This text of New Jersey § 52:32-41 (Construction contracts, timely payment to subs and suppliers, procedure) is published on Counsel Stack Legal Research, covering New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
N.J. Stat. Ann. § 52:32-41 (2026).
Text
2.
a.Prior to the issuance of a progress payment by a State agency to a prime contractor, the prime contractor shall certify to the State agency that a subcontractor or supplier has been paid any amount due from any previous progress payment and shall be paid any amount due from the current progress payment, or that there exists a valid basis under the terms of the subcontractor's or supplier's contract to withhold payment from the subcontractor or supplier and therefore payment is withheld.
b.If the prime contractor withholds payment from a subcontractor or supplier, the prime contractor shall provide to the subcontractor or supplier written notice of a withholding of payment. The notice shall detail the reason for withholding payment and state the amount of payment withheld. A copy of
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
15
§ 52:32-1.3
"Public contract" defined§ 52:32-1.4
Retaliatory discrimination§ 52:32-1.5
Rules, regulations§ 52:32-10
Certificate of use or occupancy; issuance; compliance with requirements for physically handicapped§ 52:32-13
Enforcement§ 52:32-16
Access facilities; nonapplication of act§ 52:32-17
Short title§ 52:32-18
Declaration; finding§ 52:32-19
DefinitionsCite This Page — Counsel Stack
Bluebook (online)
New Jersey § 52:32-41, Counsel Stack Legal Research, https://law.counselstack.com/statute/nj/52/52%3A32-41.