69-4-402 . Petition for relocation of overhead line. An owner of agricultural land across which an overhead utility line has been constructed may petition the district court for an order for relocation of the line for the purpose of installing an agricultural improvement. The petition shall set forth the nature of the proposed agricultural improvement, the increase in productivity of the land anticipated to result from the improvement, and a feasible alternative route, across other land to be provided by the petitioner at no cost to the owner of the overhead utility line.
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
En. 24-202 by Sec. 2, Ch. 123, L. 1975; R.C.M. 1947, 24-202.
Nearby Sections
15
§ 69-4-1001
Definitions§ 69-4-1002
Meter Security -- Data Disclosure§ 69-4-1003
Advanced Metering Devices -- Notice Required§ 69-4-104
And 69-4-105 Reserved§ 69-4-106
Definitions§ 69-4-107
Certificate Of Public Convenience And Necessity For Transmission Lines And Facilities -- Rulemaking§ 69-4-1101
Purpose -- Remedies Cumulative§ 69-4-1102
Definitions§ 69-4-1103
Liability For Bypass Or TamperingCite This Page — Counsel Stack
Bluebook (online)
Montana § 69-4-402, Counsel Stack Legal Research, https://law.counselstack.com/statute/mt/4/69-4-402.