PSI Energy, Inc. v. Indiana Office of the Utility Consumer Counsel

764 N.E.2d 769, 2002 Ind. App. LEXIS 392, 2002 WL 387394
CourtIndiana Court of Appeals
DecidedMarch 13, 2002
Docket93A02-0103-EX-182
StatusPublished
Cited by8 cases

This text of 764 N.E.2d 769 (PSI Energy, Inc. v. Indiana Office of the Utility Consumer Counsel) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PSI Energy, Inc. v. Indiana Office of the Utility Consumer Counsel, 764 N.E.2d 769, 2002 Ind. App. LEXIS 392, 2002 WL 387394 (Ind. Ct. App. 2002).

Opinion

OPINION

MATHIAS, Judge.

PSI Energy, Inc. ("PSI") appeals from part of the Indiana Utility Regulatory Commission's ("the IURC") interim order, in which the IURC denied PSI recovery of demand costs attributable to purchased power contracts entered into by PSI in April, May, and August of 1999. PSI's issue on appeal, restated, is whether the TIURC's denial of PSI's request to recover demand costs incurred to purchase power to meet peak demands during the summer months of 1999 was contrary to law, arbitrary and capricious.

We affirm.

Facts and Procedural History

The facts most favorable to the IURC's decision reveal that in December of 1998, PSI's Operating Committee ("the Committee") met to review their expected operating conditions for the upcoming winter of 1998/1999 and summer of 1999. Among other things, the Committee determined that PSI would need additional resources to meet the forecasted summer load for 1999. The Committee approved purchases needed to assure that PSI would be able to maintain the forecasted twelve percent operating reserve margin needed during the peak summer period of 1999. Appellant's App. p. 21. The majority of the power purchases for the 1999 peak period were completed by March, May and August of 1999. Id. at 84.

On May 28, 1999, PSI filed a Petition with the IURC requesting approval of a purchased power tracking mechanism that would allow PSI to recover, from customers, demand costs attributable to purchased power contracts. PSI also specifically requested that it be allowed to recover the demand costs attributable to the purchased power contracts it entered for the peak periods of 1999, 2000, and 2001. Additionally, PSI proposed to file on a periodic basis, for review by the IURC, its actual purchase arrangements for future peak periods.

The IURC held a hearing on this cause on December 9, 1999, and issued an interim order on May 31, 2000. Although the IURC approved PSI's proposed tracking mechanism on an interim basis to be applied to purchased power contracts entered into for peak periods of 2000, the IURC denied PSI's request for recovery of previously incurred demand costs attribut *772 able to purchased power contracts for the 1999 peak period. The IURC found that even though there were legitimate reasons why PSI's proceeding took a long time to process (about one year from petition filing to Commission interim order), with regard to recovery of the 1999 demand costs, "PSI should have filed its case in a more timely manner with an appropriate review period for this Commission to be able to make a determination of reasonableness." Id. at 21.

Nevertheless, the IURC found "that PSI's proposed tracker is reasonable, just and proper, and should be approved for the summer of 2000, provided that PSI includes a mitigation credit in its tracker." Id. at 24. Importantly, the mitigation credit referred to in the finding was not offered by PSI, but rather, was proposed by the Office of the Utility Consumer Counselor ("the OUCC") during the pen-dency of PSI's petition. 1 The IURC found "[that the mitigation credit should be calculated on an after-the-fact basis and should reflect profits from off-system sales made from PSI generation which has been 'freed up' as a result of tracked power purchases." Id. The IURC further found that PSI's request for recovery of demand costs attributable to purchased power contracts entered for the peak summer period of 2000 was appropriately sought prior to the period for which the proposed purchases were to be used. Id. at 21.

Next, the IURC held that in conformance with PSI's proposal, it should file a subdocket in order to periodically file its actual purchase arrangements for the upcoming peak months for IURC review. Id. at 24. The IURC found that thereafter, it would hold a hearing to scrutinize the reasonableness of and need for the contracts, including the reasonableness of the prices. Then, after issuing an order on reasonableness, the IURC would hold another "hearing for purposes of an after the fact review of the summer, 2000 purchases with any offsetting mitigation ered-it." Id. The IURC found that after its review of summer 2000 purchases, it would determine whether PSI would be allowed to continue the tracker mechanism. Id.

On June 20, 2000, PSI filed a Petition for Rehearing and/or Reconsideration and the OUCC filed a Petition for Reconsideration. PSI argued that the IURC erred when it denied recovery of PSI's 1999 demand costs attributable to the purchased power contracts. PSI specifically argued that it was not feasible or practical for it to have filed its original petition any earlier than May of 1999 because it had not completed the actual power purchases required to meet the operating reserve margin of twelve percent until March, April and August 1999. Therefore, PSI requested that the IURC reconsider its finding that PSI failed to timely file its request for recovery of its 1999 costs attributable to purchased power contracts for the peak periods of 1999. PSI also argued that the IURC's after-the-fact reasonableness determination regarding its 1999 costs was inappropriate, and therefore, requested that the IURC reconsider its finding that there was insufficient evi-denee upon which the IURC could base its decision.

In its Petition for Reconsideration, the OUCC argued that the IURC should not adopt PSI's proposed purchased power tracker mechanism because the tracker would require "customers to pay for large amounts of purchase power irrespective of *773 whether that power is used to satisfy retail Indiana demand for electricity." Id. at 27. The OUCC also argued that it never had an opportunity to respond to PSI's testimony regarding the mitigation credit or to present any alternative mitigation credits. Id. at 28.

On February 21, 2001, the IURC issued its Order on Petitions for Reconsideration. The IURC denied PSI's request for Rehearing and/or Reconsideration, finding that PSI was merely reiterating arguments it had made throughout the proceeding. The IURC also found that it was not necessary to rule on the OUCC's petition because the OUCC would have ample opportunity to present evidence regarding the mitigation eredit in a subdocket, which had already been scheduled for hearing on March 15, 2001.

PSI filed this appeal on March 28, 2001. PSI now argues that the IURC's denial of its recovery of 1999 purchased power demand costs was contrary to law, arbitrary and capricious. PSI also argues that the IURC's summary denial of PSI's Petition for Rehearing and/or Reconsideration was arbitrary and capricious. Additional facts will be provided as necessary. '

Standard of Review

Our review of an administrative decision is limited to whether the agency based its decision on substantial evidence, whether the agency's decision was arbitrary and capricious, and whether it was contrary to any constitutional, statutory, or legal principle. Ind. Civil Rights Comm'n v. Marion County Sheriff's Dep't, 644 N.E.2d 913, 915 (Ind.Ct.App.1994), trans. denied (citation omitted). We are not allowed to conduct a trial de novo, but rather, we defer to an agency's fact-finding, so long as its findings are supported by substantial evidence. Id. (citation omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
764 N.E.2d 769, 2002 Ind. App. LEXIS 392, 2002 WL 387394, Counsel Stack Legal Research, https://law.counselstack.com/opinion/psi-energy-inc-v-indiana-office-of-the-utility-consumer-counsel-indctapp-2002.