Feed Fat Co., L.L.C. v. Custom Agri Sys., Inc.

2025 Ohio 897
Ohio Court of Appeals·Decided March 14, 2025·No. 24-COA-031·Published

Opinion

COURT OF APPEALS

ASHLAND COUNTY, OHIO

FIFTH APPELLATE DISTRICT

FEED FAT COMPANY, LLC : d/b/a ORIGO, : JUDGES:

: Hon. William B. Hoffman, P.J.

Plaintiff - Appellee : Hon. Robert G. Montgomery, J.

: Hon. Kevin W. Popham, J.

-vs- :

:

CUSTOM AGRI SYSTEMS, INC., : Case No. 24-COA-031 :

Defendant - Appellant : OPINION

CHARACTER OF PROCEEDING: Appeal from the Ashland County Court of Common Pleas,

Case No. 24-CIV-038

JUDGMENT: Reversed

DATE OF JUDGMENT: March 14, 2025

APPEARANCES: For Defendant-Appellant For Plaintiff-Appellee

DAVID R. HUDSON ERIC T. MICHENER CLINTON J. WASSERMAN GAGE T. RIGHTER Reminger Co., LPA Critchfield, Critchfield & One SeaGate, Suite 1600 Johnston, Ltd. Toledo, OH 43604 225 North Market Street P.O. Box 599

Wooster, OH 44691

Montgomery, J.

STATEMENT OF THE FACTS AND THE CASE

{¶1} On January 2, 2018, MBH Acres, LLC (“MBH”) and Custom Agri Systems, Inc. (“CAS”) executed a Written Estimate/Contract (“Contract”) for the construction of a commercial agricultural facility located in Ashland, Ohio (“the Project”). A Supplement to Construction Contract (“Supplement”) was executed on January 3, 2018. (The Contract and Supplement will be collectively referred to as the “Agreement”.) At the time of the agreement, MBH did not provide CAS with complete drawings, plans or specifications for the Project. Michael Hippert, who served as the CEO of MBH and the general contractor for the Project, provided an explanation to CAS of the Project. Michael Hippert is also the CEO of Origo. Origo is the entity that would ultimately be running the business upon completion of the Project.

{¶2} CAS began work on the Project on March 23, 2018. The Agreement originally set a completion date of June 30, 2018. On April 2, 2018, CAS advised MBH that the scope of the Project far exceeded the Agreement and the June 20, 2018, completion date was not feasible. MBH and CAS did not formalize a new agreement but utilized fourteen (14) change orders to encompass the work requested and the work that was performed outside the scope of the Project. The Project and work performed outside the Project was completed on or about June 6, 2019.

{¶3} Origo filed a complaint in the Ashland County Common Pleas Court asserting breach of contract against CAS as an alleged third-party beneficiary to the Agreement between MBH and CAS. Origo is seeking over $2 million in “lost profits”.

{¶4} MBH, CAS, and Origo agreed to arbitrate the dispute pursuant to the terms of the Agreement. CAS moved for summary judgment arguing that Origo was not entitled to damages under the Agreement because Origo is a third-party beneficiary. Origo argued that there is a direct conflict between Section 7 of Contract and Section 7 of the Supplement. Origo argued that pursuant to Section 10 of the Supplement, Section 7 of the Supplement supersedes Section 7 of the Contract.

{¶5} The three provisions of the Agreement at issue are:

Section 7 of the Contract:

In no event shall contractor and its subcontractors be liable to customer or another party for incidental, special, exemplary, punitive or consequential damages, including loss of income or profits, lost revenues or any economic loss, whether such customer or party has been advised of the possibility of such damage, and whether any claim for recovery is based on the theories of contract, warranty, tort (including negligence or strict liability) or otherwise. In no event shall contractor’s and its subcontractors’ aggregate liability to customer and any third party in connection with the contract, for all other damages, exceed the project total contract price. The remedies stated in this contract are exclusive.

Section 7 of the Supplement:

Indemnification. Contractor hereby releases Customer, its members, managers, partners, affiliates, employees, managers, representatives, agents, successors, and assigns, and agrees to defend, indemnify and hold harmless Customer, its members, managers, partners, affiliates, employees, representatives, agents and successors, and assigns, for and against all claims, causes of actions willful misconduct or gross negligence. Without limiting the generality, demands, judicial and administrative proceedings, losses, liabilities, damages, costs and expenses, *** Notwithstanding the foregoing, this provision shall not apply to such claims that are caused by Customer’s willful misconduct or gross negligence. Without limiting the generality of the foregoing, Contractor further agrees to indemnify Customer, its members, managers, partners, affiliates, employees, representatives, agents and successors, and assigns, against and hold and save Customer, its members, managers, partners, successors, and assigns, against and hold and save Customer, its members, managers, partners, affiliates, employees, managers, representatives, agents, successors, and assigns harmless from any and all claims, causes of action, fines, costs, expenses **** arising or resulting from, in conjunction with, or due to: (i) any act or omission of Contractor, its officers, employees, contractors, or servants which results in (A) injury to or death of person, including employees of Contractor, (B) damage to any property, (C) defects of materials or workmanship required under the Construction Contract ***; or (D) lack of full and strict compliance by Contractor’s employees, agents, materialmen and subcontractors with all safety, civil rights and equal employment opportunity ****; or (iii) [sic] breach of any covenant or agreement contained in the Construction Contract or this Supplement or misrepresentation of any material fact or omission concerning the Construction Contract, this Supplement, or the Project.

Section 10 of the Supplement:

Construction Contract. Notwithstanding any term or condition to the contrary contained in the Construction Contract or otherwise, any and all terms and conditions set forth in this Supplement shall (a) supplement the Construction Contract to the extent any term or condition set forth here that is not set forth in the Construction Contract; (b) override, amend, revise, change, modify, replace, and restate any and all terms and or conditions contained in the Construction Contract that conflicts, in any respect, with any term or condition contained herein and (c) be incorporated into and made a part of the Construction Contract.

{¶6} The arbitrator granted summary judgment in favor of CAS on November 29, 2023, finding that the Agreement between MBH and CAS was unambiguous and precluded claims by an alleged third-party beneficiary, including Origo. The arbitrator specifically found that there was no genuine issue of material fact pertaining to Origo’s status as a third-party beneficiary. (Order as to Respondent CAS’s Motion for Summary Judgment, p.4)

{¶7} Origo filed a Motion for Reconsideration. Upon reconsideration of his decision, the arbitrator stated that he reviewed his notes, the original ruling and the recent briefs submitted by the parties, but his ruling is unchanged. The arbitrator issued an Order as to [Origo’s] Motion for Reconsideration holding that “the reason for the Arbitrator’s original decision is the Arbitrator concluded that the Indemnification provision in the

Supplement did not conflict with Section 7 of the Agreement”. (Order as to Claimant’s Motion for Reconsideration pg.1)

{¶8} Origo filed a Motion to Vacate Arbitrator’s Award Pursuant to R.C. 2711.10 in the Ashland County Court of Common Pleas on February 28, 2024. The case came before a magistrate who found that the arbitrator’s interpretation of the Agreement did not conflict with its’ express terms and the arbitrator’s decision can be rationally derived from the terms of the Agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Feed Fat Co., L.L.C. v. Custom Agri Sys., Inc., 2025 Ohio 897 (Ohio Ct. App. 2025).

2025 Ohio 897 (Feed Fat Co., L.L.C. v. Custom Agri Sys., Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Elon Property Mgt. Co., L.L.C. v. Shif Rockside Place, L.L.C.
2026 Ohio 735 (Ohio Court of Appeals, 2026)