§ 45-23-37. General provisions — Administrative subdivision.
(a) Any applicant requesting approval of a proposed administrative subdivision, as defined
in this chapter, shall submit to the administrative officer the items required by
the local regulations.
(b) The application shall be certified, in writing, as complete or incomplete by the administrative
officer within a fifteen (15) day period from the date of its submission according
to the provisions of § 45-23-36(c).
(c) Review process:
(1) Within fifteen (15) days of c
Free access — add to your briefcase to read the full text and ask questions with AI
§ 45-23-37. General provisions — Administrative subdivision.
(a) Any applicant requesting approval of a proposed administrative subdivision, as defined
in this chapter, shall submit to the administrative officer the items required by
the local regulations.
(b) The application shall be certified, in writing, as complete or incomplete by the administrative
officer within a fifteen (15) day period from the date of its submission according
to the provisions of § 45-23-36(c).
(c) Review process:
(1) Within fifteen (15) days of certification of completeness, the administrative officer,
or the technical review committee, shall review the application and approve, deny
or refer it to the planning board with recommendations. The officer or committee shall
report its actions to the planning board at its next regular meeting, to be made part
of the record.
(2) If no action is taken by the administrative officer or the technical review committee
within the fifteen (15) days, the application shall be placed on the agenda of the
next regular planning board meeting.
(d) If referred to the planning board, the board shall consider the application and the
recommendations of the administrative officer and/or the technical review committee
and either approve, approve with conditions, or deny the application within sixty-five
(65) days of certification of completeness. Failure of the planning board to act within
the prescribed period constitutes approval of the administrative subdivision plan
and a certificate of the administrative officer as to the failure of the planning
board or committee to act within the required time and the resulting approval shall
be issued on request of the applicant.
(e) Denial of an application by the administrative officer and/or the technical review
committee is not appealable and requires the plan to be submitted as a minor subdivision
application.
(f) Any approval of an administrative subdivision shall be evidenced by a written decision
which shall be filed and posted in the office of the city or town clerk.
(g) Approval of an administrative subdivision expires ninety (90) days from the date of
approval unless within that period a plat in conformity with that approval is submitted
for signature and recording as specified in § 45-23-64.