(a)If repairs become necessary, the unit must give written notice to the contractor to make the repairs. If the contractor fails to begin the repairs not later than thirty (30) days after the notice is received, the unit may do the following:
(1)Make the repairs using the unit's own employees or an independent contractor.
(2)Recover from the contractor and the contractor's sureties the reasonable cost of the repairs and the cost of the supervision and inspection of the repairs.
(b)At the expiration of the guarantee period, the unit has sixty (60) days in which to notify the contractor of any necessary repairs.
(c)This subsection does not apply to a county. If the repairs necessary to be made at the expiration of the guarantee period amount to more than one-half (1/2) the surface of on

Free access — add to your briefcase to read the full text and ask questions with AI

Indiana § 36-9-36-26 (Repairs by contractor) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

As added by P.L.98-1993, SEC.7.