Wyckoff Farms Incorporated v. Industrial Control Concepts Inc

District Court, E.D. Washington·Decided October 27, 2020·No. 4:20-cv-05095·Unknown

Opinion

EASTERN DISTRICT OF WASHINGTON

INCORPORATED, a Washington NO. 4:20-CV-5095-TOR corporation, ORDER DENYING DEFENDANTS’ Plaintiff, MOTION TO DISMISS AND ALTERNATIVE MOTION FOR A v. MORE DEFINITE STATEMENT

CONCEPTS, INC., d/b/a ICC, INC., a Missouri corporation, ICC NORTHWEST, INC., an Oregon corporation, and ICC TURNKEY, INC., a Missouri corporation, Defendants.

BEFORE THE COURT is Defendants’ Motion to Dismiss for Failure to State a Claim and Alternative Motion for a More Definite Statement (ECF No. 11). These matters were submitted for consideration without oral argument. The Court has reviewed the record and files herein, the completed briefing, and is fully informed. For the reasons discussed below, Defendants’ Motion to Dismiss for Failure to State a Claim and Alternative Motion for a More Definite Statement (ECF No. 11) is DENIED.

This case generally concerns construction contracts related to an extraction facility. ECF No. 1. On June 12, 2020, Plaintiff filed a Complaint against

Defendants Industrial Control Concepts Inc. (“ICC”), ICC Northwest, Inc. (“ICC NW”), and ICC Turnkey, Inc. (“ICC Turnkey”). ECF No. 1. On September 10, 2020, Defendants filed the instant Motion to Dismiss for Failure to State a Claim and Alternative Motion for a More Definite Statement. ECF No. 11. Plaintiff and

Defendants timely filed their respective response and reply. ECF Nos. 12-13. The following facts are drawn from Plaintiff’s Complaint and construed in the light most favorable to Plaintiff. Shwarz v. United States, 234 F.3d 428, 435 (9th Cir.

2000). In May 2019, Plaintiff Wyckoff Farms solicited quotes from Defendants for stainless steel tanks for use in an extraction plant Plaintiff intended to build in Prosser, Washington. ECF No. 1 at 2, ¶ 8. On May 17, 2019, the parties executed

an agreement (the “Tank Contract”) for the purchase of 30 stainless steel tanks for $876,000. ECF No. 1 at 3, ¶ 9. On or about June 14, 2019, the parties executed a second agreement (the

“Engineering Contract”) pertaining to the engineering of the extraction plant. ECF No. 1 at 3, ¶ 11. The Engineering Contract required Defendants “to deliver ‘an engineering report, documents, diagrams, and models that integrate and close the

gaps between the various components of the Wyckoff Extraction facility…’ and prepare proposals for the piping system, multi zone CIP system, and integrated control and data collection system.” ECF No. 1 at 3, ¶ 12. Defendants represented

that the Engineering Contract would “identify the full scope of work and materials required to integrate the various components” needed for the extraction facility. ECF No. 1 at 3, ¶ 13. On or about August 9, 2019, the parties executed a third agreement (the

“Piping Contract”) regarding the interconnective piping needed at the extraction facility. ECF No. 1 at 3, ¶ 14. The Piping Contract “required [Defendants] to design, fabricate, and deliver piping needed to connect the various Extraction

Project components for a fixed price of $368,000.” ECF No. 1 at 4, ¶ 15. Defendants also “agreed to install and build the Piping Contract system on a time and material basis plus travel expenses, not to exceed $135,000. ECF No. 1 at 4, ¶ 16.

On or about August 19, 2019, the parties executed a fourth agreement (the “Control System Contract”) regarding the electronic control system needed at the extraction facility. ECF No. 1 at 4, ¶ 17. The Control System Contract “required

[Defendants] to design, fabricate, and deliver the electronic system needed to operate the various Extraction Project components at a fixed price of $801,000.” ECF No. 1 at 4, ¶ 18. Defendants “agreed to install and build the Control System

Contract components on a time and materials basis plus travel expenses, not to exceed $140,000.” ECF No. 1 at 4, ¶ 19. Additionally, under the Control System Contract, commissioning and start up was provided for at an hourly rate for the

commissioning and start-up engineer, not to exceed $54,000. ECF No. 1 at 4, ¶ 20. Finally, “out-of-scope materials necessary to carry the Piping Contract and Control System Contract were to be provided on a cost plus 10% basis.” ECF No. 1 at 4, ¶ 21.

Each contract incorporates the same appendix, requiring Defendants to “defend, indemnify, and hold harmless [Plaintiff] from and against all claims, actions, proceedings, liabilities, losses, damages, costs and expenses, arising out of

third party actions, including reasonable attorney’s fees and defense costs, which [Plaintiff] may sustain resulting from the acts or omissions of [Defendants].” ECF No. 1 at 7, ¶¶ 39-40. Once the parties executed the four contracts, Defendants notified Plaintiff

that it “identified 686 missing pieces of equipment, valves, instruments, and specialty items that [were] currently not supplied by any other vendor under contract. In addition … substantial amounts of installation, including piping,

insulation, structures, and electrical work, is uncovered.” ECF No. 1 at 5, ¶ 22. Defendants informed Plaintiff that an additional agreement (the “Gap Contract”) was needed to address the missing equipment and uncovered work. ECF No. 1 at

5, ¶ 24. Plaintiff relied on Defendants’ expertise and representations and executed the Gap Contract, requiring Defendants “to procure and deliver all remaining materials needed to operate the various Extraction Project components at a fixed

price of $1,638,195.” ECF No. 1 at 5, ¶ 25. Defendants “agreed to install the Gap Contract components on a time and materials basis, estimated at $922,572, plus travel expenses.” ECF No. 1 at 5, ¶ 26. Additional out-of-scope materials necessary for this contact were to be provided on a cost plus 15% basis. ECF No.

1 at 6, ¶ 27. In April 2020, Plaintiff discovered Defendants had significantly overbilled on the extraction facility projects by double-billing certain equipment and

materials, charging for work not actually performed, and charging for travel expenses not related to the contracts or pre-approved by Plaintiff. ECF No. 1 at 6, ¶¶ 29-31, 33. Plaintiff requested documentation to substantiate the bills, and Defendants submitted falsified time card records. ECF No. 1 at 6, ¶ 32.

That same month, Plaintiff discovered that Defendants were not paying their subcontractors. ECF No. 1 at 7, ¶ 35. As a result, Plaintiff sought assurances that Defendants could complete the contract work, which Defendants failed to provide.

ECF No. 1 at 7, ¶¶ 36-37. Plaintiff notified Defendants that it believed they anticipatorily repudiated their contracts, and Defendants subsequently discontinued all work on the extraction facility. ECF No. 1 at 7, ¶ 38.

On May 27, 2020 one of Defendants’ subcontractors, NIPR, LLP, recorded a Notice of Claim of Lien against Plaintiff’s property. ECF No. 1 at 7-8, ¶¶ 41-42. The lien claims that Defendant “ICC NW owes NIPR the principal amount of

$314,792.15 plus interest at a rate of 12% for work performed on the Extraction Project for which NIPR has not been paid.” ECF No. 1 at 8, ¶ 42. Defendants have refused to defend, indemnify, or hold harmless Plaintiff from the subcontractor’s lien as required under the appendix attached to each

contract. ECF No. 1 at 8, ¶ 43. Plaintiff has also overpaid Defendants no less than $1.3 million. ECF No. 1 at 6, ¶ 34.

A. Motion to Dismiss Standard Federal Rule of Civil Procedure 12(b)(6) provides that a defendant may move to dismiss the complaint for “failure to state a claim upon which relief can be granted.” “The burden of demonstrating that no claim has been stated is upon the

Free access — add to your briefcase to read the full text and ask questions with AI

Wyckoff Farms Incorporated v. Industrial Control Concepts Inc, (E.D. Wash. 2020).

Wyckoff Farms Incorporated v. Industrial Control Concepts Inc (Wyckoff Farms Incorporated v. Industrial Control Concepts Inc) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Dagley v. Russo
540 F.3d 8 (First Circuit, 2008)
State Farm Fire & Casualty Co. v. Huynh
962 P.2d 854 (Court of Appeals of Washington, 1998)
Hangman Ridge Training Stables, Inc. v. Safeco Title Insurance
719 P.2d 531 (Washington Supreme Court, 1986)
Wallace Real Estate Investment Inc. v. Groves
881 P.2d 1010 (Washington Supreme Court, 1994)
Hayden v. Mutual of Enumclaw Insurance
1 P.3d 1167 (Washington Supreme Court, 2000)
Mutual of Enumclaw Insurance v. USF Insurance
164 Wash. 2d 411 (Washington Supreme Court, 2008)
Young v. Young
164 Wash. 2d 477 (Washington Supreme Court, 2008)
Klem v. Washington Mutual Bank
295 P.3d 1179 (Washington Supreme Court, 2013)
Trujillo v. Northwest Trustee Services, Inc.
355 P.3d 1100 (Washington Supreme Court, 2015)
Lehrer v. Department of Social & Health Services
5 P.3d 722 (Court of Appeals of Washington, 2000)
Shwarz v. United States
234 F.3d 428 (Ninth Circuit, 2000)