(a)A public utility shall petition the commission for approval of the public utility's TDSIC plan for eligible transmission, distribution, and storage improvements. A plan submitted under this subsection may include for approval a targeted economic development project described in section 11 of this chapter.
(b)Following notice and hearing, and not more than two hundred ten (210) days after the public utility petitions the commission under subsection (a), the commission shall issue an order on the petition. The order must include the following:
(1)A finding of the best estimate of the cost of the eligible improvements included in the plan.
(2)A determination whether public convenience and necessity require or will require the eligible improvements included in the plan.
(3)A determinat

Free access — add to your briefcase to read the full text and ask questions with AI

Indiana § 8-1-39-10 (Petition for approval of TDSIC plan; notice, hearing, and order; approval and authorization of TDSIC treatment; targeted economic development projects; termination of existing plan) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

NIPSCO Industrial Group v. Northern Indiana Public Service Company
78 N.E.3d 730 (Indiana Court of Appeals, 2017)
3 case citations
Indiana Gas & Electric Company v. Indiana Utility Regulatory Commission
75 N.E.3d 568 (Indiana Court of Appeals, 2017)
2 case citations

Legislative History

As added by P.L.133-2013, SEC.5. Amended by P.L.89-2019, SEC.4.