§ 69-4-108 — Advanced Cost Approval Of Transmission And Related Facilities

Montana·Title 69 PUBLIC UTILITIES AND CARRIERS·Ch. 4 UTILITY LINES AND FACILITIES·Part 1 General Provisions

69-4-108 .  Advanced cost approval of transmission and related facilities.

(1)A public utility may apply to the commission for advanced cost approval of transmission lines and related facilities not yet procured, provided the utility complies with 69-4-107 .
(2)Within 45 days of a utility's application for advanced cost approval, the commission shall determine if the application is adequate and in compliance with the commission's minimum filing requirements. If the commission determines the application is inadequate, it shall explain the deficiencies.
(3)The commission shall issue an order within 90 days after receiving an application for transmission lines and related facilities, unless the commission determines that extraordinary circumstances warrant additional time.
(4)Subject to 6

Free access — add to your briefcase to read the full text and ask questions with AI

Montana § 69-4-108 (Advanced Cost Approval Of Transmission And Related Facilities) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

En. Sec. 3, Ch. 595, L. 2025.