Citizens Action Coalition of Indiana, Inc. v. Southern Indiana Gas & Electric Co.

45 N.E.3d 483, 2015 Ind. App. LEXIS 696, 2015 WL 6550654
CourtIndiana Court of Appeals
DecidedOctober 29, 2015
DocketNo. 93A02-1502-EX-110
StatusPublished
Cited by4 cases

This text of 45 N.E.3d 483 (Citizens Action Coalition of Indiana, Inc. v. Southern Indiana Gas & Electric Co.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Citizens Action Coalition of Indiana, Inc. v. Southern Indiana Gas & Electric Co., 45 N.E.3d 483, 2015 Ind. App. LEXIS 696, 2015 WL 6550654 (Ind. Ct. App. 2015).

Opinion

BRADFORD, Judge.

Case Summary

[1] On January 17, 2014, Appellee-Pe-titioner Southern Indiana Gas and Electric Company d/b/a Vectren Energy Delivery of Indiana (“Vectren”), a public utility company which provides electricity to southern Indiana residents, filed a petition with Appellee the Indiana Utility Regulatory Commission (“the Commission” or “IURC”) for approval of projects to modify their current coal-powered generating stations so as to meet new EPA standards. The petition also requested financial incentives and reimbursement from ratepayers for costs associated with the projects. Appellants-Intervenors Citizens Action Coalition of Indiana, Inc., (“CAC”) Sierra Club, Inc., and Valley Watch, Inc. (collectively “Appellants”) intervened in the action and, in addition to the Indiana Office of Utility Consumer Counselor1 (“OUCC”), opposed Vectren’s petition. Appellants argued that retiring some or all of Vectren’s current coal-powered generators and replacing them with new natural gas-powered generators was a more cost-effective plan than Vectren’s proposal to install emission controls on its .current generators. Ultimately, the OUCC ceased its opposition to Vec-tren’s proposal prior to the Commission’s decision.

[2] The Commission found that Vec-tren’s proposal was reasonable and necessary, approved the proposal, and granted Vectren’s request for reimbursement of project costs. On appeal, Appellants argue that the Commission failed to make necessary findings on (1) facts material to its determination of the issues and .(2) statutory factors required to be addressed pri- or to authorizing the use of clean coal technology. In response, Vectren claims that Appellants’ appeal is moot and that the Commission made all necessary findings. We find that the Commission erred in failing to make findings on the factors listed in Indiana Code section 8-1-8.7-3 and, accordingly, we remand with instructions. ■

Facts and Procedural History i. EPA Action

[3] Vectren is a public utility company which■ .provides - electricity ■ to southern Indiana residents. . Vectren’s baseload electricity generating units include Brown unit 1, Brown unit 2, Culley unit 2, Culley unit 3, and Warrick, all of which are coal-powered generators. In 2012, Vectren received a Notice of Violation (“NOV”) issued -by the EPA alleging that Vectren’s emissions control technology at its Brown units was noncompliant with EPA rules governing- sulfuric acid emissions. The EPA also served Vectren with a Clean Air Act (“CAA”) Information Request that highlighted concerns with the sulfur emissions at Culley unit 3. Vectren disputed the allegations raised in the NOV. At some point after Vectren’s filing of the instant petition and prior to the Commission’s ultimate decision, Vectren and the EPA reached a settlement in principle to resolve the outstanding allegations raised in the NOV and the information request. Vec-tren is also subject to additional recent federal mandates regarding emissions standards, specifically, the Mercury - and Air Toxics Standards - rule (“MATS”) and the Water Pollution Control Act which limit mercury emissions in the air and water, respectively.

it Vectren’s Petition

[4] On January 17, 2014, Vectren filed a petition with the Commission for approv[486]*486al of modifications to four of its coal-powered electricity generating facilities— Brown units 1 and 2, Culley unit 3, and Warrick — in order to comply with the MATS rule, the NOV, and the CAA information request.

3. Relief requested. Vectren requests approval of clean energy projects and issuance of a CPCN [certificate of public convenience and necessity] to construct, install, and use CCT [clean coal technology] to allow Vectren to comply with the United State Environmental Protection Agency (“EPA”) Mercury and Air Tox-ics Standards (“MATS”) rule, the Notice of Violation (“NOV”) received for Brown, and a Clean Air Act (“CAA”) § 114 Information Request received for Culley related to a 2003 federal consent decree.
Specifically, Vectren requests approval to construct, install, and operate the following projects on the Brown Units: an organo-sulfide injection system to inject an organo-sulfide solution into each scrubber at Brown units 1 and 2 to address mercury (“Hg”) re-emission ...; a soda ash injection system for sulfur trioxide (“S03”) mitigation at Brown units 1 and 2; and a hydrogen bromide injection system on Brown unit 2 to aid the conversion of elementary mercury to oxidized form (collectively, the “Brown Air Projects”).
Vectren requests approval to construct, install and operate the following projects on the Culley Units: an organo-sulfide injection system ... at the combined scrubber at Culley units 2 and 3 to address Hg re-emission ...; and a hydrated lime injection system for S03 mitigation at Culley unit 3 (collectively, the “Culley Air Projects”)....
Vectren requests approval for recovery of its portion of the costs for Alcoa[2] to install an organo-sulfide system at War-rick unit 4 (“Wairick Project”).
In addition, Vectren requests approval to construct, install, and operate equipment necessary to control wastewater discharges from the plants at both Brown and Culley as required to comply with National Pollution Discharge Elimination System (“NPDES”) Hg limitations. [“Brown Water Project” and “Culley Water Project”]_In this Order, we refer to the Brown and Culley Air Projects, the Warrick Project, and the Brown and Culley Water Projects, collectively, as the “Mandated Projects”.[3]
Vectren also requests approval of certain financial incentives and approval to defer project costs, including depreciation and operations and maintenance (“0 & M”) expenses related to the Mandated Projects (“Mandated Project Costs”), for a period up to December 31, 2020, by which time Vectren will propose a recovery mechanism for such costs. In the alternative and to the extent deferral of the Mandated Projects Costs is not permitted, Vectren requests authority to recover the reasonably incurred O & M expenses, including consumables, and depreciation expenses relating to the Mandated Projects through a rate adjustment mechanism. Finally, Vectren requests ongoing review for the Mandated Projects and specific accounting treatment of under/over recovery of the Mandated Projects Costs.

Appellants’ App. pp. 10-11, Order of the Commission pp. 3-4.

[487]*487¶ [5] In April of 2014, CAC, Valley Watch, and Sierra Club intervened in the proceedings and opposed Vectren’s proposal.

iii. Evidence Presented to the Commission

[6] In order to comply with EPA requirements, Vectren could either install additional pollution controls on its existing units or replace its existing units with new electricity-generating sources (e.g., natural gas, wind, solar, etc.) that would be in compliance with the emissions requirements. Vectren hired engineering firm Black & Veatch (“B & V”) to compare the total ratepayer cost and relative risk of its proposal to modify existing units (as described above) versus the cost and risks associated with retiring and replacing the noncompliant units. Alcoa engaged the engineering firm Burns & McDonnell for the same purpose with regards to the Warrick unit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
45 N.E.3d 483, 2015 Ind. App. LEXIS 696, 2015 WL 6550654, Counsel Stack Legal Research, https://law.counselstack.com/opinion/citizens-action-coalition-of-indiana-inc-v-southern-indiana-gas-indctapp-2015.