§ 8-1-39-10 — Petition for approval of TDSIC plan; notice, hearing, and order; approval and authorization of TDSIC treatment; targeted economic development projects; termination of existing plan
(a)A public utility shall petition the
commission for approval of the public utility's TDSIC plan for eligible
transmission, distribution, and storage improvements. A plan submitted
under this subsection may include for approval a targeted economic
development project described in section 11 of this chapter.
(b)Following notice and hearing, and not more than two hundred
ten (210) days after the public utility petitions the commission under
subsection (a), the commission shall issue an order on the petition. The
order must include the following:
(1)A finding of the best estimate of the cost of the eligible
improvements included in the plan.
(2)A determination whether public convenience and necessity
require or will require the eligible improvements included in the
plan.
(3)A determinat
Free access — add to your briefcase to read the full text and ask questions with AI
Indiana § 8-1-39-10 (Petition for approval of TDSIC plan; notice, hearing, and order; approval and authorization of TDSIC treatment; targeted economic development projects; termination of existing plan) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Related
NIPSCO Industrial Group, and, Indiana Office of Utility Consumer Counselor v. Northern Indiana Public Service Company
31 N.E.3d 1 (Indiana Court of Appeals, 2015)
NIPSCO Industrial Group v. Northern Indiana Public Service Company
78 N.E.3d 730 (Indiana Court of Appeals, 2017)
Indiana Gas & Electric Company v. Indiana Utility Regulatory Commission
75 N.E.3d 568 (Indiana Court of Appeals, 2017)
NIPSCO Industrial Group v. Northern Indiana Public Service Company and Office of the Utility Consumer Counselor
104 N.E.3d 603 (Indiana Court of Appeals, 2018)
Legislative History
As added by P.L.133-2013, SEC.5. Amended by P.L.89-2019,
SEC.4.
Nearby Sections
15
§ 8-1-1-11
Staff of commission§ 8-1-1-12
Repealed§ 8-1-1-13
Repealed§ 8-1-1-14
Annual report§ 8-1-1-15
Implementing rules; duration§ 8-1-1-16
Commission to consider effect of governmental requirements upon
utility's operational expenses§ 8-1-1-4
Repealed§ 8-1-1-4.1
Payment of expenses§ 8-1-1-6
Repealed