Akhtar v. JDN Properties at Florham Park, L.L.C.

109 A.3d 228, 439 N.J. Super. 391, 2015 N.J. Super. LEXIS 25
CourtNew Jersey Superior Court Appellate Division
DecidedFebruary 24, 2015
StatusPublished
Cited by31 cases

This text of 109 A.3d 228 (Akhtar v. JDN Properties at Florham Park, L.L.C.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Akhtar v. JDN Properties at Florham Park, L.L.C., 109 A.3d 228, 439 N.J. Super. 391, 2015 N.J. Super. LEXIS 25 (N.J. Ct. App. 2015).

Opinion

The opinion of the court was delivered by

KOBLITZ, J.A.D.

Plaintiffs, Dr. Humayun Akhtar and his wife, Yosaria, appeal from a jury verdict dismissing their malpractice claims against defendant,1 engineering firm Casey & Keller, Inc. A judge initially awarded plaintiffs summary judgment on liability, but a second judge reconsidered and vacated the grant of summary judgment. A third judge held a full trial, which yielded a no-cause jury verdict. Plaintiffs maintain that they were entitled to summary judgment as a matter of law, or at least a new trial, because their expert’s opinion was unrebutted by defendant’s expert. In light of [394]*394plaintiffs’ burden of proof and the conflicting evidence as to the factual predicates for their expert’s opinion, we affirm.

I

As developer JDN Properties at Florham Park, L.L.C., (JDN FP), was planning a ten-lot project on a set of steep properties, its manager, Randy DeLuca, engaged engineer Michael Lanzafama’s firm, Casey & Keller, Inc. Lanzafama’s firm was to perform title, topographic, and utilities surveys, prepare designs for a road and other infrastructure for the project, and submit those documents for approval from the appropriate government agencies. In the course of that work, Lanzafama drafted an individual lot grading plan for what would become plaintiffs’ property, depicting two semi-circular Allan Block retaining walls and incorporating the manufacturer’s specifications. The grading plan was filed with the municipality in conjunction with the property’s site plan and approved by borough engineer Robert Kirkpatrick in April 2005.

Plaintiffs contracted with JDN FP to purchase the lot and have a home constructed, with certain modifications, such as one to accommodate a full walk-out basement, which ultimately drove the price up to just over $1.56 million. Akhtar, who frequently visited the site during construction, testified at trial that shortly before the closing, he was surprised to find that the builder had deviated from Lanzafama’s design by constructing a much longer, higher retaining wall along the eastern side of the property than originally designed. He acknowledged, however, that he had requested that the wall be raised by at least one foot to accommodate a backyard pool, and DeLuca introduced testimony suggesting that plaintiffs’ requests for modifications required a more level backyard and consequently, expansion of the retaining wall. Lanzafama claimed at trial that his personnel had no knowledge of the modification until their site visit for a final survey, but confirmed that his design provided sufficient information for building the wall ultimately constructed.

[395]*395Nonetheless, the modification was undertaken without prior municipal approval, and JDN FP had apparently never obtained a permit for the wall in the first place. On one of his site visits, borough engineer Kirkpatrick noticed the change, along with other unauthorized work. Because the municipality had never inspected the retaining wall’s construction, he requested a letter assuring that the wall had been built according to the manufacturer’s specifications. Lanzafama wrote the letter at DeLuca’s request.

At trial Lanzafama testified that, before doing so, he discussed with DeLuea the methods that had been used to construct the wall and inspected the wall himself, albeit after its completion. He explained that while investigating, he observed geogrid fabric protruding from the wall at various points, confirming that the three appropriately spaced layers of geogrid had been placed. He also observed drainage pipes extending from the wall, suggesting that the required toe drain had been installed at the crushed stone’s base to evacuate any water that might build up within or alongside the wall. His field crew took measurements of the wall to confirm its location and elevation, and he himself examined soil immediately behind the wall to confirm its stability. He further reviewed photographs his crew had taken on site visits, which he believed showed that the blocks, gravel, and geogrid were appropriately placed and that the correct compaction tools had been used. Moreover, he recalled his own prior site visits at various stages of the wall’s construction, albeit undertaken for other reasons, where he nonetheless saw the wall being built with appropriate materials and equipment. He concluded from those observations that the wall had been appropriately built and felt comfortable writing the letter.

Borough building inspector Stephen Jones testified at deposition that the letter had not specifically been requested in connection with the review of any application for a certificate of occupancy. It was, in any event, submitted in connection with such an application. The borough issued a temporary certificate of occupancy for the property on June 1, 2006. Pursuant to the contract, [396]*396JDN FP then remitted a “time of the essence letter” to plaintiffs and set a closing date for June 9. Akhtar performed a walk-through of the property prior to closing and requested repair of certain defects. Plaintiffs first became aware of serious problems with the property when they learned from a plumber not long after closing that the house was “sliding.” They have never moved in.

Subsequent investigations by engineering firm LAN, hired by JDN FP, revealed cracking in the foundation under a substantial portion of the eastern side of the house due to improperly compacted soil. Plaintiffs, meanwhile, retained Henry Naughton, an engineering consultant, who concluded that the cracks in the foundation were attributable to the soil’s poor bearing capacity. He further concluded that the eastern retaining wall, which Lanzafama had vouched for, had questionable long term stability that, because of transport of soil through the wall, would undermine structures supported on the soil. He testified that failure of the retaining wall was one of the causes of the movement of the house. LAN recommended installing helical piles to bolster the foundation and arrest its settlement, but plaintiffs and JDN FP were never able to agree on an appropriate remedy.

At trial, plaintiffs claimed Lanzafama’s certification that the wall had been built correctly caused the certificate of occupancy to issue, requiring plaintiffs to close on a deficiently built house with a failing retaining wall. To that end, they introduced Naughton, who testified that no engineer should issue a certification without conducting an investigation sufficient to make the engineer reasonably certain of its accuracy. He set forth numerous investigatory steps a reasonable engineer might take to reach an appropriate level of certainty and how Lanzafama’s course of conduct fell short. He recounted that, although Lanzafama had never overseen the construction or inspected the wall as it was built, he should at least have discussed with the contractor how each aspect of the manufacturer’s specifications had been met, that the soil had been appropriately compacted, and that the appropriate [397]*397lengths of geogrid had been installed. Moreover, he should have requested compaction and soil density test results from the contractor and performed independent tests if the contractor made none available.

Naughton acknowledged that Lanzafama had reviewed photographs depicting the progress of construction of the wall, but disagreed that anything meaningful could be learned from them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ronald Boger v. Ideavillage Products Corp.
New Jersey Superior Court App Division, 2025
Kimberly Castro v. New Jersey Transit Corp.
New Jersey Superior Court App Division, 2025
Magnetek, Inc. v. Monsanto Company
New Jersey Superior Court App Division, 2024

Cite This Page — Counsel Stack

Bluebook (online)
109 A.3d 228, 439 N.J. Super. 391, 2015 N.J. Super. LEXIS 25, Counsel Stack Legal Research, https://law.counselstack.com/opinion/akhtar-v-jdn-properties-at-florham-park-llc-njsuperctappdiv-2015.