Affholder, Inc., (86-5348), (86-5349) v. Preston Carroll Company, Inc., and Cfw Construction Company, Inc., Defendants- (86-5348). Preston Carroll Company, Inc., and Cfw Construction Company, Inc., Third-Party (86-5349) v. The Louisville and Jefferson County Metropolitan Sewer District of Jefferson County, Kentucky, H.C. Nutting Company, Hubbard E. Ruddy Consulting Engineers, Inc. And Presnell Associates, Inc., James-Winstead & Associates, Inc., D.M.J.M., Inc. (Successor in Name to Vollmer Associates, Inc.), and E. Lionel Pavlo, Consulting Engineer, D/B/A Vollmer-Presnell-Pavlo, a Joint Venture, Third-Party

866 F.2d 881
CourtCourt of Appeals for the Third Circuit
DecidedMarch 20, 1989
Docket86-5348
StatusPublished

This text of 866 F.2d 881 (Affholder, Inc., (86-5348), (86-5349) v. Preston Carroll Company, Inc., and Cfw Construction Company, Inc., Defendants- (86-5348). Preston Carroll Company, Inc., and Cfw Construction Company, Inc., Third-Party (86-5349) v. The Louisville and Jefferson County Metropolitan Sewer District of Jefferson County, Kentucky, H.C. Nutting Company, Hubbard E. Ruddy Consulting Engineers, Inc. And Presnell Associates, Inc., James-Winstead & Associates, Inc., D.M.J.M., Inc. (Successor in Name to Vollmer Associates, Inc.), and E. Lionel Pavlo, Consulting Engineer, D/B/A Vollmer-Presnell-Pavlo, a Joint Venture, Third-Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Affholder, Inc., (86-5348), (86-5349) v. Preston Carroll Company, Inc., and Cfw Construction Company, Inc., Defendants- (86-5348). Preston Carroll Company, Inc., and Cfw Construction Company, Inc., Third-Party (86-5349) v. The Louisville and Jefferson County Metropolitan Sewer District of Jefferson County, Kentucky, H.C. Nutting Company, Hubbard E. Ruddy Consulting Engineers, Inc. And Presnell Associates, Inc., James-Winstead & Associates, Inc., D.M.J.M., Inc. (Successor in Name to Vollmer Associates, Inc.), and E. Lionel Pavlo, Consulting Engineer, D/B/A Vollmer-Presnell-Pavlo, a Joint Venture, Third-Party, 866 F.2d 881 (3d Cir. 1989).

Opinion

866 F.2d 881

AFFHOLDER, INC., Plaintiff-Appellant, (86-5348),
Plaintiff-Appellee, (86-5349),
v.
PRESTON CARROLL COMPANY, INC., and CFW Construction Company,
Inc., Defendants- Appellees, (86-5348).
PRESTON CARROLL COMPANY, INC., and CFW Construction Company,
Inc., Third-Party Plaintiffs-Appellants, (86-5349),
v.
The LOUISVILLE AND JEFFERSON COUNTY METROPOLITAN SEWER
DISTRICT OF JEFFERSON COUNTY, KENTUCKY, H.C. Nutting
Company, Hubbard E. Ruddy Consulting Engineers, Inc. and
Presnell Associates, Inc., James-Winstead & Associates,
Inc., D.M.J.M., Inc. (Successor in Name to Vollmer
Associates, Inc.), and E. Lionel Pavlo, Consulting Engineer,
d/b/a Vollmer-Presnell-Pavlo, a Joint Venture, Third-Party
Defendants-Appellees.

Nos. 86-5348, 86-5349.

United States Court of Appeals,
Sixth Circuit.

Argued March 12, 1987.
Decided Feb. 1, 1989.
Rehearing and Rehearing En Banc Denied March 20, 1989.

Stephen S. Schuster, Odgen, Robertson and Marshall, Louisville, Ky., G. Carroll Stribling, Jr. (argued), Fordyce & Mayne, St. Louis, Mo., for plaintiff-appellant in No. 86-5348.

Thomas J. Kirkwood, Cincinnati, Ohio, Kyle T. Hubbard, Walter K. Swyers, Jr., Karen A. Conrad, Louisville, Ky., for defendants-appellees in No. 86-5348.

John K. Gordinier (argued), Louisville, Ky., for Louisville & Jefferson Co. Metro. Sewer Dist.

Mary G. Moody (argued), Trabue, Sturdivant & Dewitt, Nashville, Tenn., for third-party plaintiffs-appellants in No. 86-5349.

Before ENGEL, Chief Judge*; and KRUPANSKY and GUY, Circuit Judges.

ENGEL, Chief Judge.

This appeal requires us to consider whether, under Article III, Section 2 of the United States Constitution, a cooperative litigation agreement executed by the plaintiff and defendant has eliminated any "case or controversy" between the parties, thus depriving the district court of jurisdiction over this litigation. The district court held that the litigation agreement eliminated a "case or controversy." However, we hold that Article III's "case or controversy" requirement has been met, and therefore we reverse and remand.

I.

In 1974 the Louisville and Jefferson County Metropolitan Sewer District of Jefferson County, Kentucky (MSD) undertook the planning and construction of a wastewater treatment project to serve both the North County Area and the Pond Creek-West County Areas of Louisville. Known as the Master Plan Expansion Program, the project was divided into approximately 128 different design/construction segments. This dispute focuses upon a segment known as the Pond Creek-4 Section (PC-4).

On September 11, 1974, MSD entered into a contract with a joint venture comprising Vollmer Associates, Inc., Presnell Associates, Inc., and Pavlo Engineers, Inc. (VPP). VPP was hired to provide management services in conjunction with the investigation, study, design and construction of the project.1 On March 4, 1975, H.C. Nutting Company (Nutting) contracted with VPP to provide soil testing, sampling and other geotechnical services for the project. On March 3, 1977, Hubbard E. Ruddy Consulting Engineers, Inc. (Ruddy) contracted with MSD to be the PC-4 section engineer whereby Ruddy agreed to provide MSD initial construction estimates and other engineering data.

After Ruddy completed its designing and engineering tasks, MSD sought bids from general contractors. The successful bidder was a joint venture between Preston Carroll Company, Inc. and CFW Construction Company, Inc. (PC/CFW), both Tennessee corporations with principal offices in Tennessee. On April 9, 1979, MSD and PC/CFW executed a contract whereby PC/CFW agreed to be general contractor on the PC-4 section. On July 5, 1979, PC/CFW subcontracted the underground tunneling work to Affholder, Inc. (Affholder), a Missouri corporation with its principal place of business in Missouri, at the cost of $960,000. Construction on the PC-4 section began in May 1979 and was scheduled for completion in September 1980.

Affholder, however, encountered difficulties in tunneling, which resulted in construction delays and greatly increased Affholder's expected costs. Nevertheless, the project was completed and delivered to MSD on January 16, 1981, and MSD accepted the job as complete on February 6, 1981. In the meantime, Affholder had informed PC/CFW that it would seek to offset its increased costs by filing a claim for an equitable adjustment under its subcontract, on the basis that soil conditions had been misrepresented to Affholder. On March 10, 1981, Affholder presented its claim to PC/CFW, and PC/CFW submitted the claim to MSD on April 2, 1981. On April 10, 1981, MSD rejected the claim for additional compensation.

Affholder and PC/CFW then negotiated concerning the problems on the PC-4 section, and on January 7, 1982 reached the following litigation agreement:

AGREEMENT

This Agreement entered into as of January 7, 1982 between Affholder, Inc., a corporation (Affholder) and Preston Carroll Co., Inc. and CFW Construction Co., Inc., a joint venture (PC/CFW).

WHEREAS, PC/CFW is the general contractor for the Pond Creek Interceptor Sewer Job (contract number 692) for the Louisville and Jefferson County Metropolitan Sewer District (MSD), and

WHEREAS, Affholder is a subcontractor to PC/CFW for tunnel work under a subcontract dated July 5, 1979, and

WHEREAS, Affholder has presented to PC/CFW a claim for extra costs incurred in connection with the execution of the subcontract, based upon changed conditions and/or design errors (the Affholder Claim), and

WHEREAS, PC/CFW has investigated the Affholder Claim, questioned the propriety thereof, and interrogated experts in connection therewith, and

WHEREAS, PC/CFW has concluded that the Affholder Claim is justified and has been substantiated, and

WHEREAS, PC/CFW has a claim (the PC/CFW Claim) by reason of extra costs incurred as a result of the matters which form the basis of the Affholder Claim, and

WHEREAS, the parties intend to present their claims to the MSD and desire to provide for the sharing of expenses with regard thereto and to eliminate certain issues from the presentation of the claims in order to simplify the presentation thereof.

NOW, THEREFORE, IT IS AGREED:

1. Affholder agrees that it will not seek recovery from PC/CFW with regard to the Affholder Claim, except to the extent that such claim is recovered from the MSD and/or other third parties.

2. PC/CFW agrees that it will not seek recovery from Affholder with regard to the PC/CFW claim, except to the extent that such claim is to be recovered from the MSD and/or other third parties.

3. The parties agree that the reasonable costs expended by either of them in connection with expert opinions and/or testimony in connection with the claims will be divided between them as follows: Affholder-75% and PC/CFW-25%.

4. Each party will bear its own attorneys' fees in connection with its claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aetna Life Insurance v. Haworth
300 U.S. 227 (Supreme Court, 1937)
Stewart v. Southern Railway Co.
315 U.S. 283 (Supreme Court, 1942)
Baker v. Carr
369 U.S. 186 (Supreme Court, 1962)
Liner v. Jafco, Inc.
375 U.S. 301 (Supreme Court, 1964)
Flast v. Cohen
392 U.S. 83 (Supreme Court, 1968)
DeFunis v. Odegaard
416 U.S. 312 (Supreme Court, 1974)
United Airlines, Inc. v. McDonald
432 U.S. 385 (Supreme Court, 1977)
Havens Realty Corp. v. Coleman
455 U.S. 363 (Supreme Court, 1982)
Nixon v. Fitzgerald
457 U.S. 731 (Supreme Court, 1982)
Allen v. Wright
468 U.S. 737 (Supreme Court, 1984)
Lake Coal Co. v. Roberts & Schaeffer Co.
474 U.S. 120 (Supreme Court, 1985)
Nally v. Boop
428 S.W.2d 607 (Court of Appeals of Kentucky (pre-1976), 1968)
Mitsui & Co. v. Puerto Rico Water Resources Authority
528 F. Supp. 768 (D. Puerto Rico, 1981)
Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
Ardsley Construction Co. v. Port of New York Authority
61 A.D.2d 953 (Appellate Division of the Supreme Court of New York, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
866 F.2d 881, Counsel Stack Legal Research, https://law.counselstack.com/opinion/affholder-inc-86-5348-86-5349-v-preston-carroll-company-inc-and-ca3-1989.