Advin Electric, Inc. v. Reliance Surety Co.

41 Cont. Cas. Fed. 76,990, 682 A.2d 1173, 111 Md. App. 504, 1996 Md. App. LEXIS 121
CourtCourt of Special Appeals of Maryland
DecidedSeptember 25, 1996
Docket1770, Sept. Term, 1995
StatusPublished
Cited by1 cases

This text of 41 Cont. Cas. Fed. 76,990 (Advin Electric, Inc. v. Reliance Surety Co.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Advin Electric, Inc. v. Reliance Surety Co., 41 Cont. Cas. Fed. 76,990, 682 A.2d 1173, 111 Md. App. 504, 1996 Md. App. LEXIS 121 (Md. Ct. App. 1996).

Opinion

WILNER, Chief Judge.

Advin Electric, Inc., a subcontractor on a building project, filed suit in the Circuit Court for Montgomery County against Reliance Surety Company, the surety on a payment bond posted by the general contractor, seeking money owing under its subcontract.

Reliance moved to dismiss the action on the ground that the job, and thus the claim, was subject to the Miller Act, 40 U.S.C. §§ 270a et seq. (1994), because the building project was a “public work of the United States.” Enforcement actions under the Miller Act, it urged, were within the exclusive jurisdiction of the Federal District Courts, and the State court therefore had no subject matter jurisdiction. The court granted the motion and dismissed the action. We shall reverse.

*506 FACTS

On September 28, 1989, Tyler Construction Company entered into a contract with Senior Citizens Housing Development Corporation (“Owner”), a private, non-profit organization, to build Johnson Towers, an apartment building complex for elderly persons. The Owner financed the project through a loan made from the United States Department of Housing and Urban Development (“HUD”).

The construction contract between Tyler and the Owner provided that: (1) HUD reserved the right to become the owner of the property in the event of a default by the Owner, (2) HUD had the exclusive right to interpret the principal contract and approve any changes, (3) Tyler warranted to HUD and the Owner that it would fully comply with all HUD regulations, (4) HUD retained the right of access to the construction site to inspect the progress of the work, (5) the contract date could be extended only with HUD’s written approval, and (6) Tyler was required to obtain from all subcontractors agreements waiving their right to file or perfect any liens against the project.

In accordance with a HUD regulation, 24 C.F.R. § SSS^lSfti), 1 the construction contract also contained a provision requiring that “[t]he Contractor shall furnish to the Owner assurance of completion of the work in the form of a Performance/Payment Bond (HUD Form No. 2452-EH) in the amount of 100% of the Contract. Such assurance of completion shall run to the Owner and HUD as obligees.” Tyler, as principal, and Reliance, as surety, executed and delivered to the Owner and HUD the “Performance-Payment Bond.”

*507 On November 9,1989, Tyler entered into a subcontract with Advin for the performance of electrical work and wiring for the project. The subcontract incorporated by reference all terms of the principal contract “as if attached to this Agreement or repeated herein,” which included the provision prohibiting Advin from perfecting a lien against the project. After completion of the subcontract work, a dispute arose between Advin and Tyler, which led to this action by Advin against Reliance.

DISCUSSION

(1) The Miller Act

The Miller Act, 40 U.S.C. §§ 270a (1994), requires that, before any contract exceeding $25,000 for the construction, alteration, or repair of “any public building or public work of the United States” is awarded, the contractor must furnish to the United States a performance bond for the protection of the United States and a payment bond for the protection of all persons supplying labor or material in the prosecution of the work.

We are concerned here only with the payment bond. The requirement in § 270a that such a bond be furnished is supplemented by the provisions of § 270b. Subject to the conditions stated therein, that section gives each person who has furnished labor or material in the prosecution of the work provided for in the contract and who has not been paid the right to sue on the payment bond. The suit must be brought in the name of the United States in the United States District Court. Unlike the case with certain other Federal statutes authorizing actions in the District Courts, Federal court jurisdiction under the Miller Act is exclusive. There is no concurrent jurisdiction in the State courts. See United States ex rel. Owens-Corning Fiberglass Corp. v. Brandt Constr. Co., 826 F.2d 643, 645 (7th Cir.1987), cert. denied, 484 U.S. 1026, 108 S.Ct. 751, 98 L.Ed.2d 764 (1988).

*508 The payment bond requirement of the Miller Act was intended to provide an alternative remedy for subcontractors and suppliers working on Federal projects. The normal remedy available to such persons is to file a mechanic’s lien against the property and, if not then paid, to have the property sold. That remedy is not available with respect to Federally owned property; the paramount sovereignty of the United States makes its property immune from liens created by State law. See F.D. Rich Co. v. United States ex rel. Industrial Lumber Co., 417 U.S. 116, 121-22, 94 S.Ct. 2157, 2161-62, 40 L.Ed.2d 703 (1974); U.S. for Use of General Elec. Supply v. USF & G, 11 F.3d 577, 580 (6th Cir.1993). Although the Act has been regarded as “highly remedial” in nature and therefore to be given a liberal construction “in order properly to effectuate the Congressional intent to protect those whose labor and materials go into public projects,” that salutary policy “does not justify ignoring plain words of limitation.... ” Clifford F. MacEvoy Co. v. United States ex rel. Calvin Tomkins Co., 322 U.S. 102, 107, 64 S.Ct. 890, 893, 88 L.Ed. 1163 (1944).

(2) Application

As noted, the payment bond provision of the Miller Act applies only to persons supplying labor or material in prosecuting a contract for the construction, alteration, or repair of a “public building or public work of the United States.” The sole issue in this case is whether Johnson Towers is such a project."

The critical term is not defined in the Act; its scope has been delineated by case law. Although at one time it was argued that the Act applied only to a building or public work actually owned by the United States or one of its agencies, the Supreme Court made clear in United States ex rel. Noland Co., Inc. v. Irwin, 316 U.S. 23, 62 S.Ct. 899, 86 L.Ed. 1241 (1942), that that was not necessarily the case.

The precise scope of Irwin is in some dispute. The contract, for the construction of a library at Howard University, was financed as a public works project under the National *509

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
41 Cont. Cas. Fed. 76,990, 682 A.2d 1173, 111 Md. App. 504, 1996 Md. App. LEXIS 121, Counsel Stack Legal Research, https://law.counselstack.com/opinion/advin-electric-inc-v-reliance-surety-co-mdctspecapp-1996.