§ 36-9-27-50 — Reconstruction of drains; preparation of schedule of assessments and damages

Indiana·Title 36 LOCAL GOVERNMENT·Art. 9 TRANSPORTATION AND PUBLIC WORKS·Ch. 27 Drainage Law

When the county surveyor files a reconstruction report, the county surveyor shall consult with the board, and the board shall take the following actions:

(1)Prepare a schedule of assessments containing a description of each tract of land determined to be benefited by the reconstruction, and the name and address of the owner of the land. The name, address, and description shall be taken from the county surveyor's report. The board shall enter in the assessment schedule the percentage of the total cost of the reconstruction to be assessed against each tract of land, with the percentage to be based upon the benefit accruing to the land from the reconstruction. The percentage allocated to all lands benefited must be at least one hundred percent (100%) and as near to one hundred percent (100%)

Free access — add to your briefcase to read the full text and ask questions with AI

Indiana § 36-9-27-50 (Reconstruction of drains; preparation of schedule of assessments and damages) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Johnson v. Kosciusko County Drainage Board
594 N.E.2d 798 (Indiana Court of Appeals, 1992)
7 case citations
Panhandle Eastern Pipe Line Co. v. Madison County Drainage Board
898 F. Supp. 1302 (S.D. Indiana, 1995)
4 case citations
Crowel v. Marshall County Drainage Board
951 N.E.2d 290 (Indiana Court of Appeals, 2011)
2 case citations