Strother v. Novak Sons, Inc., Unpublished Decision (7-27-2000)

CourtOhio Court of Appeals
DecidedJuly 27, 2000
DocketNO. 76306 and 76385.
StatusUnpublished

This text of Strother v. Novak Sons, Inc., Unpublished Decision (7-27-2000) (Strother v. Novak Sons, Inc., Unpublished Decision (7-27-2000)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Strother v. Novak Sons, Inc., Unpublished Decision (7-27-2000), (Ohio Ct. App. 2000).

Opinion

JOURNAL ENTRY and OPINION
In this consolidated appeal, appellant Frank Novak Sons (Frank Novak) appeals the trial court's denial of its directed verdict motion in a negligence action filed by appellee Larry Strother against both subcontractor Frank Novak and general contractor Standard Construction Company (Standard). Strother sought to recover for injuries sustained when he fell from a six foot scaffold while painting a one hundred thirty eight-year-old building under renovation by Standard. The trial court granted Standard's motion for summary judgment. The case proceeded to trial against Frank Novak. Frank Novak's motion for a directed verdict was denied by the trial court and the jury returned a comparative negligence verdict finding Frank Novak fifty percent liable and Strother fifty percent liable.

Frank Novak assigns the following error for our review in its appeal No. 76306:

THE TRIAL COURT ERRED IN FAILING TO DIRECT A VERDICT PURSUANT TO RULE 50 OF THE OHIO RULES OF CIVIL PROCEDURE IN FAVOR OF DEFENDANT, FRANK NOVAK SONS.

In appeal No. 76385, Strother assigns the following two errors for our review:

I. THE TRIAL COURT ERRED IN AWARDING SUMMARY JUDGMENT TO DEFENDANT STANDARD CONSTRUCTION CO. BECAUSE THERE WAS SUFFICIENT EVIDENCE THAT STANDARD DID RETAIN CONTROL OVER A CRITICAL ASPECT OF THE WORK SITE.

II. THE TRIAL COURT ERRED IN DENYING PLAINTIFF'S MOTION FOR JUDGMENT N.O.V. BECAUSE THE ONLY EVIDENCE ON COMPARATIVE NEGLIGENCE WAS HABIT PURSUANT TO EVIDENCE RULE 406, AND THERE WAS INSUFFICIENT EVIDENCE TO ESTABLISH HABIT.

Having reviewed the record and the legal arguments of the parties, we reverse the trial court's denial of Frank Novak's Civ.R. 50 directed verdict motion on the grounds that as a matter of law Strother failed to show that Frank Novak as subcontractor directed the activity which resulted in the injury and/or gave or denied permission for the critical acts that led to Strother's injury. Here, Strother showed that Greg Pawlowski, HC Painting's foreman, directed him to the fourth floor and assumed control over his work activity, not Frank Novak. For these same reasons, we affirm the trial court's granting of summary judgment for Standard who had merely a general supervisory role over the painting project and who regularly scheduled the work to be performed in an area thought to be safe. The apposite facts follow.

Strother fell from a six foot scaffold while painting sprinkler lines on the fourth floor of a one hundred thirty eight-year-old building under renovation by Standard. Standard successfully bid for the project and hired subcontractor Frank Novak to paint the building. In turn, Novak contracted with minority-owned HC Painting to handle the preliminary painting and stripping work.

The facts showed Frank Novak needed a minority firm in order to qualify for the bid. Frank Novak employed Strother and other workers in its company and loaned them to HC Painting. Strother testified this practice had occurred on prior jobs. For purposes of this appeal, these facts are superfluous. The trial court found and we agree that for purposes of this action, Strother worked for independent contractor HC Painting.

The uncontroverted fact is that the building was in disrepair and contained numerous defects, soft spots, and unleveled areas in the floor. Standard's project manager, James Donelan, and Frank Novak's representative agreed that before any work was to be performed, a two to four inch concrete topping would be applied over the building's deteriorated wood floors. Frank Novak agreed to provide all of the materials and in fact provided the scaffold used by Strother on the day Strother fell. Standard did lay the concrete floor as promised in some areas. On the date in question, Strother was actually painting in an area with a concrete floor when he was ordered by Pawlowski, HC Painting's foreman, to paint the fourth floor area that had not been covered with concrete. Strother protested, but to no avail.

During the trial against Frank Novak, Strother presented evidence that his fall was due to the failure of a soft spot in the floor. Novak presented testimony from several other workers on the project who said they saw Strother move the scaffold by holding onto the sprinkler pipe and dragging the scaffold a practice they described as dangerous, although common. Novak argued that this improper movement of the scaffold is what caused Strother's fall. Strother maintained that he always locked the wheels of the scaffold before climbing onto it and that he did not drag the scaffold while standing on it, but climbed down from the scaffold and unlocked its wheels before moving it.

At the end of Strother's case in chief and again at the end of all the evidence, Frank Novak moved for a directed verdict. Each time, the motion was denied. The jury awarded Strother $135,000 in damages and found, via interrogatories, that Strother and Frank Novak were each fifty percent negligent. Strother filed a motion for judgment notwithstanding the verdict (JNOV) alleging that there was no evidence that he dragged the scaffold at the moment of the accident and that Frank Novak's claim that he had a habit of dragging the scaffold did not support a finding that he dragged the scaffolding at the time of the accident. The motion for a JNOV was denied. These appeals followed.

At the outset, we must acknowledge the convoluted working relationship of these parties. It is undisputed that Strother worked for Frank Novak and considered Frank Novak his employer. However, to obtain this job, Frank Novak hired a minority firm, HC Painting, so as to meet the city's minority set aside standards. Frank Novak then loaned Strother and Greg Pawlowski to HC Painting. If we were to conclude that Strother worked for Frank Novak and that these relationships were a sham, the issues in this case would not center on ordinary negligence independent contractor issues but on intentional employer tort issues. We decline to view the facts of this case under the intentional tort law area and resolve this case under the rules set forth in Sopkovich v. Ohio Edison Co. (1988), 81 Ohio St.3d 628, 693 N.E.2d 233; Hirschbach v. Cincinnati Gas Electric Co. (1983), 6 Ohio St.3d 206,452 N.E.2d 326; Cafferkey v. Turner Constr. Co. (1986), 21 Ohio St.3d 110,488 N.E.2d 189; Bond v. Howard Corp. (1995), 72 Ohio St.3d 332,650 N.E.2d 416. In those cases, the supreme court held that the traditional ordinary negligence principles of business invitee rules apply when an independent contractor is employed by an owner or a general contractor and is injured on the job. See Wellman v. East Ohio Gas Co. (1953), 160 Ohio St. 103, 113 N.E.2d 629, citing Bosjnak v. Superior (1945), 145 Ohio St. 538, 62 N.E.2d 305.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Betzner v. Navistar International Transportation Corp.
603 N.E.2d 256 (Ohio Court of Appeals, 1991)
Bosjnak v. Superior Sheet Steel Co.
62 N.E.2d 305 (Ohio Supreme Court, 1945)
Abbott v. Jarrett Reclamation Services, Inc.
726 N.E.2d 511 (Ohio Court of Appeals, 1999)
Hawkins v. Ivy
363 N.E.2d 367 (Ohio Supreme Court, 1977)
Strother v. Hutchinson
423 N.E.2d 467 (Ohio Supreme Court, 1981)
Ruta v. Breckenridge-Remy Co.
430 N.E.2d 935 (Ohio Supreme Court, 1982)
Hirschbach v. Cincinnati Gas & Electric Co.
452 N.E.2d 326 (Ohio Supreme Court, 1983)
Cafferkey v. Turner Construction Co.
488 N.E.2d 189 (Ohio Supreme Court, 1986)
Fyffe v. Jeno's, Inc.
570 N.E.2d 1108 (Ohio Supreme Court, 1991)
Bond v. Howard Corp.
650 N.E.2d 416 (Ohio Supreme Court, 1995)
Michaels v. Ford Motor Co.
650 N.E.2d 1352 (Ohio Supreme Court, 1995)
Wagner v. Roche Laboratories
671 N.E.2d 252 (Ohio Supreme Court, 1996)
Sopkovich v. Ohio Edison Co.
693 N.E.2d 233 (Ohio Supreme Court, 1998)
Cefaratti v. Mason Structural Steel Co.
694 N.E.2d 915 (Ohio Supreme Court, 1998)
Apel v. Katz
697 N.E.2d 600 (Ohio Supreme Court, 1998)
Cater v. City of Cleveland
83 Ohio St. 3d 24 (Ohio Supreme Court, 1998)
Wagner v. Midwestern Indemnity Co.
699 N.E.2d 507 (Ohio Supreme Court, 1998)
Apel v. Katz
700 N.E.2d 334 (Ohio Supreme Court, 1998)
Wagner v. Roche Laboratories
709 N.E.2d 162 (Ohio Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Strother v. Novak Sons, Inc., Unpublished Decision (7-27-2000), Counsel Stack Legal Research, https://law.counselstack.com/opinion/strother-v-novak-sons-inc-unpublished-decision-7-27-2000-ohioctapp-2000.