X.L.O. Concrete Corp. v. John T. Brady & Co.

104 A.D.2d 181, 482 N.Y.S.2d 476, 1984 N.Y. App. Div. LEXIS 20611
CourtAppellate Division of the Supreme Court of the State of New York
DecidedDecember 6, 1984
StatusPublished
Cited by40 cases

This text of 104 A.D.2d 181 (X.L.O. Concrete Corp. v. John T. Brady & Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
X.L.O. Concrete Corp. v. John T. Brady & Co., 104 A.D.2d 181, 482 N.Y.S.2d 476, 1984 N.Y. App. Div. LEXIS 20611 (N.Y. Ct. App. 1984).

Opinion

OPINION OF THE COURT

Sullivan, J. P.

This appeal presents the question of whether a construction contract clause providing recompense to the owner at a stipulated amount per day for the contractor’s delay in completing the project is vitiated by the owner’s own culpability in causing at least some of the delay, so that the owner is free to seek actual delay damages in excess of the sum stipulated. We hold that it is not.

On or about June 15, 1979, John T. Brady and Company, a general contractor, entered into an agreement with New York University (N.Y.U.) to furnish, for the sum of $14,993,000, all of the work, labor and materials required for the construction of a new residence hall for students attending the university’s School of Law. In accordance with the contract’s requirements, Federal Insurance Company posted a performance bond guaranteeing full performance by Brady of its contractual obligations. The contract, which provided for substantial completion of the work on or before June 15,1981, contained a liquidated damage clause entitling N.Y.U. to deduct from any amounts otherwise due Brady $2,000 per day for each day beyond June 15, 1981 that the work remained uncompleted.

The June 15, 1981 completion date was critical to N.Y.U., which was concerned that the residence hall be ready to house the 630 or more students who were scheduled to arrive for the beginning of the fall semester. Construction on the project began on or about June 25,1979. The date of its completion is in issue. While Brady contends that it completed construction in or about June, 1981, N.Y.U. claims that the residence hall had not been substantially completed when the students arrived in early September, 1981. In any event, on March 6, 1981, plaintiff X.L.O. Concrete Corp., a subcontractor engaged by Brady to perform a portion of the concrete work, commenced this action against Brady (and against Federal on its bond), seeking a balance allegedly due on the adjusted subcontract price, as well as the value of the labor furnished and material supplied in performing extra and change order work, and the additional costs incurred by reason of delay caused by Brady’s interference with the performance and completion of its subcontract. Brady [183]*183thereafter impleaded N.Y.U. and its architect, seeking, inter alia, indemnification for any recovery by X.L.O. against it on the ground that any damage sustained by X.L.O. was caused by the wrongful acts and omissions of N.Y.U. and its architect.

N.Y.U.’s answer to the third-party complaint contained a seventh affirmative defense which, by way of a counterclaim against Brady and cross claim against Federal, seeks actual and consequential damages caused by, inter alia, Brady’s alleged delay in its performance of the contract. The eighth affirmative defense included a counterclaim against Brady which seeks liquidated damages, “in an amount not as yet determined but which it is believed will exceed the sum of $50,000,” pursuant to contract provision therefor at the rate of $2,000 per day for each day the work was allegedly delayed by Brady beyond June 15, 1981. Brady and Federal moved for partial summary judgment dismissing N.Y.U.’s claim for actual and consequential damages asserted in the seventh affirmative defense, by way of counterclaim and cross claim against Brady and Federal, respectively. In so moving, Brady and Federal argued that N.Y.U. is precluded from asserting a delay damage claim against them since the contract’s liquidated damage clause provides the sole and exclusive remedy for any delay damage sustained by it. Special Term denied the motion, finding triable issues of fact. We reverse and strike from the counterclaim and cross claim asserted in the seventh affirmative defense any request for actual and consequential delay damages.

Parties to a contract may provide for anticipatory damages in the event of failure to complete performance within the time specified, as long as such agreement is neither unconscionable nor contrary to public policy. (Mosler Safe Co. v Maiden Lane Safe Deposit Co., 199 NY 479, 485.) Absent statutory authority, the imposition of penalties or forfeitures contravenes public policy. (City of Rye v Public Serv. Mut. Ins. Co., 34 NY2d 470, 472-473.) If the amount stipulated in the liquidated damage clause is manifestly disproportionate to the actual damage, then its purpose is not to “provide fair compensation but to secure performance by the compulsion of the very disproportion.” (Truck Rent-A-Center v Puritan Farms 2nd, 41 NY2d 420, 424.) Thus, the rule has evolved that when the damages flowing from the breach of a contract are easily ascertainable, or the damages fixed are plainly disproportionate to the injury, the stipulated sum will be treated as a penalty (Mosler Safe Co. v Maiden Lane Safe Deposit Co., supra, p 485), but, where they are uncertain, or difficult, if not incapable, of ascertainment, then a provision liquidating them in advance of loss will be enforced, if the [184]*184amount liquidated bears a reasonable proportion to the probable loss. (City of Rye v Public Serv. Mut. Ins. Co., supra, p 473; Wirth & Hamid Fair Booking v Wirth, 265 NY 214, 223.) Whether the sum stipulated represents a liquidation of the anticipated damages or a penalty is a question of law, with due consideration for the nature of the contract and the attendant circumstances. (Mosler Safe Co. v Maiden Lane Safe Deposit Co., supra, p 485.) Moreover, the agreement should be interpreted as of the date of its execution, not the date of its breach. (See Seidlitz v Auerbach, 230 NY 167, 172.)

In light of these principles, we conclude that the liquidated damage clause is valid. It should be noted that N.Y.U. has not challenged, nor could it, the validity of the clause on the ground that the amount specified bears no rational relationship to the amount of actual delay damages which it reasonably anticipated at the time the contract was executed. In any event, N.Y.U., which prepared and drafted the contract and imposed both the liquidated damage provision and the $2,000 per day figure, could hardly argue that the provision constituted a penalty designed to induce performance rather than a means of providing “just compensation for loss” (Truck Rent-A-Center v Puritan Farms 2nd, supra, p 424). Nor can N.Y.U., which, alone, was in the best position to estimate the harm to be caused by delay, and the amount of compensation needed to redress that harm, now argue that the liquidated damage clause is invalid because it does not adequately compensate for the alleged actual delay damages.

The rule is well established that a valid contractual provision for liquidated damages controls the rights of the parties in the event of a breach, notwithstanding that the stipulated sum may be less than the actual damages allegedly sustained by the injured party. (General Supply & Constr. Co. v Goelet, 241 NY 28, 37-38; Estate of Richter v Novo Corp., 43 AD2d 1; Sulyok v Penzintezeti Kozpont Budapest, 279 App Div 528.) As early as 1902, the Court of Appeals recognized that “when the parties by their contract provide for the consequences of a breach, lay down a rule to admeasure the damages and agree when they are to be paid, the remedy thus provided must be exclusively followed.” (McCready v Lindenborn,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Populus Media, Inc. v. Erb
S.D. New York, 2024
NGM Mgt. Group, LLC v. Bareburger Group, LLC
2024 NY Slip Op 00979 (Appellate Division of the Supreme Court of New York, 2024)
Parkmerced Invs., LLC v. WeWork Cos. LLC
2023 NY Slip Op 03290 (Appellate Division of the Supreme Court of New York, 2023)
Jefferies LLC v. Gegeheimer
S.D. New York, 2020
Jannetti v. Whelan
2018 NY Slip Op 7108 (Appellate Division of the Supreme Court of New York, 2018)
Wenger Constr. Co., Inc. v. City of Long Beach
2017 NY Slip Op 5761 (Appellate Division of the Supreme Court of New York, 2017)
Trilegiant Corp. v. Orbitz, LLC
45 Misc. 3d 348 (New York Supreme Court, 2014)
Grynberg v. Advance Nanotech, Inc.
79 A.D.3d 480 (Appellate Division of the Supreme Court of New York, 2010)
Blue Heron Construction Co., LLC v. Village of Nunda
63 A.D.3d 1694 (Appellate Division of the Supreme Court of New York, 2009)
Days Inns Worldwide v. Mandir, Inc.
393 F. Supp. 2d 1240 (W.D. Oklahoma, 2005)
McKesson Automated Healthcare, Inc. v. Brooklyn Hosp. Ctr.
2004 NY Slip Op 24205 (New York Supreme Court, Kings County, 2004)
McKesson Automated Healthcare, Inc. v. Brooklyn Hospital Center
4 Misc. 3d 491 (New York Supreme Court, 2004)
Hunts Point Multi-Service Center, Inc. v. Terra Firma Construction Management & General Contracting, LLC
5 A.D.3d 183 (Appellate Division of the Supreme Court of New York, 2004)
Special Situations Fund III v. Attunity, Ltd.
3 A.D.3d 408 (Appellate Division of the Supreme Court of New York, 2004)
Federal Realty Ltd. Partnership v. Choices Women's Medical Center, Inc.
289 A.D.2d 439 (Appellate Division of the Supreme Court of New York, 2001)
Lease Corp. of America, Inc. v. Resnick
288 A.D.2d 533 (Appellate Division of the Supreme Court of New York, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
104 A.D.2d 181, 482 N.Y.S.2d 476, 1984 N.Y. App. Div. LEXIS 20611, Counsel Stack Legal Research, https://law.counselstack.com/opinion/xlo-concrete-corp-v-john-t-brady-co-nyappdiv-1984.