Feed Fat Co., L.L.C. v. Custom Agri Sys., Inc.

2025 Ohio 897
CourtOhio Court of Appeals
DecidedMarch 14, 2025
Docket24-COA-031
StatusPublished

This text of 2025 Ohio 897 (Feed Fat Co., L.L.C. v. Custom Agri Sys., Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Feed Fat Co., L.L.C. v. Custom Agri Sys., Inc., 2025 Ohio 897 (Ohio Ct. App. 2025).

Opinion

[Cite as Feed Fat Co., L.L.C. v. Custom Agri Sys., Inc., 2025-Ohio-897.]

COURT OF APPEALS ASHLAND COUNTY, OHIO FIFTH APPELLATE DISTRICT

FEED FAT COMPANY, LLC : d/b/a ORIGO, : JUDGES: : Hon. William B. Hoffman, P.J. Plaintiff - Appellee : Hon. Robert G. Montgomery, J. : Hon. Kevin W. Popham, J. -vs- : : CUSTOM AGRI SYSTEMS, INC., : Case No. 24-COA-031 : Defendant - Appellant : OPINION

CHARACTER OF PROCEEDING: Appeal from the Ashland County Court of Common Pleas, Case No. 24-CIV-038

JUDGMENT: Reversed

DATE OF JUDGMENT: March 14, 2025

APPEARANCES:

For Defendant-Appellant For Plaintiff-Appellee

DAVID R. HUDSON ERIC T. MICHENER CLINTON J. WASSERMAN GAGE T. RIGHTER Reminger Co., LPA Critchfield, Critchfield & One SeaGate, Suite 1600 Johnston, Ltd. Toledo, OH 43604 225 North Market Street P.O. Box 599 Wooster, OH 44691 Montgomery, J.

STATEMENT OF THE FACTS AND THE CASE

{¶1} On January 2, 2018, MBH Acres, LLC (“MBH”) and Custom Agri Systems,

Inc. (“CAS”) executed a Written Estimate/Contract (“Contract”) for the construction of a

commercial agricultural facility located in Ashland, Ohio (“the Project”). A Supplement to

Construction Contract (“Supplement”) was executed on January 3, 2018. (The Contract

and Supplement will be collectively referred to as the “Agreement”.) At the time of the

agreement, MBH did not provide CAS with complete drawings, plans or specifications for

the Project. Michael Hippert, who served as the CEO of MBH and the general contractor

for the Project, provided an explanation to CAS of the Project. Michael Hippert is also the

CEO of Origo. Origo is the entity that would ultimately be running the business upon

completion of the Project.

{¶2} CAS began work on the Project on March 23, 2018. The Agreement

originally set a completion date of June 30, 2018. On April 2, 2018, CAS advised MBH

that the scope of the Project far exceeded the Agreement and the June 20, 2018,

completion date was not feasible. MBH and CAS did not formalize a new agreement but

utilized fourteen (14) change orders to encompass the work requested and the work that

was performed outside the scope of the Project. The Project and work performed outside

the Project was completed on or about June 6, 2019.

{¶3} Origo filed a complaint in the Ashland County Common Pleas Court

asserting breach of contract against CAS as an alleged third-party beneficiary to the

Agreement between MBH and CAS. Origo is seeking over $2 million in “lost profits”. {¶4} MBH, CAS, and Origo agreed to arbitrate the dispute pursuant to the terms

of the Agreement. CAS moved for summary judgment arguing that Origo was not entitled

to damages under the Agreement because Origo is a third-party beneficiary. Origo argued

that there is a direct conflict between Section 7 of Contract and Section 7 of the

Supplement. Origo argued that pursuant to Section 10 of the Supplement, Section 7 of

the Supplement supersedes Section 7 of the Contract.

{¶5} The three provisions of the Agreement at issue are:

Section 7 of the Contract:

In no event shall contractor and its subcontractors be liable to customer

or another party for incidental, special, exemplary, punitive or

consequential damages, including loss of income or profits, lost revenues

or any economic loss, whether such customer or party has been advised

of the possibility of such damage, and whether any claim for recovery is

based on the theories of contract, warranty, tort (including negligence or

strict liability) or otherwise. In no event shall contractor’s and its

subcontractors’ aggregate liability to customer and any third party in

connection with the contract, for all other damages, exceed the project

total contract price. The remedies stated in this contract are exclusive.

Section 7 of the Supplement:

Indemnification. Contractor hereby releases Customer, its members,

managers, partners, affiliates, employees, managers, representatives,

agents, successors, and assigns, and agrees to defend, indemnify and

hold harmless Customer, its members, managers, partners, affiliates, employees, representatives, agents and successors, and assigns, for and

against all claims, causes of actions willful misconduct or gross

negligence. Without limiting the generality, demands, judicial and

administrative proceedings, losses, liabilities, damages, costs and

expenses, *** Notwithstanding the foregoing, this provision shall not apply

to such claims that are caused by Customer’s willful misconduct or gross

negligence. Without limiting the generality of the foregoing, Contractor

further agrees to indemnify Customer, its members, managers, partners,

affiliates, employees, representatives, agents and successors, and

assigns, against and hold and save Customer, its members, managers,

partners, successors, and assigns, against and hold and save Customer,

its members, managers, partners, affiliates, employees, managers,

representatives, agents, successors, and assigns harmless from any and

all claims, causes of action, fines, costs, expenses **** arising or resulting

from, in conjunction with, or due to: (i) any act or omission of Contractor,

its officers, employees, contractors, or servants which results in (A) injury

to or death of person, including employees of Contractor, (B) damage to

any property, (C) defects of materials or workmanship required under the

Construction Contract ***; or (D) lack of full and strict compliance by

Contractor’s employees, agents, materialmen and subcontractors with all

safety, civil rights and equal employment opportunity ****; or (iii) [sic]

breach of any covenant or agreement contained in the Construction

Contract or this Supplement or misrepresentation of any material fact or omission concerning the Construction Contract, this Supplement, or the

Project.

Section 10 of the Supplement:

Construction Contract. Notwithstanding any term or condition to the

contrary contained in the Construction Contract or otherwise, any and all

terms and conditions set forth in this Supplement shall (a) supplement the

Construction Contract to the extent any term or condition set forth here

that is not set forth in the Construction Contract; (b) override, amend,

revise, change, modify, replace, and restate any and all terms and or

conditions contained in the Construction Contract that conflicts, in any

respect, with any term or condition contained herein and (c) be

incorporated into and made a part of the Construction Contract.

{¶6} The arbitrator granted summary judgment in favor of CAS on November 29,

2023, finding that the Agreement between MBH and CAS was unambiguous and

precluded claims by an alleged third-party beneficiary, including Origo. The arbitrator

specifically found that there was no genuine issue of material fact pertaining to Origo’s

status as a third-party beneficiary. (Order as to Respondent CAS’s Motion for Summary

Judgment, p.4)

{¶7} Origo filed a Motion for Reconsideration. Upon reconsideration of his

decision, the arbitrator stated that he reviewed his notes, the original ruling and the recent

briefs submitted by the parties, but his ruling is unchanged. The arbitrator issued an Order

as to [Origo’s] Motion for Reconsideration holding that “the reason for the Arbitrator’s

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Elon Property Mgt. Co., L.L.C. v. Shif Rockside Place, L.L.C.
2026 Ohio 735 (Ohio Court of Appeals, 2026)

Cite This Page — Counsel Stack

Bluebook (online)
2025 Ohio 897, Counsel Stack Legal Research, https://law.counselstack.com/opinion/feed-fat-co-llc-v-custom-agri-sys-inc-ohioctapp-2025.