Indiana Statutes

§ 8-1-8.4-6 — Necessity for public convenience and necessity certification; considerations for issuing a certificate

Indiana § 8-1-8.4-6
JurisdictionIndiana
Art. 1UTILITIES GENERALLY
Ch. 8.4Federally Mandated Requirements for Energy Utilities

This text of Indiana § 8-1-8.4-6 (Necessity for public convenience and necessity certification; considerations for issuing a certificate) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 8-1-8.4-6 (2026).

Text

(a)Except as provided in subsection (c), or unless an energy utility has elected to file for:
(1)a certificate of public convenience and necessity; or
(2)the recovery of costs; under another statute, an energy utility that seeks to recover federally mandated costs under section 7(c) of this chapter must obtain from the commission a certificate that states that public convenience and necessity is served by the energy utility's compliance project.
(b)The commission shall issue a certificate of public convenience and necessity under section 7(b) of this chapter if the commission finds that the compliance project allows the energy utility to comply directly or indirectly with one (1) or more federally mandated requirements. In determining whether to grant a certificate under this section,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Citizens Action Coalition of Indiana, Inc. v. Southern Indiana Gas & Electric Co.
45 N.E.3d 483 (Indiana Court of Appeals, 2015)
4 case citations

Legislative History

As added by P.L.150-2011, SEC.1. Amended by P.L.2-2023, SEC.4.