(a)A contractor for construction under this chapter is entitled to monthly estimates of the work done during each month. The estimates shall be made by the engineer and approved by the municipal works board.
(b)The works board shall issue to the contractor certificates for sixty-five percent (65%) of the amount shown by the estimates to be due to the contractor. The contractor is entitled to receive the amounts named in the certificates in cash or sewer improvement bonds to be collected or issued by the municipality, as is provided for in the construction of street, alley, and other improvements.
(c)Certificates issued under this section (or under IC 36-9-21 before its repeal in 1993) are negotiable instruments.
(d)Interest on the certificates is payable out of the contract price and t

Free access — add to your briefcase to read the full text and ask questions with AI

Indiana § 36-9-39-29 (Contractors; submission of monthly estimates of work done; issuance of certificates in payment; negotiability; interest; retainage) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

As added by P.L.98-1993, SEC.10. Amended by P.L.1-1994, SEC.183.