Aero Corp. v. Department of the Navy

558 F. Supp. 404, 30 Cont. Cas. Fed. 70,825, 1983 U.S. Dist. LEXIS 19196
District Court, District of Columbia·Decided February 16, 1983·No. Civ. A. 79-2944·Published·Cited by 20 cases

Opinion

MEMORANDUM

OBERDORFER, District Judge.

This is the final chapter of this protracted litigation 1 in which plaintiff has challenged *406 the Navy’s decision to award contracts for the C-130 aircraft Service Life Extension Program (SLEP) to the Lockheed-Georgia Corporation (“Lockheed” or “LGC”) without competition. 2 Plaintiff is an aerospace firm with ten years of experience in performing maintenance on C-130’s, as defendant’s contractor for Standard Depot Level Maintenance (SDLM) for its C-130 fleet. 3 Plaintiff alleges that the Navy was legally obligated to conduct a competition for its SLEP contracts, and that plaintiff would have submitted adequate bids for SLEP if a competition had been held. 4

I. Overview

Almost six years ago, the Navy formally began planning SLEP for 49 of its C-130’s. By mid-1979, defendant had decided to procure SLEP for all 49 planes from Lockheed on a “sole source” basis, that is, without attempting competitive bid solicitation for SLEP service contracts from other firms such as plaintiff or others experienced in the maintenance of C-130 aircraft. 5

This action was filed on October 30,1979, after defendant had made its final decision to award the SLEP contracts for all 49 C-130’s to Lockheed; contracts for the first 13 planes were actually awarded on November 30, 1979. On March 4, 1980, after obtaining the advice of the General Accounting Office (GAO), C.R. A-35, considering briefs and documentary evidence and holding a hearing, the Court filed a Memorandum (Aero I) finding and concluding that, due to the military urgency of the SLEP induction schedule, 6 defendant’s sole-source award of the initial SLEP contracts was not unreasonable. The Court also concluded, however, that defendant had “not satisfied the GAO or the Court that it now has a reasonable basis for precluding competition for SLEP procurement with respect to the balance of the procurement.” 493 F.Supp. at 568. The Court therefore ordered defendant, inter alia, “in good faith to consider the feasibility of competitive procurement for the remaining planes to undergo SLEP, including the use of kits tailored to depot level contractors experienced with the C-130.” 7 Id. at 570 (hereinafter “March 1980 Order”).

*407 Thereafter, while defendant ostensibly studied competitive options, the Court invited further GAO consideration of the possibilities and requirements for competition for SLEP procurement. 8 Meanwhile, plaintiff began to charge that Navy was not complying with the March 1980 Order and was otherwise acting in bad faith. See, e.g., C.R. 2; C.R. 29; C.R. 32. In June and September, 1981, the Acting Comptroller General of the GAO rendered two opinions, concluding that the Navy still had not rationally justified its decision to award the contracts for SLEP service for the remaining 29 C-130’s without attempting competition. C.R. 84; C.R. 63 at 2. The GAO advised the Court that the Navy should take specified actions to attempt to compete the remaining SLEP contracts before it decided to award them to Lockheed on a sole-source basis.

Because the GAO’s opinion does not bind the parties or the Court, see Wheelabrator Corporation v. Chafee, 455 F.2d 1306, 1316-17 (D.C.Cir.1971), the Court invited further briefs, received further evidence and held further hearings on the merits and on the questions raised by plaintiff about the Navy’s good faith compliance with the March 1980 Order. These culminated in a Memorandum filed on February 18, 1982, (Aero II), in which the Court concluded that defendant’s decision not to permit competition for the remainder of the SLEP procurement still had no rational support in the record, and that plaintiff would probably prevail on its claim that defendant’s decision to contract with Lockheed as the sole-source for SLEP for the remaining C-130’s without competition violated the Armed Services Procurement Act, 10 U.S.C. § 2304(g) (1976 & Supp. V 1981), 9 and Section Three of the Defense Acquisition Regulations, 32 C.F.R., part 1, vol. 1, ¶ 3-101(d) (1981) (“DAR 3-101(d)”). 10 See 540 F.Supp. at 184, 211. In order to secure compliance with its March 1980 Order, the GAO’s subsequent advice, and the requirements of § 2304(g) and DAR 3-101(d), the Court issued a preliminary injunction. This injunction specified procurement actions to be taken by defendant “to foster competitive conditions for subsequent procurements ... and possible breakout of components for competitive procurement.” DAR 3-101(d). Specifically, the injunction (hereinafter “1982 Order”) ordered defendant to “commence forthwith preparation of such an Engineering Change Proposal (ECP) and Air Frame Change (AFC) as may be needed for C-130 SLEP accomplishment by experienced C-130 Standard Depot Level Mainte *408 nance (SDLM) contractors following competitive negotiation limited to LGC and experienced C-130 SDLM contractors,” 11 and to “commence to take all other steps necessary to avoid the need for future non-competitive procurement of C-130 SLEP.” 540 F.Supp. at 219 (citations omitted). The Court also ordered defendant to file a report on or before May 31,1982, based on its engineering progress to that date, regarding the possibilities of competition for SLEP contracts for the remaining C-130’s. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Aero Corp. v. Department of the Navy, 558 F. Supp. 404, 30 Cont. Cas. Fed. 70,825, 1983 U.S. Dist. LEXIS 19196 (D.D.C. 1983).

558 F. Supp. 404 (Aero Corp. v. Department of the Navy) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Shelby County, Alabama v. Holder
43 F. Supp. 3d 47 (District of Columbia, 2014)
Cobell v. Norton
407 F. Supp. 2d 140 (District of Columbia, 2005)
ALABAMA DEM v. Town of Lowndesboro
950 So. 2d 1180 (Court of Civil Appeals of Alabama, 2005)
Labat-Anderson, Inc. v. United States
346 F. Supp. 2d 145 (District of Columbia, 2004)
Armstrong v. Executive Office of the President
821 F. Supp. 761 (District of Columbia, 1993)
Davis v. City & County of San Francisco
890 F.2d 1438 (Ninth Circuit, 1989)
Synanon Foundation, Inc. v. Bernstein
517 A.2d 28 (District of Columbia Court of Appeals, 1986)
Nepera Chemical, Inc. v. Sea-Land Service, Inc.
794 F.2d 688 (D.C. Circuit, 1986)
Greenfield v. District of Columbia
623 F. Supp. 47 (District of Columbia, 1985)
NAACP, Jefferson County Branch v. Brock
619 F. Supp. 846 (District of Columbia, 1985)
Atochem v. United States
609 F. Supp. 319 (Court of International Trade, 1985)
St. Paul Fire & Marine Insurance v. United States
4 Cl. Ct. 762 (Court of Claims, 1984)
Acme of Precision Surgical Co., Inc. v. Weinberger
580 F. Supp. 490 (E.D. Pennsylvania, 1984)
Bregstone v. United States
4 Cl. Ct. 507 (Court of Claims, 1984)
Massachusetts Union of Public Housing Tenants v. Pierce
577 F. Supp. 1499 (District of Columbia, 1984)