Colorado Statutes

§ 8-14-103 — Flooring - hoisting of materials - regulations

Colorado·Title 08 Labor and·Art. Protection of Building Employees
(1)All contractors and owners, when constructing buildings in cities where the plans and specifications require the floors to be arched between the beams thereof or where the floors or filling in between the floors are of fireproof material or brick work, shall complete the flooring or filling in as the building progresses to not less than within three tiers of beams below that on which the iron work is being erected. If the plans and the specifications of the buildings do not require filling in between the beams of floors with brick or fireproof material, all contractors for carpenter work in the course of construction shall lay the underflooring thereof on each story as the building progresses to not less than within two stories below the one to which the building has been ere

Free access — add to your briefcase to read the full text and ask questions with AI

Colorado § 8-14-103 (Flooring - hoisting of materials - regulations) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

Source: L. 13: p. 449, � 3. C.L. � 4188. CSA: C. 97, � 119. CRS 53: � 80-16-3. C.R.S. 1963: � 80-13-3.