Zeck v. Smith Custom Homes & Design, L.L.C.

2022 Ohio 622
Ohio Court of Appeals·Decided March 3, 2022·No. 110574·Published·Cited by 11 cases

Opinion

COURT OF APPEALS OF OHIO

EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA

DARREN ZECK, ET AL., :

Petitioners-Appellants, :

No. 110574

v. :

SMITH CUSTOM HOMES & DESIGN, LLC, :

Respondent-Appellee. :

JOURNAL ENTRY AND OPINION

JUDGMENT: AFFIRMED

RELEASED AND JOURNALIZED: March 3, 2022

Civil Appeal from the Cuyahoga County Court of Common Pleas Case No. CV-20-939797

Appearances:

Seeley, Savidge, Ebert & Gourash Co., LPA, and Jeffrey S.

Moeller, for appellants.

Berns, Ockner & Greenberger, LLC, and Douglas V.

Bartman, for appellee.

MARY J. BOYLE, J.:

Petitioners-appellants, Darren and Nicole Zeck (“the Zecks”), appeal the trial court’s judgment entry denying their application to vacate the arbitration award (in part) and confirming the arbitration award in favor of respondent-

appellee, Smith Custom Homes & Design, LLC (“Smith”). For the reasons set forth below, we affirm.

The instant case arises from a breach of contract dispute between the Zecks and Smith. In October 2019, the parties entered into an agreement for Smith to remodel a home the Zecks recently purchased. Under the agreement, Smith was to begin work on October 30, 2019, and substantially complete the remodel within 130 days of commencement. The parties agreed to a contract amount of $180,920, which included allowances identified in the project proposal and allowance schedule. According to paragraph 6 (“Selections/Allowances”) of the agreement, if the cost of the Zecks’ selected materials exceeded the allowance, Smith was to notify the Zecks, and the amount in excess of the allowance, plus 20% for overhead, would be added to the next payment. The Zecks paid Smith an initial deposit of $27,000.

Time was of the essence for the Zecks because they were living in a rental home during the remodel. Throughout the remodel, there were several delays, resulting from concealed conditions with the framing, water intrusion, and electrical wiring, that had to be addressed. As a result of these delays, Smith was unable to substantially complete the project within 130 days.

In March 2020, Smith requested payment for its third draw for drywall. The Zecks declined to pay the draw without Smith first giving a firm move- in date. In response, Smith advised that no further work would be performed without payment. The Zecks responded by advising Smith that it was not permitted to perform any further work on their home.

The parties’ agreement contained an arbitration clause in which the parties agreed to submit to arbitration in the event of any dispute. In August 2020, a hearing was held before a Construction Industry Division Arbitrator of the American Arbitration Association. The hearing lasted eight hours, at which six different witnesses presented testimony and evidence. After the conclusion of the hearing, the arbitrator issued her decision, awarding Smith $13,704.99.

The arbitrator found that Smith did not meet the original substantial-

completion date due to delays from structural, water, and electrical conditions. The arbitrator found that Smith was entitled to an extension of time because the delays resulted from concealed conditions for which Smith was not responsible. The arbitrator further found that the Zecks breached the contract when they informed Smith that no money would be paid and that it was not permitted to perform any further work.

As of the date of the breach, Smith incurred costs totaling $116,807.14 or 65% percent of the contract amount. The arbitrator found that this amount was taken from Smith’s internal budget and did not include “overhead and profit.” This amount did include a “Construction Management Fee,” which the arbitrator found was really Smith’s overhead and profit. The arbitrator further found that Smith had an obligation to mitigate its damages and was only entitled to the costs of correctly completed work, which resulted in a deduction of $35,043.15. The deductions included $22,085 for the Construction Management Fee, $600 for TBD Drywall add-ons, $6,617 for granite, $745.15 for a Z-Line Hood, and $4,996 for Wolf Brothers. The arbitrator then added $16,352.80 to Smith’s costs for its overhead and profits, making the subtotal $98,116.79. After deducting the $78,115.80 in payments the Zecks made, Smith’s total was $20,000.99. However, the arbitrator found that the Zecks were entitled to $6,296 in expenses, which made the total net award to Smith $13,704.99.

Thereafter, the Zecks filed an application with the trial court to vacate (in part) the arbitration award. Smith filed its own application with the trial court, seeking to confirm the award. The trial court denied the Zecks’ application to vacate and confirmed the arbitration award, stating that “[w]hen the parties agreed to submit their contract interpretation disputes to arbitration, the Arbitrator’s interpretation of the Agreement, and not the interpretation of this Court, governs the rights of the parties.” The court found that the Zecks failed to establish that the arbitrator exceeded her authority. The arbitrator specifically determined that the Zecks breached the contract, and therefore, it was within her authority to award overhead damages pursuant to the contract terms.

It is from this order that the Zecks appeal, raising the following two assignments of error for review.

Assignment of Error One: The trial court erred by failing to vacate (in part) or correct the arbitration award, despite undisputed evidence that the arbitrator had double counted when calculating the amount of the award.

Assignment of Error Two: The trial court erred by failing to partially vacate (or clarify) that $6,447 worth of the award for allegedly unsalvageable materials, allegedly paid for by [Smith], requires delivery of those materials to the Zecks.

Within these assigned errors, the Zecks challenge the arbitration award, arguing that the arbitrator exceeded her authority when she awarded double profit to Smith on the completed percentage of work. The Zecks further argue that the arbitrator erred when she awarded Smith $6,447 for the cultured marble but did not order Smith to give the marble to the Zecks.

R.C. Chapter 2711 governs the method to grant and challenge an arbitration award. Under R.C. 2711.09, the trial court is required to grant a timely application for an order confirming an arbitration award “unless the award is vacated, modified, or corrected as prescribed in [R.C. 2711.10 and 2711.11].” Upon an application to vacate the arbitration award, R.C. 2711.10 provides that the trial court shall vacate the award under limited circumstances. Relevant to the instant case, R.C. 2711.10(D) requires the arbitration award to be vacated when the arbitrators “exceeded their powers[.]”

In Portage Cty. Bd. of Dev. Disabilities v. Portage Cty. Educators’

Assn. for Dev. Disabilities, 153 Ohio St.3d 219, 2018-Ohio-1590, 103 N.E.3d 804, the Supreme Court of Ohio held that “[w]hen reviewing a decision of a common pleas court confirming, modifying, vacating, or correcting an arbitration award, an appellate court should accept findings of fact that are not clearly erroneous but decide questions of law de novo.” Id. at syllabus, citing First Options of Chicago,

Inc. v. Kaplan, 514 U.S. 938, 115 S.Ct. 1920, 131 L.Ed.2d 985 (1995). Whether an arbitrator has exceeded their authority pursuant to R.C. 2711.10(D) is a “‘question of law’” that is reviewed de novo. Id. at ¶ 25, quoting Green v. Ameritech Corp., 200 F.3d 967, 974 (6th Cir.2000). Our de novo review on appeal, however, is not a de novo review of the merits of the dispute as presented to the arbitrator. Adams Cty./Ohio Valley Local School v. OAPSE/AFSCME, Local 572, 2017-Ohio-6929, 94 N.E.3d 937, ¶ 18 (4th Dist.), citing Jackson Cty., Ohio Sheriff v. FOP Ohio Labor Council, Inc., 4th Dist. Jackson No. 02CA15, 2004-Ohio-3535, ¶ 19-20. Rather, we review a trial court’s decision whether to vacate an arbitration award “de novo to see whether any of the statutory grounds for vacating an award exist.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Zeck v. Smith Custom Homes & Design, L.L.C., 2022 Ohio 622 (Ohio Ct. App. 2022).

2022 Ohio 622 (Zeck v. Smith Custom Homes & Design, L.L.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Parma VTA, L.L.C. v. Parma GE 7400, L.L.C.
2025 Ohio 3279 (Ohio Court of Appeals, 2025)
Feed Fat Co., L.L.C. v. Custom Agri Sys., Inc.
2025 Ohio 897 (Ohio Court of Appeals, 2025)
Cuyahoga Cty. v. Ohio Patrolmen's Benevolent Assn.
2024 Ohio 1055 (Ohio Court of Appeals, 2024)
Toledo Clinic, Inc. v. Felix
2024 Ohio 489 (Ohio Court of Appeals, 2024)
Carothers v. Shumaker, Loop & Kendrick, L.L.P.
2023 Ohio 1907 (Ohio Court of Appeals, 2023)
Cleveland v. Cleveland Police Patrolmen's Assn.
2022 Ohio 4284 (Ohio Court of Appeals, 2022)
Ohio Patrolmen's Benevolent Assn. v. Olmsted Falls
2022 Ohio 2958 (Ohio Court of Appeals, 2022)
Cleveland v. Communication Workers of Am., Local 4340
2022 Ohio 2498 (Ohio Court of Appeals, 2022)