(a)If, in the course of the construction, reconstruction, or repair of a public work project, it becomes necessary to change or alter the original specifications, a change order may be issued to add, delete, or change an item or items in the original contract. The change order becomes an addendum to the contract and must be approved and signed by the board and the contractor.
(b)If a licensed architect or engineer is assigned to the public work project, the change order must be prepared by that person.
(c)A change order may not be issued before commencement of the actual construction, reconstruction, or repairs except in the case of an emergency. In that case, the board must make a declaration, and the board's minutes must show the nature of the emergency.
(d)The total of all change or

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Town of New Ross v. Ferretti
815 N.E.2d 162 (Indiana Court of Appeals, 2004)
18 case citations

Legislative History

As added by P.L.329-1985, SEC.24.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Indiana § 36-1-12-18, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/36-1-12-18.