Wyckoff Farms Incorporated v. Industrial Control Concepts Inc

District Court, E.D. Washington·Decided September 26, 2022·No. 4:20-cv-05095·Unknown

Opinion

EASTERN DISTRICT OF WASHINGTON

WYCKOFF FARMS, INCORPORATED, a Washington CASE NO: 4:20-CV-5095-TOR Corporation, Plaintiff, FINDINGS OF FACT AND v. INDUSTRIAL CONTROL CONCEPTS, INC. d/b/a ICC, INC., a Missouri corporation, ICC NORTHWEST, INC., an Oregon corporation, ICC TURNKEY, INC., a Missouri corporation; ALEX ALEXANDROV, an individual; and MICHAEL NEWMAN, an individual,

Defendants.

The Court held a bench trial from July 25-29, 2022. Daniel M. Weiskopf and Claire Martirosian appeared on behalf of Plaintiff/Counterclaim Defendant. Robert W. Novasky appeared on behalf of Defendants/Counterclaim Plaintiffs. The Court has reviewed the briefing and the record and files herein, considered the evidence and the parties’ arguments, and is fully informed. Pursuant to Federal

Rule of Civil Procedure 52(a), below are the Court’s Findings of Fact and Conclusions of Law. To the extent a finding of fact or conclusion of law is deemed the opposite, the label the Court places on the finding does not control.

This case concerns various contract disputes regarding the building of a cannabinoid extraction facility. Plaintiff’s second amended complaint raises the following claims: (1) breach of contract, (2) breach of contract – anticipatory

repudiation, (3) unjust enrichment, (4) breach of contract – defend and indemnify, (5) fraud, and (6) unfair and deceptive business practices. ECF No. 82. Only claim (5) for fraud pertains to the individual Defendants, as well as the ICC Group. The

ICC Group raises the following counterclaims: (1) breach of contract and (2) unjust enrichment – quantum meruit. ECF No. 17. The Court entered partial summary judgment in favor of Plaintiff on claim (4) for the breach of contract claim for failure to defend and indemnify and has awarded

three judgments associated with that claim for related state court litigation. ECF Nos. 54, 74, 120. On July 12, 2022, the Court held a pretrial conference and ruled on the

parties’ motions in limine and reserved ruling on the parties’ witness and exhibit lists until trial. ECF No. 147. A bench trial was held from July 25 to July 29, 2022. The Court heard

testimony from the following witnesses and experts: David Wyckoff, Ryan Coates, Dan Gustafiv, Patricia Westmoreland, Sherri Pierce, David Pierce, Alex Alexandrov, Michael Newman, and Arik Van Zandt. All witnesses and experts

were cross-examined. The Court also admitted into evidence various exhibits, including five deposition transcripts. The Court overrules Defendants’ objection to the introduction of David E. Kekec’s deposition. Pursuant to Federal Rule of Civil Procedure 32(a), Defendant’s counsel attended the deposition by videoconference,

had the opportunity to cross-examine, and the witness resides more than 100 miles from the Court. Thus, those portions of his deposition designated by Plaintiff are admitted. Having considered all the foregoing evidence, the Court now issues the

following Findings of Fact and Conclusions of Law. A number of facts were stipulated by the parties in the Joint Pretrial

Statement (ECF No. 151). Those facts are accepted by the Court without further proof. The remaining findings of fact are based on evidence presented at trial. Each finding that is not stipulated to is based on a preponderance of the evidence

standard, unless otherwise stated. 1. Wyckoff Farms Incorporated (“WFI”) is a farming and crop processing company based out of Grandview, Washington. For over six decades, WFI

has farmed, processed, and packaged a variety of crops at its properties in Eastern Washington. 2. David Wyckoff, CEO of WFI, has worked in agriculture for approximately

47 years. Mr. Wyckoff has a juris doctor degree and practiced law before working at WFI, the Wyckoff family business. 3. Industrial Control Concepts (“ICC”) manufactures stainless steel tanks and provides engineering services for various industries, including distilling and

brewing, food and beverage, and hemp and CBD. ICC has offices in Oregon, Honolulu, Illinois, Missouri, and South Carolina. 4. In 2019, WFI sought to construct a cannabinoid extraction plant in Prosser,

Washington (“the Project”). 5. WFI and ICC entered into multiple agreements regarding the Project. 6. On or about May 17, 2019, the parties executed an agreement for the purchase of 22 tanks and tank-related equipment for a fixed fee of $876,000

(the “Tank Contract”). No damages are sought regarding the Tank Contract. 7. Wyckoff paid ICC $876,000 under the Tank Contract. 8. On or about June 14, 2019, the parties executed an agreement for process

engineering of the Project (the “Engineering Contract”). ICC agreed, for a fixed fee of $212,000 and reasonable out of pocket travel expenses. Wyckoff paid ICC $212,000 under the Engineering Contract. No damages are sought

regarding the Engineering Contract. 9. On or about August 9, 2019, the parties executed an Interconnection Piping Build/Install contract (the “Piping Contract”). ICC agreed to provide final

design/fabrication, delivery, and installation of certain “interconnection” piping for (1) a fixed fee of $368,000; and (2) a non-binding estimate of T&M (Time and Materials) of $110,000 to $125,000 plus travel expenses with a not to exceed $135,000 for the contract scope unless agreed to prior.

10. On or about August 19, 2019, the parties executed a Controls Build/Install contract for the Project (the “Controls Contract”). The Controls Contract provided for: (1) a fixed fee of $801,000; (2) a non-binding estimate for time

and travel costs for install of $115,000 to $135,000 with a not to exceed of $140,000 for the contract scope unless agreed to prior; (3) a non-binding estimate for commissioning and start up engineering time and travel costs of $42,000 to $48,000 with a not to exceed $54,000 for the contract scope

unless agreed to prior. 11. WFI paid ICC $600,750 under the fixed fee portion of the Controls Contract.

12. On October 9, 2019, ICC represented it had identified missing equipment currently not supplied by any other vendors under contract and certain other

work not covered by the prior agreements between ICC and WFI. ICC told WFI that WFI needed to execute a contract to “close the gaps” so that the project could be completed.

13. On October 9, 2019, WFI and ICC executed the Gap Closure Build/Install Contract (the “Gap Contract”). Included with the Gap Contract was a highlighted P&ID that ICC claimed represented its understanding of existing scope ownership and the remaining gap scope to be addressed. ICC agreed

to provide the scope changes and gap closure for (1) a fixed fee of $1,638,195; and (2) estimated T&M costs covering “commissioning and install labor time” of $922,572 plus travel costs.

14. The Gap Contract allowed for overtime to reduce schedule timeline regarding mechanical and electrical installation, at a cost to WFI. No other contract contained a provision for overtime. 15. WFI paid $1,638,195 under the fixed fee portion of the Gap Contract.

16. The Engineering Contract, Piping Contract, Controls Contract, and Gap Contract all incorporate the same Appendix 1, General Terms and Conditions (“Terms and Conditions”).

17. The Terms and Conditions provide, among other things, that: a. “Agreements reached and/or contracts issued as a result of acceptance of all or part of this proposal by the Client or the Client’s authorized

representative(s) may be terminated upon thirty (30) days written notice by either party.” b. “Cancellation with immediate effect is justified if the other party is

Free access — add to your briefcase to read the full text and ask questions with AI

Wyckoff Farms Incorporated v. Industrial Control Concepts Inc, (E.D. Wash. 2022).

Wyckoff Farms Incorporated v. Industrial Control Concepts Inc (Wyckoff Farms Incorporated v. Industrial Control Concepts Inc) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Prier v. Refrigeration Engineering Co.
442 P.2d 621 (Washington Supreme Court, 1968)
Hangman Ridge Training Stables, Inc. v. Safeco Title Insurance
719 P.2d 531 (Washington Supreme Court, 1986)
Baertschi v. Jordan
413 P.2d 657 (Washington Supreme Court, 1966)
Wallace Real Estate Investment Inc. v. Groves
881 P.2d 1010 (Washington Supreme Court, 1994)
VersusLaw, Inc. v. Stoel Rives, L.L.P.
111 P.3d 866 (Court of Appeals of Washington, 2005)
Fairchild v. Dean
86 P.2d 271 (Washington Supreme Court, 1939)
Vance v. Mutual Gold Corp.
108 P.2d 799 (Washington Supreme Court, 1940)
Safeco Insurance v. Woodley
150 Wash. 2d 765 (Washington Supreme Court, 2004)
Jones v. Jones
152 Wash. 2d 1 (Washington Supreme Court, 2004)
Lehrer v. Department of Social & Health Services
5 P.3d 722 (Court of Appeals of Washington, 2000)
DC Farms, LLC v. Conagra Foods Lamb Weston, Inc.
317 P.3d 543 (Court of Appeals of Washington, 2014)
Top Line Builders, Inc. v. Bovenkamp
320 P.3d 130 (Court of Appeals of Washington, 2014)