Ind. Code § 8-1-3-1 (2026).
Text
Any person, firm, association, corporation,
limited liability company, city, town, or public utility adversely
affected by any final decision, ruling, or order of the commission may,
within thirty (30) days from the date of entry of such decision, ruling,
or order, appeal to the court of appeals of Indiana for errors of law
under the same terms and conditions as govern appeals in ordinary civil
actions, except as otherwise provided in this chapter and with the right
in the losing party or parties in the court of appeals to apply to the
supreme court for a petition to transfer the cause to said supreme court
as in other cases. An assignment of errors that the decision, ruling, or
order of the commission is contrary to law shall be sufficient to present
both the sufficiency of the facts foun
Free access — add to your briefcase to read the full text and ask questions with AI
Related
McClain v. Review Board of the Indiana Department of Workforce Development
693 N.E.2d 1314 (Indiana Supreme Court, 1998)
City of Evansville v. Southern Indiana Gas & Electric Co.
339 N.E.2d 562 (Indiana Court of Appeals, 1976)
Citizens Action Coalition of Indiana, Inc. v. Northern Indiana Public Service Co.
485 N.E.2d 610 (Indiana Supreme Court, 1985)
L. S. Ayres & Co. Et Al. v. IPALCO Et Al.
351 N.E.2d 814 (Indiana Court of Appeals, 1976)
Northern Indiana Public Service Co. v. United States Steel Corp.
907 N.E.2d 1012 (Indiana Supreme Court, 2009)
Indiana Telephone Corp. v. Indiana Bell Telephone Co.
358 N.E.2d 218 (Indiana Court of Appeals, 1976)
South Eastern Indiana Natural Gas Co. v. Ingram
617 N.E.2d 943 (Indiana Court of Appeals, 1993)
Indiana Bell Telephone Co. v. Friedland
373 N.E.2d 344 (Indiana Court of Appeals, 1978)
Office of Public Counsellor v. Indiana & Michigan Electric Co.
416 N.E.2d 161 (Indiana Court of Appeals, 1981)
Citizens Energy Coalition, Inc. v. Indiana & Michigan Electric Co.
396 N.E.2d 441 (Indiana Court of Appeals, 1979)
Citizens Action Coalition of Indiana, Inc. v. Public Service Commission
425 N.E.2d 178 (Indiana Court of Appeals, 1981)
Indiana Gas Company, Inc. and Southern Indiana Gas and Electric Company v. Indiana Finance Authority and Indiana Gasification, LLC
999 N.E.2d 63 (Indiana Supreme Court, 2013)
Knox County Rural Electric Membership Corp. v. PSI Energy, Inc.
663 N.E.2d 182 (Indiana Court of Appeals, 1996)
Indiana Bell Telephone Co. v. T. A. S. I., Inc.
433 N.E.2d 1195 (Indiana Court of Appeals, 1982)
Citizens Action Coalition of Indiana, Inc. v. Northern Indiana Public Service Co.
804 N.E.2d 289 (Indiana Court of Appeals, 2004)
Micronet, Inc. v. Indiana Utility Regulatory Commission
866 N.E.2d 278 (Indiana Court of Appeals, 2007)
Home Builder's Ass'n of Indiana, Inc. v. Indiana Utility Regulatory Commission
544 N.E.2d 181 (Indiana Court of Appeals, 1989)
PSI Energy, Inc. v. Indiana Office of the Utility Consumer Counsel
764 N.E.2d 769 (Indiana Court of Appeals, 2002)
GOLD BOND BLDG. PROD. DIV., ETC. v. Review Bd., Ind.
349 N.E.2d 258 (Indiana Court of Appeals, 1976)
Charles W. Cole & Son, Inc. v. Indiana & Michigan Electric Co.
426 N.E.2d 1349 (Indiana Court of Appeals, 1981)
Nearby Sections
15
§ 8-1-1-11
Staff of commission§ 8-1-1-12
Repealed§ 8-1-1-13
Repealed§ 8-1-1-14
Annual report§ 8-1-1-15
Implementing rules; duration§ 8-1-1-16
Commission to consider effect of governmental requirements upon
utility's operational expenses§ 8-1-1-4
Repealed§ 8-1-1-4.1
Payment of expenses§ 8-1-1-6
RepealedCite This Page — Counsel Stack
Bluebook (online)
Indiana § 8-1-3-1, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/8-1-3-1.