This text of Indiana § 36-9-27-103 (Construction, reconstruction, or maintenance projects for regulated drains; hearings required) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 36-9-27-103 (2026).

Text

Notwithstanding any other provision of this chapter, after the establishment of a cumulative drainage fund, a hearing shall be held before the board undertakes any project to construct or reconstruct a regulated drain or to maintain a regulated drain when the total cost of the maintenance project is more than twenty-five thousand dollars ($25,000). The board shall:

(1)publish a notice of the hearing in accordance with IC 5-3-1; and
(2)mail a notice of the hearing, at least fifteen (15) days before the hearing, to the owner of each piece of property adjoining the proposed or established regulated drain. [Pre-Local Government Recodification Citation: 19-4-10.1-4 part.] As added by Acts 1981, P.L.309, SEC.101. Amended by Acts 1981, P.L.45, SEC.84; P.L.206-1984, SEC.11; P.L.154-1993, SEC.9.

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Indiana § 36-9-27-103, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/36-9-27-103.