69-4-107 . Certificate of public convenience and necessity for transmission lines and facilities -- rulemaking.
(1)A public utility, as defined in 69-3-101 , may request a certificate of public convenience and necessity from the commission prior to commencing actual construction work on an electric transmission facility that is rated higher than 69 kilovolts.
(2)If the utility requests a certificate of public convenience and necessity from the commission pursuant to subsection (1), the department may not make a determination regarding the requirements of subsections 75-20-301 (1)(a), (1)(d), and (1)(f).
(3)(a) Upon receiving a request from a public utility or entity, the commission shall determine within 300 days whether the construction of the proposed transmission facility is in the p
Free access — add to your briefcase to read the full text and ask questions with AI
Montana § 69-4-107 (Certificate Of Public Convenience And Necessity For Transmission Lines And Facilities -- Rulemaking) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
En. Sec. 2, Ch. 595, L. 2025.
Nearby Sections
15
§ 69-4-1001
Definitions§ 69-4-1002
Meter Security -- Data Disclosure§ 69-4-1003
Advanced Metering Devices -- Notice Required§ 69-4-104
And 69-4-105 Reserved§ 69-4-106
Definitions§ 69-4-107
Certificate Of Public Convenience And Necessity For Transmission Lines And Facilities -- Rulemaking§ 69-4-1101
Purpose -- Remedies Cumulative§ 69-4-1102
Definitions§ 69-4-1103
Liability For Bypass Or Tampering