§ 36-7-4-1109.3 — Appeal of granted permit; tolling of time for commencing and completing permitted use; approved permitted use as lawful use while appeal pending

Indiana § 36-7-4-1109.3
JurisdictionIndiana
Title 36LOCAL GOVERNMENT
Art. 7PLANNING AND DEVELOPMENT
Ch. 4Local Planning and Zoning

This text of Indiana § 36-7-4-1109.3 (Appeal of granted permit; tolling of time for commencing and completing permitted use; approved permitted use as lawful use while appeal pending) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 36-7-4-1109.3 (2026).

Text

3.

(a)This section applies if:
(1)a zoning ordinance establishes a time within which an applicant must obtain a permit or commence or complete a permitted use; and
(2)the local authority's decision to grant the applicant the permit is appealed.
(b)The time specified in the zoning ordinance for:
(1)commencing a permitted use is tolled to allow the permitted use to be commenced:
(A)upon the start of actual construction of the use as approved; and
(B)not later than two (2) years after the date of the final disposition of all appeals of the permitting authority's decision; and
(2)completing a permitted use may not begin to run until actual construction has started. Any zoning ordinance to the contrary is invalid or unenforceable.
(c)Upon approval of a permit, the approved permitted us

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.202-2025, SEC.19.