Zeck v. Smith Custom Homes & Design, L.L.C.

2022 Ohio 622
CourtOhio Court of Appeals
DecidedMarch 3, 2022
Docket110574
StatusPublished
Cited by11 cases

This text of 2022 Ohio 622 (Zeck v. Smith Custom Homes & Design, L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zeck v. Smith Custom Homes & Design, L.L.C., 2022 Ohio 622 (Ohio Ct. App. 2022).

Opinion

[Cite as Zeck v. Smith Custom Homes & Design, L.L.C., 2022-Ohio-622.]

COURT OF APPEALS OF OHIO

EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA

DARREN ZECK, ET AL., :

Petitioners-Appellants, : No. 110574 v. :

SMITH CUSTOM HOMES & DESIGN, LLC, :

Respondent-Appellee. :

JOURNAL ENTRY AND OPINION

JUDGMENT: AFFIRMED RELEASED AND JOURNALIZED: March 3, 2022

Civil Appeal from the Cuyahoga County Court of Common Pleas Case No. CV-20-939797

Appearances:

Seeley, Savidge, Ebert & Gourash Co., LPA, and Jeffrey S. Moeller, for appellants.

Berns, Ockner & Greenberger, LLC, and Douglas V. Bartman, for appellee.

MARY J. BOYLE, J.:

Petitioners-appellants, Darren and Nicole Zeck (“the Zecks”), appeal

the trial court’s judgment entry denying their application to vacate the arbitration

award (in part) and confirming the arbitration award in favor of respondent- appellee, Smith Custom Homes & Design, LLC (“Smith”). For the reasons set forth

below, we affirm.

The instant case arises from a breach of contract dispute between the

Zecks and Smith. In October 2019, the parties entered into an agreement for Smith

to remodel a home the Zecks recently purchased. Under the agreement, Smith was

to begin work on October 30, 2019, and substantially complete the remodel within

130 days of commencement. The parties agreed to a contract amount of $180,920,

which included allowances identified in the project proposal and allowance

schedule. According to paragraph 6 (“Selections/Allowances”) of the

agreement, if the cost of the Zecks’ selected materials exceeded the allowance, Smith

was to notify the Zecks, and the amount in excess of the allowance, plus 20% for

overhead, would be added to the next payment. The Zecks paid Smith an initial

deposit of $27,000.

Time was of the essence for the Zecks because they were living in a

rental home during the remodel. Throughout the remodel, there were several

delays, resulting from concealed conditions with the framing, water intrusion, and

electrical wiring, that had to be addressed. As a result of these delays, Smith was

unable to substantially complete the project within 130 days.

In March 2020, Smith requested payment for its third draw for

drywall. The Zecks declined to pay the draw without Smith first giving a firm move-

in date. In response, Smith advised that no further work would be performed without payment. The Zecks responded by advising Smith that it was not permitted

to perform any further work on their home.

The parties’ agreement contained an arbitration clause in which the

parties agreed to submit to arbitration in the event of any dispute. In August 2020,

a hearing was held before a Construction Industry Division Arbitrator of the

American Arbitration Association. The hearing lasted eight hours, at which six

different witnesses presented testimony and evidence. After the conclusion of the

hearing, the arbitrator issued her decision, awarding Smith $13,704.99.

The arbitrator found that Smith did not meet the original substantial-

completion date due to delays from structural, water, and electrical conditions. The

arbitrator found that Smith was entitled to an extension of time because the delays

resulted from concealed conditions for which Smith was not responsible. The

arbitrator further found that the Zecks breached the contract when they informed

Smith that no money would be paid and that it was not permitted to perform any

further work.

As of the date of the breach, Smith incurred costs totaling $116,807.14

or 65% percent of the contract amount. The arbitrator found that this amount was

taken from Smith’s internal budget and did not include “overhead and profit.” This

amount did include a “Construction Management Fee,” which the arbitrator found

was really Smith’s overhead and profit. The arbitrator further found that Smith had

an obligation to mitigate its damages and was only entitled to the costs of correctly

completed work, which resulted in a deduction of $35,043.15. The deductions included $22,085 for the Construction Management Fee, $600 for TBD Drywall

add-ons, $6,617 for granite, $745.15 for a Z-Line Hood, and $4,996 for Wolf

Brothers. The arbitrator then added $16,352.80 to Smith’s costs for its overhead

and profits, making the subtotal $98,116.79. After deducting the $78,115.80 in

payments the Zecks made, Smith’s total was $20,000.99. However, the arbitrator

found that the Zecks were entitled to $6,296 in expenses, which made the total net

award to Smith $13,704.99.

Thereafter, the Zecks filed an application with the trial court to vacate

(in part) the arbitration award. Smith filed its own application with the trial court,

seeking to confirm the award. The trial court denied the Zecks’ application to vacate

and confirmed the arbitration award, stating that “[w]hen the parties agreed to

submit their contract interpretation disputes to arbitration, the Arbitrator’s

interpretation of the Agreement, and not the interpretation of this Court, governs

the rights of the parties.” The court found that the Zecks failed to establish that the

arbitrator exceeded her authority. The arbitrator specifically determined that the

Zecks breached the contract, and therefore, it was within her authority to award

overhead damages pursuant to the contract terms.

It is from this order that the Zecks appeal, raising the following two

assignments of error for review.

Assignment of Error One: The trial court erred by failing to vacate (in part) or correct the arbitration award, despite undisputed evidence that the arbitrator had double counted when calculating the amount of the award. Assignment of Error Two: The trial court erred by failing to partially vacate (or clarify) that $6,447 worth of the award for allegedly unsalvageable materials, allegedly paid for by [Smith], requires delivery of those materials to the Zecks.

Within these assigned errors, the Zecks challenge the arbitration

award, arguing that the arbitrator exceeded her authority when she awarded double

profit to Smith on the completed percentage of work. The Zecks further argue that

the arbitrator erred when she awarded Smith $6,447 for the cultured marble but did

not order Smith to give the marble to the Zecks.

R.C. Chapter 2711 governs the method to grant and challenge an

arbitration award. Under R.C. 2711.09, the trial court is required to grant a timely

application for an order confirming an arbitration award “unless the award is

vacated, modified, or corrected as prescribed in [R.C. 2711.10 and 2711.11].” Upon

an application to vacate the arbitration award, R.C. 2711.10 provides that the trial

court shall vacate the award under limited circumstances. Relevant to the instant

case, R.C. 2711.10(D) requires the arbitration award to be vacated when the

arbitrators “exceeded their powers[.]”

In Portage Cty. Bd. of Dev. Disabilities v. Portage Cty. Educators’

Assn. for Dev. Disabilities, 153 Ohio St.3d 219, 2018-Ohio-1590, 103 N.E.3d 804,

the Supreme Court of Ohio held that “[w]hen reviewing a decision of a common

pleas court confirming, modifying, vacating, or correcting an arbitration award, an

appellate court should accept findings of fact that are not clearly erroneous but

decide questions of law de novo.” Id. at syllabus, citing First Options of Chicago, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parma VTA, L.L.C. v. Parma GE 7400, L.L.C.
2025 Ohio 3279 (Ohio Court of Appeals, 2025)
Feed Fat Co., L.L.C. v. Custom Agri Sys., Inc.
2025 Ohio 897 (Ohio Court of Appeals, 2025)
Cuyahoga Cty. v. Ohio Patrolmen's Benevolent Assn.
2024 Ohio 1055 (Ohio Court of Appeals, 2024)
Toledo Clinic, Inc. v. Felix
2024 Ohio 489 (Ohio Court of Appeals, 2024)
Carothers v. Shumaker, Loop & Kendrick, L.L.P.
2023 Ohio 1907 (Ohio Court of Appeals, 2023)
Cleveland v. Cleveland Police Patrolmen's Assn.
2022 Ohio 4284 (Ohio Court of Appeals, 2022)
Ohio Patrolmen's Benevolent Assn. v. Olmsted Falls
2022 Ohio 2958 (Ohio Court of Appeals, 2022)
Cleveland v. Communication Workers of Am., Local 4340
2022 Ohio 2498 (Ohio Court of Appeals, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2022 Ohio 622, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zeck-v-smith-custom-homes-design-llc-ohioctapp-2022.