§ 36-9-39-29 — Contractors; submission of monthly estimates of work done; issuance of certificates in payment; negotiability; interest; retainage

Indiana § 36-9-39-29
JurisdictionIndiana
Title 36LOCAL GOVERNMENT
Art. 9TRANSPORTATION AND PUBLIC WORKS
Ch. 39Barrett Law Funding for Municipal Sewers

This text of Indiana § 36-9-39-29 (Contractors; submission of monthly estimates of work done; issuance of certificates in payment; negotiability; interest; retainage) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 36-9-39-29 (2026).

Text

(a)A contractor for construction under this chapter is entitled to monthly estimates of the work done during each month. The estimates shall be made by the engineer and approved by the municipal works board.
(b)The works board shall issue to the contractor certificates for sixty-five percent (65%) of the amount shown by the estimates to be due to the contractor. The contractor is entitled to receive the amounts named in the certificates in cash or sewer improvement bonds to be collected or issued by the municipality, as is provided for in the construction of street, alley, and other improvements.
(c)Certificates issued under this section (or under IC 36-9-21 before its repeal in 1993) are negotiable instruments.
(d)Interest on the certificates is payable out of the contract price and t

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.98-1993, SEC.10. Amended by P.L.1-1994, SEC.183.