anthony Ross
848 F.3d 1129 (D.C. Circuit, 2017)
United States v. Cotton
District of Columbia, 2011
United States v. Cain
583 F.3d 408 (Sixth Circuit, 2009)
United States v. Marcus Cain
Sixth Circuit, 2009
United States v. Gould
568 F.3d 459 (Fourth Circuit, 2009)
Parkdale International, Ltd. v. United States
508 F. Supp. 2d 1338 (Court of International Trade, 2007)
Chamber Cmerc USA v. SEC
443 F.3d 890 (D.C. Circuit, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
969 F.2d 1141, 297 U.S. App. D.C. 141, 133 P.U.R.4th 608, 1992 U.S. App. LEXIS 15700, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-gas-pipeline-company-v-federal-energy-regulatory-commission-cadc-1992.