[Cite as Feed Fat Co., L.L.C. v. Custom Agri Sys., Inc., 2025-Ohio-897.]
COURT OF APPEALS ASHLAND COUNTY, OHIO FIFTH APPELLATE DISTRICT
FEED FAT COMPANY, LLC : d/b/a ORIGO, : JUDGES: : Hon. William B. Hoffman, P.J. Plaintiff - Appellee : Hon. Robert G. Montgomery, J. : Hon. Kevin W. Popham, J. -vs- : : CUSTOM AGRI SYSTEMS, INC., : Case No. 24-COA-031 : Defendant - Appellant : OPINION
CHARACTER OF PROCEEDING: Appeal from the Ashland County Court of Common Pleas, Case No. 24-CIV-038
JUDGMENT: Reversed
DATE OF JUDGMENT: March 14, 2025
APPEARANCES:
For Defendant-Appellant For Plaintiff-Appellee
DAVID R. HUDSON ERIC T. MICHENER CLINTON J. WASSERMAN GAGE T. RIGHTER Reminger Co., LPA Critchfield, Critchfield & One SeaGate, Suite 1600 Johnston, Ltd. Toledo, OH 43604 225 North Market Street P.O. Box 599 Wooster, OH 44691 Montgomery, J.
STATEMENT OF THE FACTS AND THE CASE
{¶1} On January 2, 2018, MBH Acres, LLC (“MBH”) and Custom Agri Systems,
Inc. (“CAS”) executed a Written Estimate/Contract (“Contract”) for the construction of a
commercial agricultural facility located in Ashland, Ohio (“the Project”). A Supplement to
Construction Contract (“Supplement”) was executed on January 3, 2018. (The Contract
and Supplement will be collectively referred to as the “Agreement”.) At the time of the
agreement, MBH did not provide CAS with complete drawings, plans or specifications for
the Project. Michael Hippert, who served as the CEO of MBH and the general contractor
for the Project, provided an explanation to CAS of the Project. Michael Hippert is also the
CEO of Origo. Origo is the entity that would ultimately be running the business upon
completion of the Project.
{¶2} CAS began work on the Project on March 23, 2018. The Agreement
originally set a completion date of June 30, 2018. On April 2, 2018, CAS advised MBH
that the scope of the Project far exceeded the Agreement and the June 20, 2018,
completion date was not feasible. MBH and CAS did not formalize a new agreement but
utilized fourteen (14) change orders to encompass the work requested and the work that
was performed outside the scope of the Project. The Project and work performed outside
the Project was completed on or about June 6, 2019.
{¶3} Origo filed a complaint in the Ashland County Common Pleas Court
asserting breach of contract against CAS as an alleged third-party beneficiary to the
Agreement between MBH and CAS. Origo is seeking over $2 million in “lost profits”. {¶4} MBH, CAS, and Origo agreed to arbitrate the dispute pursuant to the terms
of the Agreement. CAS moved for summary judgment arguing that Origo was not entitled
to damages under the Agreement because Origo is a third-party beneficiary. Origo argued
that there is a direct conflict between Section 7 of Contract and Section 7 of the
Supplement. Origo argued that pursuant to Section 10 of the Supplement, Section 7 of
the Supplement supersedes Section 7 of the Contract.
{¶5} The three provisions of the Agreement at issue are:
Section 7 of the Contract:
In no event shall contractor and its subcontractors be liable to customer
or another party for incidental, special, exemplary, punitive or
consequential damages, including loss of income or profits, lost revenues
or any economic loss, whether such customer or party has been advised
of the possibility of such damage, and whether any claim for recovery is
based on the theories of contract, warranty, tort (including negligence or
strict liability) or otherwise. In no event shall contractor’s and its
subcontractors’ aggregate liability to customer and any third party in
connection with the contract, for all other damages, exceed the project
total contract price. The remedies stated in this contract are exclusive.
Section 7 of the Supplement:
Indemnification. Contractor hereby releases Customer, its members,
managers, partners, affiliates, employees, managers, representatives,
agents, successors, and assigns, and agrees to defend, indemnify and
hold harmless Customer, its members, managers, partners, affiliates, employees, representatives, agents and successors, and assigns, for and
against all claims, causes of actions willful misconduct or gross
negligence. Without limiting the generality, demands, judicial and
administrative proceedings, losses, liabilities, damages, costs and
expenses, *** Notwithstanding the foregoing, this provision shall not apply
to such claims that are caused by Customer’s willful misconduct or gross
negligence. Without limiting the generality of the foregoing, Contractor
further agrees to indemnify Customer, its members, managers, partners,
affiliates, employees, representatives, agents and successors, and
assigns, against and hold and save Customer, its members, managers,
partners, successors, and assigns, against and hold and save Customer,
its members, managers, partners, affiliates, employees, managers,
representatives, agents, successors, and assigns harmless from any and
all claims, causes of action, fines, costs, expenses **** arising or resulting
from, in conjunction with, or due to: (i) any act or omission of Contractor,
its officers, employees, contractors, or servants which results in (A) injury
to or death of person, including employees of Contractor, (B) damage to
any property, (C) defects of materials or workmanship required under the
Construction Contract ***; or (D) lack of full and strict compliance by
Contractor’s employees, agents, materialmen and subcontractors with all
safety, civil rights and equal employment opportunity ****; or (iii) [sic]
breach of any covenant or agreement contained in the Construction
Contract or this Supplement or misrepresentation of any material fact or omission concerning the Construction Contract, this Supplement, or the
Project.
Section 10 of the Supplement:
Construction Contract. Notwithstanding any term or condition to the
contrary contained in the Construction Contract or otherwise, any and all
terms and conditions set forth in this Supplement shall (a) supplement the
Construction Contract to the extent any term or condition set forth here
that is not set forth in the Construction Contract; (b) override, amend,
revise, change, modify, replace, and restate any and all terms and or
conditions contained in the Construction Contract that conflicts, in any
respect, with any term or condition contained herein and (c) be
incorporated into and made a part of the Construction Contract.
{¶6} The arbitrator granted summary judgment in favor of CAS on November 29,
2023, finding that the Agreement between MBH and CAS was unambiguous and
precluded claims by an alleged third-party beneficiary, including Origo. The arbitrator
specifically found that there was no genuine issue of material fact pertaining to Origo’s
status as a third-party beneficiary. (Order as to Respondent CAS’s Motion for Summary
Judgment, p.4)
{¶7} Origo filed a Motion for Reconsideration. Upon reconsideration of his
decision, the arbitrator stated that he reviewed his notes, the original ruling and the recent
briefs submitted by the parties, but his ruling is unchanged. The arbitrator issued an Order
as to [Origo’s] Motion for Reconsideration holding that “the reason for the Arbitrator’s
Free access — add to your briefcase to read the full text and ask questions with AI
[Cite as Feed Fat Co., L.L.C. v. Custom Agri Sys., Inc., 2025-Ohio-897.]
COURT OF APPEALS ASHLAND COUNTY, OHIO FIFTH APPELLATE DISTRICT
FEED FAT COMPANY, LLC : d/b/a ORIGO, : JUDGES: : Hon. William B. Hoffman, P.J. Plaintiff - Appellee : Hon. Robert G. Montgomery, J. : Hon. Kevin W. Popham, J. -vs- : : CUSTOM AGRI SYSTEMS, INC., : Case No. 24-COA-031 : Defendant - Appellant : OPINION
CHARACTER OF PROCEEDING: Appeal from the Ashland County Court of Common Pleas, Case No. 24-CIV-038
JUDGMENT: Reversed
DATE OF JUDGMENT: March 14, 2025
APPEARANCES:
For Defendant-Appellant For Plaintiff-Appellee
DAVID R. HUDSON ERIC T. MICHENER CLINTON J. WASSERMAN GAGE T. RIGHTER Reminger Co., LPA Critchfield, Critchfield & One SeaGate, Suite 1600 Johnston, Ltd. Toledo, OH 43604 225 North Market Street P.O. Box 599 Wooster, OH 44691 Montgomery, J.
STATEMENT OF THE FACTS AND THE CASE
{¶1} On January 2, 2018, MBH Acres, LLC (“MBH”) and Custom Agri Systems,
Inc. (“CAS”) executed a Written Estimate/Contract (“Contract”) for the construction of a
commercial agricultural facility located in Ashland, Ohio (“the Project”). A Supplement to
Construction Contract (“Supplement”) was executed on January 3, 2018. (The Contract
and Supplement will be collectively referred to as the “Agreement”.) At the time of the
agreement, MBH did not provide CAS with complete drawings, plans or specifications for
the Project. Michael Hippert, who served as the CEO of MBH and the general contractor
for the Project, provided an explanation to CAS of the Project. Michael Hippert is also the
CEO of Origo. Origo is the entity that would ultimately be running the business upon
completion of the Project.
{¶2} CAS began work on the Project on March 23, 2018. The Agreement
originally set a completion date of June 30, 2018. On April 2, 2018, CAS advised MBH
that the scope of the Project far exceeded the Agreement and the June 20, 2018,
completion date was not feasible. MBH and CAS did not formalize a new agreement but
utilized fourteen (14) change orders to encompass the work requested and the work that
was performed outside the scope of the Project. The Project and work performed outside
the Project was completed on or about June 6, 2019.
{¶3} Origo filed a complaint in the Ashland County Common Pleas Court
asserting breach of contract against CAS as an alleged third-party beneficiary to the
Agreement between MBH and CAS. Origo is seeking over $2 million in “lost profits”. {¶4} MBH, CAS, and Origo agreed to arbitrate the dispute pursuant to the terms
of the Agreement. CAS moved for summary judgment arguing that Origo was not entitled
to damages under the Agreement because Origo is a third-party beneficiary. Origo argued
that there is a direct conflict between Section 7 of Contract and Section 7 of the
Supplement. Origo argued that pursuant to Section 10 of the Supplement, Section 7 of
the Supplement supersedes Section 7 of the Contract.
{¶5} The three provisions of the Agreement at issue are:
Section 7 of the Contract:
In no event shall contractor and its subcontractors be liable to customer
or another party for incidental, special, exemplary, punitive or
consequential damages, including loss of income or profits, lost revenues
or any economic loss, whether such customer or party has been advised
of the possibility of such damage, and whether any claim for recovery is
based on the theories of contract, warranty, tort (including negligence or
strict liability) or otherwise. In no event shall contractor’s and its
subcontractors’ aggregate liability to customer and any third party in
connection with the contract, for all other damages, exceed the project
total contract price. The remedies stated in this contract are exclusive.
Section 7 of the Supplement:
Indemnification. Contractor hereby releases Customer, its members,
managers, partners, affiliates, employees, managers, representatives,
agents, successors, and assigns, and agrees to defend, indemnify and
hold harmless Customer, its members, managers, partners, affiliates, employees, representatives, agents and successors, and assigns, for and
against all claims, causes of actions willful misconduct or gross
negligence. Without limiting the generality, demands, judicial and
administrative proceedings, losses, liabilities, damages, costs and
expenses, *** Notwithstanding the foregoing, this provision shall not apply
to such claims that are caused by Customer’s willful misconduct or gross
negligence. Without limiting the generality of the foregoing, Contractor
further agrees to indemnify Customer, its members, managers, partners,
affiliates, employees, representatives, agents and successors, and
assigns, against and hold and save Customer, its members, managers,
partners, successors, and assigns, against and hold and save Customer,
its members, managers, partners, affiliates, employees, managers,
representatives, agents, successors, and assigns harmless from any and
all claims, causes of action, fines, costs, expenses **** arising or resulting
from, in conjunction with, or due to: (i) any act or omission of Contractor,
its officers, employees, contractors, or servants which results in (A) injury
to or death of person, including employees of Contractor, (B) damage to
any property, (C) defects of materials or workmanship required under the
Construction Contract ***; or (D) lack of full and strict compliance by
Contractor’s employees, agents, materialmen and subcontractors with all
safety, civil rights and equal employment opportunity ****; or (iii) [sic]
breach of any covenant or agreement contained in the Construction
Contract or this Supplement or misrepresentation of any material fact or omission concerning the Construction Contract, this Supplement, or the
Project.
Section 10 of the Supplement:
Construction Contract. Notwithstanding any term or condition to the
contrary contained in the Construction Contract or otherwise, any and all
terms and conditions set forth in this Supplement shall (a) supplement the
Construction Contract to the extent any term or condition set forth here
that is not set forth in the Construction Contract; (b) override, amend,
revise, change, modify, replace, and restate any and all terms and or
conditions contained in the Construction Contract that conflicts, in any
respect, with any term or condition contained herein and (c) be
incorporated into and made a part of the Construction Contract.
{¶6} The arbitrator granted summary judgment in favor of CAS on November 29,
2023, finding that the Agreement between MBH and CAS was unambiguous and
precluded claims by an alleged third-party beneficiary, including Origo. The arbitrator
specifically found that there was no genuine issue of material fact pertaining to Origo’s
status as a third-party beneficiary. (Order as to Respondent CAS’s Motion for Summary
Judgment, p.4)
{¶7} Origo filed a Motion for Reconsideration. Upon reconsideration of his
decision, the arbitrator stated that he reviewed his notes, the original ruling and the recent
briefs submitted by the parties, but his ruling is unchanged. The arbitrator issued an Order
as to [Origo’s] Motion for Reconsideration holding that “the reason for the Arbitrator’s
original decision is the Arbitrator concluded that the Indemnification provision in the Supplement did not conflict with Section 7 of the Agreement”. (Order as to Claimant’s
Motion for Reconsideration pg.1)
{¶8} Origo filed a Motion to Vacate Arbitrator’s Award Pursuant to R.C. 2711.10
in the Ashland County Court of Common Pleas on February 28, 2024. The case came
before a magistrate who found that the arbitrator’s interpretation of the Agreement did not
conflict with its’ express terms and the arbitrator’s decision can be rationally derived from
the terms of the Agreement.
{¶9} Origo timely filed Objections to the Magistrate’s Decision. The trial court
overruled the magistrate’s decision finding that the issue before the court was whether
the Agreement expressly provides Plaintiff (Origo) with an accrued right to indemnification
once it suffers a loss thereby allowing Plaintiff (Origo) to directly pursue a cause of action
against Defendant (CAS) and issued a Judgment Entry on August 13, 2024 that granted
Origo’s Motion to Vacate the Arbitrator’s Award.
{¶10} Appellant (CAS) appeals the Judgment Entry filed August 13, 2024 in the
Ashland County Common Pleas Court and asserts the following assignments of error:
{¶11} “THE TRIAL COURT ABUSED ITS AUTHORITY IN VACATING THE ARBITRATOR’S AWARD BASED ON FINDING AN “EXPRESS CONFLICT” IN THE ARBITRATOR’S INTERPRETATION OF THE AGREEMENT BETWEEN MBH ACRES, LLC AND DEFENDANT-APPELLANT CUSTOM AGRI SYSTEM, INC.
{¶12} THE TRIAL COURT ERRED IN DETERMINING THAT SECTION 7 OF THE SUPPLEMENT EXPRESSLY CONFLICTS WITH SECTION 7 OF THE CONTRACT, IN GRANTING PLAINTIFF-APPELLEE FEED FAT COMPANY D/B/A ORIGO’S MOTION TO VACATE ARBITRATOR’S AWARD PURSUANT TO R.C. 2711.10.
{¶13} THE TRIAL COURT ERRED IN DETERMINING THAT THE GENERAL INDEMNIFICATION PROVISION ALLOWS FOR A DIRECT ACTION BROUGHT BY PLAINTIFF-APPELLEE FEED FAT COMPANY, LLC. A PURPORTED THIRD-PARTY BENEFICIARY ASSERTING A “LOST PROFIT” CLAIM, DESPITE THE EXPRESS PRECLUSION IN THE AGREEMENT BETWEEN MBH ACRES, LLC AND CUSTOM AGRI SYSTEMS, INC.” STANDARD OF REVIEW
{¶14} Pursuant to R.C. 2711.15, “An appeal may be taken from an order
confirming, modifying, correcting, or vacating an award made in an arbitration proceeding
or from judgment entered upon an award.” An appellate court’s review under this statute
is confined to the trial court’s order and does not include a review of the original arbitration.
Warren Educ. Assn, 18 Ohio St. 3d at 173-174, citing Lockart v Am. Res. Ins. Co., 2 Ohio
App.3d 99, 101 (8th Dist.1981).
{¶15} “When reviewing a decision of a common pleas court * * * vacating * * * an
arbitration award, an appellate court should accept findings of fact that are not clearly
erroneous but decide questions of law de novo”. Portage Cty. Bd. Of Developmental
Disabilities, 2018-Ohio-1590, syllabus. Whether an arbitrator has exceeded his or her
authority is a question of law. Id. at 25. An appellate court’s de novo review of the
existence of statutory grounds under R.C. 2711.10(D) is not a de novo review of the merits
of the dispute as presented to the arbitrator. Zeck v. Smith Custom Homes & Design,
LLC, 2022-Ohio-622, 12 (8th Dist.)
{¶16} A trial court can only vacate an arbitration award under certain
circumstances. Subsection (D) of R.C. 2711.10 states that a court shall vacate an award
if the “arbitrators exceed their powers, or so imperfectly executed them that a mutual, final
and definite award upon the subject matter submitted was not made”.
ANALYSIS
{¶17} Judicial deference in arbitration cases is based on recognition that the
parties have agreed to have their dispute settled by an arbitrator rather than the courts
and “to accept the arbitrator’s view of the facts and the meaning of the contract regardless of the outcome of the arbitration”. United Paperworkers Internatl. Union v. Misco, Inc.,
484 U.S. 29, 37-38. (1987).
{¶18} The trial court may not substitute its judgment for that of the arbitrator except
in very limited circumstances. A reviewing court has a very limited role in reviewing a
binding arbitration award. Madison Local School Dist. Bd. Of Edn. V OAPSE/AFSCME
Local 4, 2009-Ohio-1315, paragraph 9 (11th Dist.) The arbitrator is the final judge of both
the law and the facts, and a court may not substitute its judgment for that of the arbitrator.
Id. The Madison court went on to say that “when a provision in an arbitration agreement
is subject to more than one reasonable interpretation, an arbitrator’s interpretation, rather
than that of the reviewing court, governs the rights of the parties”.
{¶19} The trial court and the arbitrator interpreted the Agreement differently. The
trial court found that “Section 7 of the Supplement to Construction Contract conflicts with
Section 7 of the original January 2, 2018 agreement. Page 5 of Judgment Entry. The
arbitrator found that “the language of the Contract was not ambiguous.” Arbitrator’s
November 29, 2023 Order, page 4. The arbitrator went on to state that “Respondent is
entitled to judgment as a matter of law and that there is no genuine issue of material fact
pertaining to Origo’s status as a third-party beneficiary to the Contract – such status is
precluded by the unambiguous language of the Contract”. Id. In applying the language of
the Madison case, the Agreement in this case is subject to two different interpretations
and the trial court, as the reviewing court, should have accepted the arbitrator’s
interpretation of the Agreement.
{¶20} A trial court shall vacate an arbitration award under certain circumstances.
R.C. 2711.10(D) states that a court shall vacate an award if the “arbitrators exceeded their powers, or so imperfectly executed them that a mutual, final, and definite award upon
the subject matter submitted was not made”.
{¶21} Looking at Appellant’s first assignment of error, the court finds that in the
case at hand, the trial court found that, “In deciding the Plaintiff’s Motion to Vacate
Arbitrator’s Award, the Court’s role is to determine whether the Arbitrator’s decision
conflicts with the express terms of the agreement or whether the award is without rational
support or cannot be rationally derived from the terms of the agreement”. Citing Cedar
Fair, L.P. v Falfas, 140 Ohio St. 3d 447, 449 (2014) (Pg 3 of JE). The trial court relied
upon this standard of review in finding that “the Arbitrator’s November 29, 2023 decision
conflicts with the express terms of the agreement.” Judgment Entry p.5.
{¶22} The trial court did not make a finding that the Arbitrator exceeded his powers
or that he imperfectly executed them. The trial court did not find the arbitrator’s award
was not rationally supported. The arbitrator stated in his decision that he had reviewed
the briefs, depositions, and exhibits before issuing his judgment. Arbitrator’s January 8,
2024 decision. The trial court vacated the arbitrator’s award solely on its interpretation
that “the award conflicted with the express terms of the Agreement”. Judgment Entry p.5.
The trial court substituted its’ interpretation of the Agreement for that of the arbitrator. In
doing so, the trial court did not give judicial deference to the arbitrator’s award and
erroneously vacated the award.
{¶23} In analyzing Appellant’s second assignment of error, the trial court reviewed
Section 7 of the Contract and Section 7 of the Supplement and found that these two
sections conflicted. The trial court went on to find that the conflict between these two
sections warranted vacating the arbitrator’s award. Judgment Entry p.5. {¶24} The trial court’s role in determining whether an arbitration award should be
vacated is set out in R.C. 2711.10 which states:
In any of the following cases, the court of common pleas shall make an
order vacating the award upon the application of any party to the
arbitration if:
(D) The arbitrators exceeded their powers, or so imperfectly executed
them that a mutual, final and definite award upon the subject matter
submitted was not made.
{¶25} The trial court recognized that the arbitrator found that Section 7 of the
Contract and Section 7 of the Supplement speak to legally distinct rights. The trial court
also recognized that the magistrate supported the arbitrator’s award. However, the trial
court interpreted the Agreement to say that Section 7 of the Supplement conflicts with
Section 7 of the Contract. The trial court’s August 13, 2024 Judgment Entry is the first
time that a reviewing body determined that the two sections were in conflict. The trial
court in this case substituted its’ judgment for that of the arbitrator and came to a different
conclusion. “The fact that the common pleas court may have arrived at a different
conclusion than did the arbitrator is immaterial”. Motor Wheel Corp. V. Goodyear Tire &
Rubber Co., 98 Ohio App.3d 45, 52, 647 N.E. 2d 844 (8 th Dist. 1994). Finding a direct
conflict between Section 7 of the contract and Section 7 of the Agreement is not a basis
for the trial court to vacate the arbitrator’s award pursuant R.C. 2711.10(D).
{¶26} In analyzing Appellant’s third assignment of error, the trial court erred in it’s
findings regarding the issue of indemnification. The trial court substituted it’s judgment for
that of the arbitrator and should not have made a finding regarding indemnification. The issue at hand is not whether the trial court would have arrived at a different conclusion
when reviewing an arbitrator’s decision. The trial court shall only vacate an arbitrator’s
award pursuant to R.C. 2711.10.
CONCLUSION
{¶27} Based on the foregoing, Appellant’s first, second and third assignments of
error are sustained, and the decision of the trial court is reversed.
By: Montgomery, J.
Hoffman, P.J. and
Popham, J. concur.