Placid Oil Company v. Federal Energy Regulatory Commission

875 F.2d 487, 1989 U.S. App. LEXIS 8625
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 16, 1989
Docket88-4349
StatusPublished
Cited by1 cases

This text of 875 F.2d 487 (Placid Oil Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Placid Oil Company v. Federal Energy Regulatory Commission, 875 F.2d 487, 1989 U.S. App. LEXIS 8625 (5th Cir. 1989).

Opinion

*488 PER CURIAM:

The Federal Energy Regulatory Commission (FERC) issued an order requiring Placid Oil Company (Placid) to make refunds to a pipeline customer on the grounds that Placid had charged in excess of the maximum lawful price for the sale of certain natural gas. On petition for review of that order, we affirm in part and vacate in part.

I.

Placid has a 50% interest in an onshore natural gas well located in Louisiana. The drilling of the well began on September 30, 1972. By December 20, 1972, the well had been drilled to a depth of 18,912 feet. A drilling tool lodged in the hole at this depth, and “fishing” operations to remove the tool took place from December 20, 1972 to January 11, 1973. The fishing operations were unsuccessful. In order to reach the desired depth it became necessary to get around the tool. A secondary drilling operation was commenced on January 17, 1973. It utilized the existing well bore to a depth of 17,237 feet. At that point the well was angled past the blockage and completed to a depth of 17,850 feet which resulted in the production of a total of 265,295 Mcf of natural gas from the “Z-2” sand at the 17,569-17,650 foot level. Placid did not take its 50% share of this gas because its pipeline purchaser, Tennessee Gas Pipeline Company (Tennessee Gas), had not yet made a connection to the well. Instead, Placid retained a right to take its share from other production at a later date.

In January 1977 the well was “recomplet-ed” in the original well bore between 17,-169 and 17,180 feet. The hole below was sealed off at 17,194 feet. All of this activity was above the point of departure for the secondary drilling located at a depth of 17,237 feet. The recompletion resulted in the production of a total of 8,489,345 Mcf of natural gas from the “Lower X” sand at the 17,169-180 foot level.

Tennessee Gas connected its pipeline to the well in May 1977. Placid took its 50% share of the production from the Lower X sand, plus an additional 132,648 Mcf attributable to Placid’s share in the production from the Z-2 sand, for a total of 4,373,676 Mcf of gas. Placid sold this gas to Tennessee Gas based on the 1973-74 biennium rate of 93 cents per Mcf established in Opinion No. 770, 56 F.P.C. 509, modified, Opinion No. 770-A, 56 F.P.C. 2698 (1976); aff'd, American Public Gas Ass’n v. Federal Power Comm’n, 567 F.2d 1016 (D.C.Cir.1977), cer t. denied, 435 U.S. 907, 98 S.Ct. 1456, 1457, 55 L.Ed.2d 499 (1978).

FERC found that all gas sold by Placid was only entitled to the recompletion rate of 52 cents per Mcf provided in 18 C.F.R. § 2.56a(a)(5) (1988), and issued an order directing Placid to refund the overcharges to Tennessee Gas. Placid Oil Co., 37 F.E.R. C. ¶ 61,248 (1986). FERC denied Placid’s request to waive the refund on equitable grounds, and denied rehearing. Placid petitions for review of FERC’s order.

II.

Under the Natural Gas Act FERC has the duty to fix just and reasonable rates for sales in interstate commerce of natural gas for resale. See 15 U.S.C. §§ 717d(a), 717(b). Pursuant to this duty, FERC has established a cost-based vintage system to set prices for natural gas. The vintage price is based on the average cost of gas production during a particular period. Under this vintage system the date the drilling of a natural gas well begins (the spud date) is normally the basis for determining the price of gas produced from that well. See Shell Oil Co. v. FERC, 707 F.2d 230, 232 (5th Cir.1983). Gas produced from a recompletion of a well is generally entitled to the price governed by the spud date. See Imperial Oil Co., 58 F.P.C. 680, 685 (1977); Opinion No. 770-A, 56 F.P.C. at 2792. Gas produced from a secondary or “sidetrack” operation, however, may be entitled to the price applicable at the time the sidetrack operation is commenced. Shell Oil, 707 F.2d 230, on remand, 24 F.E.R.C. ¶ 61,359 (1983). Producers desiring a higher vintage rate for gas produced from onshore sidetrack operations in the vicinity of the initial well must make a rate filing pursuant to 18 C.F.R. § 2.56a(p) and justify *489 the need for the sidetrack operation. 24 F.E.R.C. ¶ 61,359.

The 1973 Secondary Drilling

FERC found that the gas attributable to the Z-2 sand production did not qualify for the 1973-74 biennium rate because the secondary drilling in January 1973 did not meet the definition of “sidetracking.” FERC explained the sidetracking technique in Imperial Oil Co., 58 F.P.C. 680, 685 n. 7 (1977):

[Sidetracking] is a secondary operation. After the hole has been drilled and casing has been set, it may become necessary, for various reasons, to drill a second hole in the vicinity of the initial hole. Rather than starting at the surface with a new hole and setting new casing strings all the way, it may be less expensive to utilize a portion of the casing in the original cased hole. To do this, a milling tool is used to grind out a “window” through the side of the casing at some selected depth. After this is done, a whipstock is utilized to direct a drilling bit out of the window at some desired angle into previously undrilled earth strata. From this directional start a new hole is drilled to the desired formation depth and casing is set in the new hole and tied back to the older casing.

The 1973 secondary drilling involved here falls within Imperial’s, definition of sidetracking. The initial drilling had stopped for more than three weeks while fishing operations were performed to remove lodged tools. Because the fishing operations were unsuccessful it became impossible to use the well to reach the desired depth. Rather than begin drilling a new well at the surface, part of the existing well was used with directional drilling to reach the depth intended. A portion of the original casing in the well bore was removed and new casing and tubing were put in to accommodate the secondary drilling. The secondary well left the original bore at 17,237 feet, almost 1700 feet above where the tools were stuck. The cost of the secondary drilling was $320,618. This operation is clearly within FERC’s definition of sidetracking set forth in Imperial Oil. It is also encompassed by a statement we made in commenting on the Imperial Oil definition: “A sidetracking operation thus results in a well that is partly old and partly new. Costs are incurred both when the well is initially drilled and later when the sidetracking operation occurs.” Shell Oil, 707 F.2d at 233. Indeed, in its order in Placid’s case FERC repeatedly referred to the 1973 secondary drilling as a sidetracking.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PetroQuest Energy, LLC v. Banks
208 So. 3d 543 (Louisiana Court of Appeal, 2016)
Petroquest Energy, LLC v. Sam L. Banks
Louisiana Court of Appeal, 2016

Cite This Page — Counsel Stack

Bluebook (online)
875 F.2d 487, 1989 U.S. App. LEXIS 8625, Counsel Stack Legal Research, https://law.counselstack.com/opinion/placid-oil-company-v-federal-energy-regulatory-commission-ca5-1989.