(a)A contractor for construction of a system
must guarantee the contractor's workmanship and all materials used in
the work.
(b)The guarantee required under subsection (a) must be in the
following form:
"The contractor warrants the contractor's workmanship and all
materials used in the work and agrees that during the guarantee
period specified, the contractor will, at the contractor's own
expense, make all repairs that may become necessary by reason
of improper workmanship or defective materials. The
maintenance obligation, however, does not include repair of any
damage resulting from any force or circumstance beyond the
control of the contractor, nor is the contractor a guarantor of the
plans and specifications furnished by the county.".
Free access — add to your briefcase to read the full text and ask questions with AI
Indiana § 36-9-40-14 (Contractor guarantee of workmanship and materials) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
As added by P.L.7-2002, SEC.1.
Nearby Sections
15
§ 36-1-10-1
Application of chapter§ 36-1-10-10
Plans, specifications, and estimates for structures, systems, and
transportation projects§ 36-1-10-11
Property held in fee simple; sale procedure§ 36-1-10-12
Lease in anticipation of acquisition or construction of structure, system,
or transportation project§ 36-1-10-13
Hearing; procedure; execution of lease§ 36-1-10-17
Annual appropriation and tax levy§ 36-1-10-18
Tax exemption of leased structures, systems, and transportation
projects; taxation of rental paid lessor§ 36-1-10-19
Assignment or conveyance of lease; conveyance of structure, system,
or transportation project§ 36-1-10-2
Definitions§ 36-1-10-20
Repealed