Abbott v. Jarrett Reclamation Services, Inc.

726 N.E.2d 511, 132 Ohio App. 3d 729, 1999 Ohio App. LEXIS 1082
CourtOhio Court of Appeals
DecidedMarch 15, 1999
DocketNo. 96-BA-36
StatusPublished
Cited by18 cases

This text of 726 N.E.2d 511 (Abbott v. Jarrett Reclamation Services, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Abbott v. Jarrett Reclamation Services, Inc., 726 N.E.2d 511, 132 Ohio App. 3d 729, 1999 Ohio App. LEXIS 1082 (Ohio Ct. App. 1999).

Opinions

Cox, Presiding Judge.

The present appeal arose on the death of Bradley J. Abbott, who died in the scope of his employment when the side of a deep trench that he was working in caved in and buried him. Among others, Abbott’s wife (“plaintiff’) sued the general contractor, David Black Contracting Services, Inc. (“Black”), and the subcontractor who employed her husband, Jarrett Reclamation Services, Inc. (“Jarrett”). After five days of trial by jury, the trial court granted directed verdicts in favor of both Black and Jarrett.

On November 21, 1991, the village of Clarington (“Clarington”) awarded a contract to Black to construct a sewer system within its village. Clarington also hired engineers William Brake and Valiant Roxby to oversee and monitor the project. Chris Simon was the resident project representative on site every day on behalf of Brake and kept a daily construction report. Inspections of the site were also made by the Army Corp of Engineers.

As general contractor, Black was responsible for the entire project, which included installing the main sewer line to the wastewater treatment plant and installing lateral lines connecting the buildings and residences to the main line. On March 6, 1992, Black hired Jarrett to complete those parts of the project not able to be completed by Black or J & R Construction Company, another subcontractor. Black informed Rick Jarrett, the owner of Jarrett, that lateral work would be involved in his subcontractor duties as well as reclamation work. When Black gave Rick Jarrett a copy of their subcontract, it attached a copy of the specifications for the project, which included details of the trench work to be done by Jarrett, as well as the depths of the trenches. Black also attached a copy of safety procedures in excavation.

[735]*735Biweekly construction meetings were held between Black, the engineers, and others to discuss and plan each progressing part of the project. On October 15, 1992, a construction meeting was held on the part of the project that subsequently involved Abbott’s death. Rick Jarrett attended this meeting and also traveled to the site of Bob’s Bar to observe the location where the work would be done.

Jarrett’s crew on most of the project consisted of Jerry Clark, who operated the backhoe, and Abbott, the general laborer. Before this project, Rick Jarrett had never excavated a trench deeper than five feet and owned no safety equipment for digging trenches deeper than five feet. Jarrett had been working on the project for a few months before the accident occurred and had already installed a number of laterals and excavated one or two trenches deeper than five feet deep without safety equipment.

In March 1992, Black installed a main line into the ground along the side of Bob’s Bar and planted a six-inch lateral from the main underneath the street and the asphalt parking lot ending behind Bob’s Bar. Black capped the end of the lateral and refilled the trench. Black placed a location reference marker that protruded out of the ground at the main line. On the morning of October 29, 1992, the Jarrett crew was to work behind Bob’s Bar to connect three structures including the bar with a lateral to the main sewer line already installed by Black. The lateral line ran behind the bar and then turned ninety degrees to run alongside it to the main sewer line toward the street.

Clark and Abbott arrived early that morning and Clark began digging with the backhoe along the side of the bar to locate the main line instálled by Black. Clark excavated a long trench. Abbott jumped into the ditch with a shovel to dig and precisely locate the main without breaking it as a backhoe would. Clark and Abbott then worked at the other end of the trench seeking to locate the pipes coming out of the structures for the hookup to the lateral. At about this point, Rick Jarrett arrived on the scene.

Clark and Abbott had difficulty locating the outlet pipes from the buildings and Simon arrived to help the Jarrett crew locate these. Simon, Clark, and Abbott went into the basement of one of the buildings to see if they could locate approximately where the lines were. Conflicting testimony was presented as to whether Jack Schoolcraft, one of Black’s supervisors, had stopped at the scene that morning to help locate the outlets. It was undisputed that Schoolcraft was somewhere on the project site that day and was available if help was needed. Upon finding no direction as to the location of the lines, Clark started digging behind the bar with the backhoe to find a line.

After digging a trench behind the bar that was approximately thirty feet long and four feet deep, Abbott jumped into the ditch, dug around with a shovel, and located the lateral tie-in. Abbott and Rick Jarrett then left while Clark contin[736]*736ued digging around the corner of the bar toward the street to find the main line marked above ground by Black. Clark extended the trench to fifty feet long when Abbott, Rick Jarrett, and Simon returned to have lunch. Clark finished his lunch first and again began digging to uncover the main line on the side of the bar. Most of the areas inside this trench were deeper than five feet and the ditch was approximately twenty inches wide. No safety measures or trench boxes were placed in the trench, nor was the trench sloped so that a means of egress existed. Clark piled the earth he removed from the trench immediately next to the left side of the trench. Rick Jarrett left the scene after lunch.

While Clark was digging the trench, he noticed Abbott in the trench walking toward him with a shovel. Clark returned to his digging when he saw Abbott running up the ditch. Clark then saw the ditch crack and the bank of the trench cave in on Abbott. Clark jumped in to dig Abbott out, and others aided in the rescue attempt. Abbott’s body was eventually recovered.

On October 19,1993, plaintiff brought a lawsuit alleging intentional tort against Jarrett, and a wrongful death and survivorship action against general contractor Black, the village of Clarington, and the engineers hired by the village, Brake and Roxby. Jarrett, Brake, and Roxby filed answers, and Black filed an answer and cross-claim against Jarrett. Clarington also filed an answer and cross-claim against all of the other defendants in the complaint. Discovery began in the case. On June 24, 1994, Clarington filed a motion for summary judgment arguing that governmental immunity applied under R.C. 2744.02(A)(1) to bar the lawsuit. The trial court granted the motion. On July 18, 1994, Black filed a motion for summary judgment arguing that it had no duty as a matter of law to Abbott, as the employee of its subcontractor, because plaintiff failed to show that Black actively participated in Jarrett’s work. Black also argued that Abbott knew that he was performing inherently dangerous work. Black attached supporting materials.

On September 12, 1994, Brake and Roxby filed a joint motion for summary judgment. On September 23,1994, Jarrett filed a motion for summary judgment arguing that plaintiff failed to present evidence to prove that Jarrett committed an intentional tort. Plaintiff filed motions opposing the motions for summary judgment.

Extensive discovery continued on the case and there were extensive tangential motions filed by all parties.

On February 24,1995, Clarington voluntarily dismissed its cross-claims against Brake and Roxby. On April 4, 1995, plaintiff voluntarily dismissed Brake and Roxby with prejudice, leaving only Jarrett and Black as the remaining defendants.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Madden v. Prod. Concrete, Inc.
2013 Ohio 5393 (Ohio Court of Appeals, 2013)
Venable v. Greater Friendship Baptist Church
2010 Ohio 3159 (Ohio Court of Appeals, 2010)
Lillie v. Meachem
2009 Ohio 4934 (Ohio Court of Appeals, 2009)
Duco v. Wheeling-Pittsburgh Steel Corp., 07 Je 41 (6-18-2008)
2008 Ohio 3092 (Ohio Court of Appeals, 2008)
Pavlik v. Barium Chemicals, Inc., Unpublished Decision (3-29-2004)
2004 Ohio 1726 (Ohio Court of Appeals, 2004)
Wyczalek v. Rowe Construction Services Co.
773 N.E.2d 560 (Ohio Court of Appeals, 2001)
Cummins v. JGB Industries, Inc.
4 F. App'x 270 (Sixth Circuit, 2001)
Summa Health System v. Viningre
749 N.E.2d 344 (Ohio Court of Appeals, 2000)
Frost v. Dayton Power and Light Company
138 Ohio App. 3d 182 (Ohio Court of Appeals, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
726 N.E.2d 511, 132 Ohio App. 3d 729, 1999 Ohio App. LEXIS 1082, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abbott-v-jarrett-reclamation-services-inc-ohioctapp-1999.