(a)If, in the course of the construction,
reconstruction, or repair of a public work project, it becomes necessary
to change or alter the original specifications, a change order may be
issued to add, delete, or change an item or items in the original
contract. The change order becomes an addendum to the contract and
must be approved and signed by the board and the contractor.
(b)If a licensed architect or engineer is assigned to the public work
project, the change order must be prepared by that person.
(c)A change order may not be issued before commencement of the
actual construction, reconstruction, or repairs except in the case of an
emergency. In that case, the board must make a declaration, and the
board's minutes must show the nature of the emergency.
(d)The total of all change or
Free access — add to your briefcase to read the full text and ask questions with AI
Indiana § 36-1-12-18 (Change or alteration of specifications; change orders) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Related
Town of New Ross v. Ferretti
815 N.E.2d 162 (Indiana Court of Appeals, 2004)
Legislative History
As added by P.L.329-1985, SEC.24.
Nearby Sections
15
§ 36-1-10-1
Application of chapter§ 36-1-10-10
Plans, specifications, and estimates for structures, systems, and
transportation projects§ 36-1-10-11
Property held in fee simple; sale procedure§ 36-1-10-12
Lease in anticipation of acquisition or construction of structure, system,
or transportation project§ 36-1-10-13
Hearing; procedure; execution of lease§ 36-1-10-17
Annual appropriation and tax levy§ 36-1-10-18
Tax exemption of leased structures, systems, and transportation
projects; taxation of rental paid lessor§ 36-1-10-19
Assignment or conveyance of lease; conveyance of structure, system,
or transportation project§ 36-1-10-2
Definitions§ 36-1-10-20
Repealed