Madden v. Prod. Concrete, Inc.

2013 Ohio 5393
CourtOhio Court of Appeals
DecidedDecember 10, 2013
Docket13AP-208
StatusPublished
Cited by1 cases

This text of 2013 Ohio 5393 (Madden v. Prod. Concrete, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Madden v. Prod. Concrete, Inc., 2013 Ohio 5393 (Ohio Ct. App. 2013).

Opinion

[Cite as Madden v. Prod. Concrete, Inc., 2013-Ohio-5393.]

IN THE COURT OF APPEALS OF OHIO

TENTH APPELLATE DISTRICT

Larry Madden et al., :

Plaintiffs-Appellants, :

v. : No. 13AP-208 (C.P.C. No. 12CV-4549) Production Concrete, Inc., : (REGULAR CALENDAR) Defendant-Appellee. :

D E C I S I O N Rendered on December 10, 2013

Mark A. Adams, LLC, and Mark A. Adams, for appellants.

Isacc, Brant, Ledman & Teetor, LLP, J. Stephen Teetor, James M. Roper and Maribeth Deavers, for appellee.

APPEAL from the Franklin County Court of Common Pleas TYACK, J. {¶ 1} Plaintiff-appellant, Larry Madden was injured when a trench collapsed while he was repairing an underground sewer pipe. For the reasons that follow, we affirm the judgment of the trial court granting summary judgment to defendant-appellee, Production Concrete ("PC"), albeit for a different reason. {¶ 2} Madden was employed by non-party Madden Building and Remodeling who, in 2006, originally installed the sewer pipe at the Creekside Communities No. 13AP-208 2

condominium unit known as Building No. 1. The pipe was covered and not disturbed until 2007 when PC dug a large hole over the sewer pipe in order to install a water meter. For purposes of summary judgment only, PC admitted it was negligent in installing the water meter pit. {¶ 3} The first occupant to move into the building reported a sewer line back up in March 2008. The owners contacted Madden Building and Remodeling to repair the sewer line. The portion of the sewer pipe that was broken was approximately six to eight feet below the surface. By use of shovels and a hose, Madden was able to determine that the pipe was blocked in the vicinity of the water meter pit. {¶ 4} Madden and his co-workers began using a backhoe to expose more of the pipe. They excavated a trench about four feet deep and three feet wide. Once the backhoe had reached four feet of depth, Madden and his co-workers would enter the trench and dig two or three more feet with hand tools until they reached the pipe. As they progressed, they would stop every six or seven feet to shore up the sides of the trench using plywood and 4x4s along the banks. {¶ 5} When the cave-in occurred, about 15 feet of the trench had been shored up. The backhoe had just excavated the next section when Madden entered the trench and began to hand-dig. Suddenly, the trench collapsed, severely injuring Madden. {¶ 6} Madden and his wife filed suit against PC, alleging negligence and loss of consortium. Madden argued that PC negligently damaged the sewer pipe while installing a water meter pit, and that as a direct and proximate result of PC's damage to the sewer pipe, Madden was foreseeably injured while making the necessary underground repairs. Madden asserted that PC owed a legal duty to him based on the foreseeability of injury to No. 13AP-208 3

a person making repairs, and is thus liable for the resultant damages that he claims were directly and proximately caused by PC's negligence. {¶ 7} PC moved for summary judgment on the basis that it did not owe any duty to Madden and that its negligent installation of the water meter was not the proximate cause of Madden's injuries. {¶ 8} The trial court found the existence of any duty owed to Madden to be questionable, but on the record before it, could not rule out the possibility that PC owed a duty to Madden. For purposes of summary judgment, PC admitted it had negligently broken the sewer line while installing or lowering the water meter underground. However, the court could not determine the likelihood of injury, the extent of PC's negligence, and its effect on the likelihood of injury. The court instead granted summary judgment in favor of PC on the issue of proximate cause, finding PC's conduct was, at best, a remote cause and that the proximate cause of Madden's injuries was the collapsing trench. {¶ 9} This appeal followed. Madden assigns a single assignment of error for our consideration: The trial court erred by granting appellee's motion for summary judgment and finding as a matter of law that appellee's negligence was a remote cause of appellant's injuries, without ever applying the law of proximate cause, and even though appellee's negligence was continuous and unbroken, and the harm to appellant as a result was foreseeable.

{¶ 10} Appellate review of summary judgment motions is de novo. Helton v. Scioto Cty. Bd. of Commrs., 123 Ohio App.3d 158, 162 (4th Dist.1997). "When reviewing a trial court's ruling on summary judgment, the court of appeals conducts an independent No. 13AP-208 4

review of the record and stands in the shoes of the trial court." Mergenthal v. Star Banc Corp., 122 Ohio App.3d 100, 103 (12th Dist.1997). Civ.R. 56(C) provides that summary judgment may be granted when the moving party demonstrates that: (1) there is no genuine issue of material fact, (2) the moving party is entitled to judgment as a matter of law, and (3) reasonable minds can come to but one conclusion, and that conclusion is adverse to the party against whom the motion for summary judgment is made. State ex rel. Grady v. State Emp. Relations Bd., 78 Ohio St.3d 181, 183 (1997). {¶ 11} "[N]egligence is conduct which falls below the standard established by law for the protection of others against unreasonable risk of harm." 2 Restatement of the Law 2d, Torts, Section 282 (1965). Negligence occurs when the defendant fails to recognize that he owes a duty to protect the plaintiff from harm and that failure proximately resulted in injury or damage to the plaintiff. Di Gildo v. Caponi, 18 Ohio St.2d 125, 127 (1969); Kauffman v. First-Central Trust Co., 151 Ohio St. 298, 306 (1949). The elements of a claim of negligence are: (1) the existence of a legal duty owing from the defendant to the plaintiff; (2) the defendant's breach of that duty; and (3) injury to the plaintiff proximately resulting from such failure. Wallace v. Ohio Dept. of Commerce, 96 Ohio St.3d 266, 2002-Ohio-4210, ¶ 22, citing Mussivand v. David, 45 Ohio St.3d 314, 318 (1989). To recover, a plaintiff must also prove damages proximately resulting from the breach. Horsley v. Essman, 145 Ohio App.3d 438, 442 (4th Dist.2001), citing Jeffers v. Olexo, 43 Ohio St.3d 140, 142 (1989). {¶ 12} The existence and conditions of a duty between two parties is determined by the nature of the relationship between them. Wallace at ¶ 23, citing Commerce & Industry Ins. Co. v. Toledo, 45 Ohio St.3d 96, 98 (1989). The duty element of negligence poses a question of law for the court to determine. Wallace at ¶ 22. "[T]he existence of a No. 13AP-208 5

duty depends upon the foreseeability of harm: if a reasonably prudent person would have anticipated that an injury was likely to result from a particular act, the court could find that the duty element of negligence is satisfied." Id. at ¶ 23, citing Texler v. D.O. Summers Cleaners & Shirt Laundry Co., 81 Ohio St.3d 677, 680 (1998); Commerce, supra; Menifee v. Ohio Welding Prods., Inc., 15 Ohio St.3d 75, 77 (1984). Duty has also been described as "the court's 'expression of the sum total of those considerations of policy which lead the law to say that the particular plaintiff is entitled to protection.' " Wallace at ¶ 24, quoting Mussivand at 318, in turn quoting Prosser & Keeton, The Law of Torts, (4th Ed.1971), 325-26. Thus, there is no explicit formula for determining whether a duty exists and the existence of a duty is largely dependent upon the facts and circumstances present. See Payne v. Vance, 103 Ohio St. 59, 67 (1921). {¶ 13} Madden characterizes his injury as flowing directly from PC's negligence and as result, entirely foreseeable. First, he submits that PC's negligence in damaging the sewer line continued in an unbroken chain up to the point of the trench collapse.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lee Testing & Eng. Inc. v. Ohio Dept. of Transp.
2014 Ohio 1850 (Ohio Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2013 Ohio 5393, Counsel Stack Legal Research, https://law.counselstack.com/opinion/madden-v-prod-concrete-inc-ohioctapp-2013.