§ 69-4-1005 — Advanced Metering Gateway Device Opt-In Provisions -- Rulemaking
Montana·Title 69 PUBLIC UTILITIES AND CARRIERS·Ch. 4 UTILITY LINES AND FACILITIES·Part 10 Requirements for Use of Advanced Metering Devices
69-4-1005 . Advanced metering gateway device opt-in provisions -- rulemaking.
(1)A utility may allow customers to opt-in to the installation of all advanced metering gateway devices located at an end user's residence or business.
(2)A utility may charge customers who opt in to advanced metering gateway device installation additional fees or charges related to the installation.
(3)If the commission determines an opt in program should be established, the commission shall adopt rules providing options, requirements, and a process for determination of fees or charges for individual customers to opt in to advanced metering gateway device installation.
(4)Utilities seeking to allow an advanced metering gateway device opt-in program shall file a report detailing the program requirements and p
Free access — add to your briefcase to read the full text and ask questions with AI
Montana § 69-4-1005 (Advanced Metering Gateway Device Opt-In Provisions -- Rulemaking) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
En. Sec. 1, Ch. 546, L. 2021.
Nearby Sections
15
§ 69-4-1001
Definitions§ 69-4-1002
Meter Security -- Data Disclosure§ 69-4-1003
Advanced Metering Devices -- Notice Required§ 69-4-104
And 69-4-105 Reserved§ 69-4-106
Definitions§ 69-4-107
Certificate Of Public Convenience And Necessity For Transmission Lines And Facilities -- Rulemaking§ 69-4-1101
Purpose -- Remedies Cumulative§ 69-4-1102
Definitions§ 69-4-1103
Liability For Bypass Or Tampering