Indiana Gas & Electric Company v. Indiana Utility Regulatory Commission

75 N.E.3d 568, 2017 WL 1506037, 2017 Ind. App. LEXIS 179
CourtIndiana Court of Appeals
DecidedApril 27, 2017
DocketCourt of Appeals Case 93A02-1604-EX-943
StatusPublished
Cited by2 cases

This text of 75 N.E.3d 568 (Indiana Gas & Electric Company v. Indiana Utility Regulatory Commission) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Indiana Gas & Electric Company v. Indiana Utility Regulatory Commission, 75 N.E.3d 568, 2017 WL 1506037, 2017 Ind. App. LEXIS 179 (Ind. Ct. App. 2017).

Opinion

Statement of the Case

Pyle, Judge.

This case concerns the interpretation of Indiana Code § 8-1-39-1 et seq, the Transmission, Distribution, and Storage System Improvement Charges and Deferrals (“TDSIC”) statute (“TDSIC statute”). Specifically, the parties dispute whether a utility may, once it has established a seven-year plan for its transmission, distribution, and storage system improvements under Section 10 of the TDSIC statute, update its seven-year plan by adding new projects under Section 9 of the TDSIC statute. Appellants/Plaintiffs, Indiana Gas Company, Inc. (“Vectren North”) and Southern Indiana Gas & Electric Company (“Vectren South”) (collectively, “Vectren”), filed a petition with the Appellee, Indiana Utility Regulatory Commission (“the Commission”), under Section 9 of the TDSIC statute, requesting to update their seven-year Section 10 TDSIC plan with additional projects. The Commission partially denied Vectren’s petition, and now Vectren appeals the Commission’s denial. The Indiana Office of Utility Consumer Counselor (“OUCC”) is also an Appellee, and we will refer to the Commission and the OUCC collectively as “the Appellees.”

On appeal, Vectren argues that the Commission erred when it partially denied their petition because the Commission misinterpreted the TDSIC statute. They also argue that the Commission should be barred from denying their petition on the basis of res judicata. Because we conclude that the Commission did not misinterpret the TDSIC statute and the doctrine of res judicata does not apply, we affirm the Commission’s decision.

We affirm.

Issues

1. Whether the Commission erred when it partially denied Vectren’s petition to update its seven-year TDSIC plan.
2. Whether the Commission should be barred from denying Vectren’s petition to add new projects under the doctrine of res judicata.

Facts 1

Traditionally, a utility’s . rates charged to customers are adjusted through *572 periodic general rate cases. These can be “expensive, time consuming, and sometimes result in large, sudden rate hikes for customers.” NIPSCO Indus. Group v. N. Ind. Pub. Serv. Co., 31 N.E.3d 1, 4 (Ind. Ct. App. 2015). Another way to adjust rates is through a “tracker” proceeding, which is a cost-recovery proceeding that allows smaller increases in rates so that a utility can recover costs for specific projects between general rate case proceedings. 2 Id.

In 2013, the Legislature enacted the TDSIC statute, Indiana Code § 8-1-39-1 et seq, which allows a utility to petition for a tracker proceeding for new or replacement electric or gas transmission, distribution, or storage projects, and thereby recover its costs in a timelier manner than through a general rate case. Under Section 10 of the TDSIC statute (“Section 10”), a utility may create a seven-year plan for its predicted transmission, distribution, and storage improvements and may seek approval of that plan from the Commission. Ind. Code § 8-1-39-10. Following notice and a hearing on the petition, the Commission is required to issue an order that includes the following:

(1)A finding of the best estimate of the cost of the eligible improvements included in the plan.
(2) A determination whether public convenience and necessity require or will require the eligible improvements included in the plan.
(3) A determination whether the estimated costs of the eligible improvements included in the plan are justified by incremental benefits attributable to the plan.

I.C. § 8-l-39-10(b). Section 10 provides that “[i]f the [Cjommission determines that the public utility’s seven (7) year plan is reasonable, the [Cjommission shall approve the plan and designate the eligible transmission, distribution, and storage improvements included in the plan as eligible for TDSIC treatment.” Id.

Once the Commission has approved a utility’s Section 10 seven-year plan, the utility may recover 80% of the capital expenditures and costs approved by the Commission, although it must wait to recover the remaining 20% during its next general rate case. During the seven years of the plan, the utility may petition to recover 80% of its costs or for an “update” of the plan under Section 9 of the TDSIC statute (“Section 9”). A utility’s Section 9 petition must, in relevant part:

* ⅛ #
(2) include the public utility’s seven (7) year plan for eligible transmission, distribution, and storage system improvements; and
(3) identify projected effects of the plan described in subdivision
(2) on retail rates and charges.

I.C. § 8-l-39-9(a). The utility is also required to “update” its seven-year plan “with each petition the public utility files under [Section 9j.” Id.

Vectren North and Vectren South are two Indiana gas utilities that do business as Vectren Energy Delivery. of Indiana and that provide Indiana consumers with natural gas utility services. The two utilities received approval for their seven-year TDSIC plans in 2013 in Cause Numbers 44429 and 44430, respectively. *573 These causes were largely consolidated before the Commission and are completely consolidated on appeal.

Vectren’s original seven-year plan included project-by-project details for only the first year and contained cost estimates for years two through seven. In its order approving the plan, the Commission found that “the projects in Years 2 through 7 were presumed to be eligible improvements subject to further definition and specifics being provided in updates to the Plan.” (App. Vol. 2 at 10). It approved an update process whereby Vectren would “move [its] upcoming year-specific projects into a work-order level of detail,” each year, similar to the work-order level of detail it had provided for year one. (App. Vol. 2 at 62).

Subsequently, the OUCC appealed the Commission’s approval of Vectren’s seven-year plan on grounds that are not relevant for the instant appeal. However, Vectren Industrial Group intervened in that appeal and argued that the Commission had erred in approving the seven-year plan because it lacked sufficient detail. See Ind. Office of Util. Consumer Counselor v. S. Ind. Gas & Elec. Co., No. 93A02-1409-EX-668, 36 N.E.3d 319 (Ind. Ct. App. June 11, 2015).

In the meantime, while the appeal of Vectren’s seven-year plan was pending, Vectren petitioned for its first update to the plan (“TDSIC Update-1”) under Section 9 of the TDSIC statute. On January 14, 2015, the Commission approved the update, which included new projects that were not a part of Vectren’s seven-year plan.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Benjamin P. Ingram and Ben's Quarry, LLC v. Diamond Equipment, Inc.
118 N.E.3d 1 (Indiana Court of Appeals, 2018)
NIPSCO Industrial Group v. Northern Indiana Public Service Company
78 N.E.3d 730 (Indiana Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
75 N.E.3d 568, 2017 WL 1506037, 2017 Ind. App. LEXIS 179, Counsel Stack Legal Research, https://law.counselstack.com/opinion/indiana-gas-electric-company-v-indiana-utility-regulatory-commission-indctapp-2017.