Tennessee Gas Pipeline Co. v. Federal Energy Regulatory Commission

972 F.2d 376, 297 U.S. App. D.C. 323
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 14, 1992
DocketNos. 89-1094, 89-1257, 89-1455 and 89-1621
StatusPublished
Cited by1 cases

This text of 972 F.2d 376 (Tennessee Gas Pipeline Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Gas Pipeline Co. v. Federal Energy Regulatory Commission, 972 F.2d 376, 297 U.S. App. D.C. 323 (D.C. Cir. 1992).

Opinion

Opinion for the Court filed by Circuit Judge D.H. GINSBURG.

D.H. GINSBURG, Circuit Judge:

The petitioner (Tennessee), a purchaser, transporter, and seller of natural gas, and a purchaser of transportation services, seeks review of six orders of the Federal Energy Regulatory Commission, three of which promulgate rules and regulations under the Natural Gas Act (NGA) and section 5 of the Outer Continental Shelf Lands Act (OCSLA), and three of which apply those rules to the petitioner. We deny all of the petitions except insofar as the orders they challenge regulate onshore activities, in which regard we remand this matter to the agency.

I. The Orders

Section 5 of the OCSLA provides that every “pipeline on or across the outer Continental Shelf of oil or gas ... must provide open and nondiscriminatory access to both owner and nonowner shippers.” 43 U.S.C. § 1334(f)(1) & (1)(A). In Order No. 491 the FERC promulgated an interpretive rule in which it spelled out the meaning of § 5 as follows:

[I]f all of an OCS pipeline’s capacity is under firm transportation contracts and if the pipeline received another request for firm transportation service, the pipeline would be required to allocate capacity on a pro rata basis in order to provide the requested service. Similarly, if a pipeline receives a request for interruptible transportation service, the pipeline would be required to reallocate its interruptible capacity on a pro rata basis in order to provide the requested service. Of course, an interruptible shipper cannot receive priority over a firm shipper.

43 FERC ¶ 61,006, at 61,032 (1988).

The Commission promulgated this interpretation in response to complaints it had received from shippers “stating that they have been unable to secure the transportation of gas from the OCS to onshore destinations.” Id. at 61,031. Because the complaints all concerned interstate natural gas pipelines subject to the NGA, the Commission concluded that “although the OCSLA may cover facilities outside the scope of the NGA ... at this time, it is unnecessary to extend its interpretation of section 5 of the OCSLA to govern those facilities.” Id.

In Order No. 509 the Commission reversed itself to the extent of making the proration scheme of Order No. 491 optional with each individual OCS pipeline. 53 Fed. Reg. 50,925, 50,929-30 (1988). The Commission newly required, however, that every OCS pipeline accept a blanket transportation certificate. This had the effect of (1) enabling an incumbent shipper voluntarily to relinquish its right to firm transportation capacity if another shipper requests capacity and agrees to assume all of the obligations of the incumbent shipper’s firm service agreement, and (2) subjecting OCS pipelines to the requirement of filing a transportation rate schedule pursuant to Subpart A of Part 284 of the Commission’s regulations. Further, because new shippers would then be subject to Part 284 rates while existing shippers on the same pipeline would be subject to Part 154 (individually certificated) rates, which the Commission viewed as an unjust discrimination in the prices paid by similarly situated customers, it also provided “under section 5 of the NGA” that the Part 284 rates would be applicable, once approved, “to all transportation service performed by the OCS pipeline.” Id. at 50,930 (emphasis in original). For these purposes, Order No. 509 defined an OCS pipeline so as to include all “facilities that fall within the scope of the Commission’s jurisdiction under section 7 of the NGA, and that are used or necessary to transport OCS gas off of the OCS to the first point of interconnection with some other entity” on the shoreward side of the OCS. Id. at 50,932. This definition made the regime of Order No. 509 applicable to some onshore pipeline facilities but inapplicable to all offshore gathering facilities, which link producing fields to interstate pipelines on the OCS.

On rehearing, the Commission issued a third Order, No. 509-A, which seemed further to relax the regime applicable to the OCS, this time by providing that an OCS pipeline might be able to go on charging individually certificated Part 154 rates instead of the regulated Part 284 rates that [327]*327are normally required under a blanket certificate. Although the FERC “continue[d] to believe that the existing rates are unjust, unreasonable, and unduly discriminatory, because they can result in situations wherein two shippers would be paying different rates for the same service,” it decided to proceed “on a case specific basis.” 54 Fed.Reg. 8301, 8305 (1989). Each OCS pipeline was invited to file a statement “which explains why [it] believes that continued use of [Part 154 rates] would not be unjust, unreasonable or discriminatory.” Id. The Commission also refused to extend the application of the OCS rules beyond the first point of receipt located off the OCS {i.e., onshore), stating that “any such extension ... would significantly exceed [its] underlying statutory authority under the OCSLA.” Id. at 8307.

Against this backdrop of general rule-making, the petitioner sought clarification and relief specific to its situation. As a result, the FERC issued three further orders addressing the petitioner’s requests, more often than not to deny them. The March 1989 Order rejected the petitioner’s request to limit the scope of Orders 509 and 509-A to facilities that neither receive nor deliver gas onshore. The Commission held that those Orders apply from the OCS to “the first point of interconnection with another entity that might receive gas from the OCS pipeline, regardless of whether the actual delivery- point is beyond this first point of interconnection.” 46 FERC ¶ 61,-413, at 62,306 (1989).

The May 1989 Order responded to the petitioner’s claim that an unworkable situation would arise

where an existing shipper voluntarily relinquishes capacity, [because] the replacement shipper would acquire service only from the receipt point on the OCS to the first point of interconnection off the OCS to the delivery point specified in its transportation agreement with Tennessee.

Tennessee contended that

the replacement shipper would have no delivery point and the existing shipper would have no receipt point, and thus that the relinquishment of capacity would result in both the existing and the replacement shippers having capacity that they could not use.

47 FERC ¶ 61,299, at 62,075 (1989).

The Commission clarified that it was requiring the replacement shipper to assume all of the incumbent shipper’s obligations, including those onshore, and reiterated its pledge (first made in Order No. 509-A) that it would “endeavor to process any necessary abandonment applications expeditiously.” Id. at 62,076. This Order also declared that the petitioner’s generally applicable (i.e., open access) transportation rates “would apply to new and replacement shippers on the OCS ... [and] to transportation onshore — after the first point of interconnection.” Id.

Finally, the July 1989 Order responded to Tennessee’s request for clarification.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
972 F.2d 376, 297 U.S. App. D.C. 323, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-gas-pipeline-co-v-federal-energy-regulatory-commission-cadc-1992.