Young v. Univ. of Akron, 06ap-1022 (9-11-2007)

2007 Ohio 4663
CourtOhio Court of Appeals
DecidedSeptember 11, 2007
DocketNo. 06AP-1022.
StatusPublished
Cited by19 cases

This text of 2007 Ohio 4663 (Young v. Univ. of Akron, 06ap-1022 (9-11-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Young v. Univ. of Akron, 06ap-1022 (9-11-2007), 2007 Ohio 4663 (Ohio Ct. App. 2007).

Opinion

OPINION
{¶ 1} Plaintiff-appellant, Tammy Young, the administratrix of the estate of Douglas Young, appeals from a judgment of the Court of Claims of Ohio granting summary judgment in favor of defendant-appellee, The University of Akron. For the following reasons, we affirm in part and reverse in part. *Page 2

{¶ 2} In 1994, Guy Marrelli, an electrical engineer who worked for appellee since 1990, was informed that the existing oil switchgears on appellee's campus should be replaced. A switchgear is a device that controls, meters, and protects the flow of electric power. Switchgears were located in different areas of appellee's campus to control the flow of electricity from electrical substations to various campus buildings.

{¶ 3} Sometime in 1998, Marrelli completed project drawings and specifications for the switchgear replacement and the project was bid. Pursuant to that bidding process, appellee awarded the project to Thompson Electric ("Thompson"). Thompson agreed to provide all necessary materials to complete the project in accordance with Marrelli's specifications. As part of those specifications, appellee required Thompson to notify it of any changes in the work with a written addendum or change order. Appellee also required Thompson to keep "as-built" drawings, which would show the actual work performed where the work differed from the original project drawings. Thompson was to record any approved changes on the as-built drawings. The specifications also prohibited Thompson from making any substitutions.

{¶ 4} Switchgears include a structure known as a bushing which provides an insulated entrance into the switchgear for an energized conductor. In essence, the bushing is the point of entry where a cable carrying electricity connects to the switchgear so that the switchgear can then transform the electricity and transport it to its intended destination. The bushing also prevents energized conductors from coming into contact with each other and the switchgear itself. The switchgear involved in this case contained four rows of bushings with three bushings in each row. Marrelli's project drawings specified that the new switchgears were to have 200 amp bushings. Marrelli's *Page 3 specifications also required that the energized cables connect to the bushings with 200 amp load break elbows. Load break elbows provide an insulated high voltage connection for the energized cable to connect to the switchgear. Load break elbows allow the switchgear to be "dead front," meaning that the electrical cables are fully insulated and the switchgear can be disconnected or operated while energized (under load) assuming all other safety precautions are taken.

{¶ 5} Although the project specifications required 200 amp bushings, Thompson submitted drawings showing 600 amp bushings. Nevertheless, Marrelli approved Thompson's drawings, and Thompson purchased 600 amp bushings for the project. This change in the bushings created a problem because the specified 200 amp load break elbows were incompatible with, and could not be connected to, the 600 amp bushings.

{¶ 6} Douglas Young ("Young") was a Thompson employee and the foreman for this project. When it was discovered that the 200 amp load break elbows would not fit the 600 amp bushings, Young spoke with his boss, division manager William Anderson, and a sales representative from the company who sold the switchgear, Haverstock Bowers. Pursuant to that conversation, the decision was made to tape the connections with 130C 3M electrical tape. Apparently, Young taped the connections himself. Thompson did not submit a change order for the new connections to Marrelli, nor did it make any as-built drawings showing the taped connections. Young and Anderson subsequently told Marrelli about the incompatibility of the bushings and the load break elbows and the need to tape the connections. Marrelli contends that he did not know about the taped connections until May 1999, when he made a final inspection of Thompson's work. *Page 4

Marrelli testified that he accepted the taped connections only after Thompson assured him that the connections were safe.

{¶ 7} On May 16, 2001, Young was working on the switchgear that contained the taped connections. During the course of his work, Young was electrocuted and died as a result of the injuries he sustained. Thereafter, appellant filed the instant complaint against Marrelli and appellee. Appellant alleged that appellee's negligence caused Young's death. Appellant further alleged that Marrelli's willful, wanton and reckless conduct also caused Young's death. After an evidentiary hearing, the trial court determined that Marrelli did not act with malicious purpose, in bad faith, or in a wanton or reckless manner. Thus, the trial court determined that he was entitled to civil immunity. R.C. 2743.06(F); R.C. 9.86. This court affirmed that determination.Young v. Univ. of Akron, Franklin App. No. 04AP-318, 2004-Ohio-6720.

{¶ 8} The case proceeded against appellee, who filed a motion for summary judgment. Appellee argued that it was entitled to judgment as a matter of law based on either discretionary immunity or comparative negligence principles. The trial court found that Marrelli's decisions to approve the project drawings and to accept the taped connections required a high degree of judgment and discretion. Therefore, the trial court determined that appellee was immune from liability based on the doctrine of discretionary immunity. The trial court did not address appellee's comparative negligence argument.

{¶ 9} Appellant appeals and assigns the following errors:

I. THE COURT OF CLAIMS ERRED BY GRANTING SUMMARY JUDGMENT FOR DEFENDANT, UNIVERSITY OF AKRON ON THE BASIS THAT THE UNIVERSITY OF AKRON HAD DISCRETIONARY IMMUNITY AS A RESULT OF MAKING A BASIC POLICY DECISION *Page 5 CHARACTERIZED BY A HIGH DEGREE OF OFFICIAL JUDGMENT OR DISCRETION.

II. THE COURT OF CLAIMS ERRED BY BASING ITS DECISION ON DISPUTED FACTS UPON WHICH REASONABLE MINDS COULD DRAW DIFFERENT CONCLUSIONS.

III. THE COURT OF CLAIMS ERRED BY NOT TAKING INTO CONSIDERATION ALL OF THE EVIDENCE THAT WAS OBTAINED SUBSEQUENT TO THE IMMUNITY HEARING CONDUCTED ON DECEMBER 11 AND 12, 2003.

{¶ 10} Appellee also filed the following cross-assignment of error:

THE TRIAL COURT ERRED BY NOT RULING THAT UNDER A COMPARATIVE NEGLIGENCE ANALYSIS PLAINTIFF'S DECEDENT'S NEGLIGENCE FAR EXCEEDED ANY NEGLIGENCE ON THE PART OF APPELLEE.

{¶ 11} Appellant appeals from the trial court's summary judgment decision. Appellate review of a trial court's grant of summary judgment is de novo. AAAA Enterprises, Inc. v. River Place Community UrbanRedevelopment Corp. (1990), 50 Ohio St.3d 157; Hahn v. Satullo,156 Ohio App.3d 412, 2004-Ohio-1057, at ¶ 33. "De novo review means that this court uses the same standard that the trial court should have used, and we examine the evidence to determine whether as a matter of law no genuine issues exist for trial." Brewer v. Cleveland City Schools Bd. ofEdn. (1997), 122 Ohio App.3d 378,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fox v. Schwartz & Dompier
2026 Ohio 1025 (Ohio Court of Appeals, 2026)
Klickovich v. State Med. Bd. of Ohio
2026 Ohio 31 (Ohio Court of Appeals, 2026)
McDermott v. Ohio State Univ.
2025 Ohio 396 (Ohio Court of Appeals, 2025)
State v. Enyart
2023 Ohio 3373 (Ohio Court of Appeals, 2023)
Williams v. PNC Bank, N.A.
2022 Ohio 4287 (Ohio Court of Appeals, 2022)
Anderson v. Bright Horizons Children's Ctrs., L.L.C.
2022 Ohio 1031 (Ohio Court of Appeals, 2022)
State v. Day
2019 Ohio 1327 (Ohio Court of Appeals, 2019)
Cleveland v. State
2019 Ohio 315 (Ohio Court of Appeals, 2019)
State v. Cline
2013 Ohio 5399 (Ohio Court of Appeals, 2013)
State v. Price
2013 Ohio 5329 (Ohio Court of Appeals, 2013)
State v. Lovings
2013 Ohio 5328 (Ohio Court of Appeals, 2013)
State v. Wilson
2013 Ohio 4799 (Ohio Court of Appeals, 2013)
Willoby v. Ohio Dept. of Transp.
2013 Ohio 3633 (Ohio Court of Claims, 2013)
Kasotis v. Ohio Dept. of Transp.
2013 Ohio 3632 (Ohio Court of Claims, 2013)
City of Riverside v. State
944 N.E.2d 281 (Ohio Court of Appeals, 2010)
Estate of Morgan v. Ohio Dept. of Transp.
2010 Ohio 1532 (Ohio Court of Claims, 2010)
Young v. Univ. of Akron
880 N.E.2d 482 (Ohio Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 4663, Counsel Stack Legal Research, https://law.counselstack.com/opinion/young-v-univ-of-akron-06ap-1022-9-11-2007-ohioctapp-2007.