Wyatt Inc. v. CITIZENS BANK OF PA

976 A.2d 557, 2009 Pa. Super. 107, 2009 Pa. Super. LEXIS 1008
CourtSuperior Court of Pennsylvania
DecidedJune 4, 2009
Docket1829 WDA 2007, No. 1921 WDA 2007. No. 1928 WDA 2007. No. 1929 WDA 2007 No. 1930 WDA 2007 No. 1931 WDA 2007
StatusPublished
Cited by63 cases

This text of 976 A.2d 557 (Wyatt Inc. v. CITIZENS BANK OF PA) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wyatt Inc. v. CITIZENS BANK OF PA, 976 A.2d 557, 2009 Pa. Super. 107, 2009 Pa. Super. LEXIS 1008 (Pa. Ct. App. 2009).

Opinion

OPINION BY

POPOVICH, J.:

¶ 1 These six appeals stem from the September 28, 2007 judgment in a Mechanics’ Lien action entered in favor of the *560 plaintiffs Wyatt, Inc., Apostólos Group, Inc., Mendel Steel and Ornamental Iron Co., Lighthouse Electric Co., and James E. Huckestein, Inc., (collectively Subcontractors) and against Citizens’ Bank. Each party filed an appeal, and because the issues on appeal arise from the same factual scenario and involve similar arguments, we will address them contemporaneously. Upon review, we vacate the judgment and remand for computations consistent with this Opinion.

Citizens’ contract with Carlson

¶ 2 The causes of action arose from work performed at Three Mellon Bank Center in Pittsburgh, Pennsylvania, a 41-story office building built in the late 1940s. Mellon Bank was the owner of the premises and, in 2001, entered into a ten-year lease with Citizens for approximately 206,000 square feet of space in Three Mellon Center. 1

¶ 3 Prior to this time, Citizens did not have a banking presence in Western Pennsylvania. In an effort to expand into this region, Citizens leased the space of Three Mellon Center in order to perform banking functions and to construct a regional headquarters, which included executive offices.

¶4 In an effort to utilize the leased space in a specific manner, Citizens retained Carlson Implementation Associates, Inc., as the construction company responsible for the design and renovation of the leased space (Project). The leased space was not suitable to Citizens’ needs in its pre-Project condition. Prior to the Project, Mellon used the leased space for its walk-up banking business. Carlson was the only construction company interviewed by Citizens, and the job was not put out for competitive bids.

¶ 5 Carlson initially submitted a Guaranteed Maximum Price (GMP) proposal to Citizens which set the maximum price of construction at approximately $12 million. Under the terms of the proposal, Carlson was to be “at risk” or would incur all costs of performing the Project even if the total costs exceeded the adjusted contract sum.

¶ 6 On or about October 15, 2001, Citizens entered into an American Institute of Architecture (AIA) Contract with Carlson regarding the Project. Although the form contract was submitted by Carlson, it was never signed nor was any other written agreement between Carlson and Citizens ever executed. Nonetheless, Citizens and Carlson understood that its terms governed their relationship as to the Project. Carlson submitted a number of change orders to Citizens that increased the GMP by approximately $2 million. 2

¶ 7 Three Mellon Center is a steel structure with an outer skin and core areas, 3 which are structural areas in the building which cannot be taken down without causing the collapse of the entire building. The space on each floor was demolished with the exception of the core. Carlson did not perform the work on the Project, but, instead, hired various firms, including the Subcontractors, to perform the required work. The Subcontractors entered into separate subcontracts with Carlson to perform their work on the Project. The *561 scope of each Subcontractors work as defined in their individual subcontracts was undisputed and is detailed below.

Wyatt Incorporated

¶ 8 On or about December 31, 2001, Carlson entered into a subcontract with Wyatt to perform work on the Project. The original amount of the subcontract was $1,515,947.00. After Carlson approved change orders, the subcontract amount increased to $3,289,254.00. According to the terms of the subcontract, Wyatt was to complete the drywall and ceiling of the project. Prior to this work, Wyatt had done demolition work on the Project; however, this work was not the basis of the Mechanics’ lien action.

¶ 9 The work pursuant to the subcontract included installation of metal stud drywall, acoustic ceiling tile, doors, door-frames, restrooms, hardware, and concrete work on floors 21 through 29, one half of floor 17, and the mailroom in the basement. Wyatt installed fire-resistant drywall and ceiling tiles in the UPS (uninterrupted power supply room), computer server, IDF, and MDF (main distribution frame) rooms. It also renovated the core area elevator lobbies to include domed ceilings.

¶ 10 On the 24th floor, Wyatt also demolished and refinished the exterior portion of some columns in order to provide space for a high density filing system to be installed by another subcontractor. On the 27th floor, Wyatt constructed a fitness room with a restroom. Between the 28th and 29th floor, Wyatt installed decking to accommodate the monumental staircase that was to connect the two floors. Wyatt also raised the floor in the computer room.

¶ 11 Wyatt completed its work on January 21, 2003. Of the amended subcontract amount, Wyatt claimed that it was not paid for $83,779.83 for its work on the project. On February 27, 2003, Wyatt informed Citizens that it was owed $83,779.83 for its work on the Project. On April 15, 2003, Wyatt provided formal notice of its Mechanics’ Lien to Citizens and to Carlson.

Apostolos Group, Inc.

¶ 12 On February 4, 2002, Carlson subcontracted with Apostólos for painting related to the Project. The initial subcontract was in the amount of $192,154.00 and increased to $414,705.00 after change orders were made.

¶ 13 Apostólos applied paint and wall covering to the walls on floors 21 through 29. It also painted the unfinished doors and door frames on these floors. Apostó-los was to touch up any scratches on existing exterior windows. Apostólos applied an epoxy paint for the UPS floor and angle frame paint under the battery cabinet in that room. On February 12, 2003, Apostó-los completed its painting work. On April 9, 2003, Apostólos provided Citizens notice of its Mechanics’ Lien.

Mendel Steel and Ornamental Iron

¶ 14 Carlson subcontracted with Mendel Steel on January 31, 2002, to perform miscellaneous steel and structural steel work on the Project. Mendel Steel’s work included fortifying the structural steel to support the new opening between the 28th and 29th floors. It also installed the structure for the monumental staircase between the 28th and 29th floors. This staircase was to be a showpiece, or focal point, of those floors and was the sole means of access between the floors. Regarding the stairs and adjoining balcony on the 29th floor, Mendel Steel was to provide the steel supports, brackets, glass, and stainless steel railing. Mendel Steel reinforced the raised floor built by Wyatt that was to support the high density rolling filing system on the 24th floor. It was also to supply the plate steel to be used at the UPS battery cabinet. Mendel Steel also *562 supplied steel clips for lobbies and installed steel supports for toilet partitions and vanity counters in the restrooms. Mendel Steel completed its work on the Project on April 3, 2003.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glass, E. v. Delong, M.
Superior Court of Pennsylvania, 2025
T.A.T. Trucking v. James J. Anderson Construction
Superior Court of Pennsylvania, 2024
Esposito, E. v. The Assoc. of Property Owners
Superior Court of Pennsylvania, 2024
Stein, M. v. Grabowski R. and Grabowski, S.
Superior Court of Pennsylvania, 2024
Jeffrey M. Brown Assoc. v. Main Street Phase
301 A.3d 935 (Superior Court of Pennsylvania, 2023)
Gasbarre Products v. Smith, S.
2022 Pa. Super. 21 (Superior Court of Pennsylvania, 2022)
Baker, R. v. Liptak, B.
Superior Court of Pennsylvania, 2022
Martin, S. v. Burchinal, L.
Superior Court of Pennsylvania, 2021
El-Gharbaoui, A. v. Ajayi, A.
2021 Pa. Super. 146 (Superior Court of Pennsylvania, 2021)
Terra Firma Builders v. King, W., Aplts.
Supreme Court of Pennsylvania, 2021
Newman & Co., Inc. v. City of Phila.
Commonwealth Court of Pennsylvania, 2021
Brackenridge Construction Inc. v. Lakeville DPP
Superior Court of Pennsylvania, 2020
Americo Construction v. Four Ten
Superior Court of Pennsylvania, 2020
Risinger, S. v. Litzinger, M.
Superior Court of Pennsylvania, 2019
Friedman, B. v. Murphy, M.
Superior Court of Pennsylvania, 2019
Terra Firma Builders v. King, W.
Superior Court of Pennsylvania, 2019
Stein, M. v. Grabowski, R.
Superior Court of Pennsylvania, 2019
The Estate of J.G. Guyaux v. Twp. of North Fayette ~ Appeal of: C. Guyaux
208 A.3d 1137 (Commonwealth Court of Pennsylvania, 2019)
Metro Real Estate Investment, LLC v. Bembry, D.
207 A.3d 336 (Superior Court of Pennsylvania, 2019)
McDonald Building Company v. Walnut Park Plaza
Superior Court of Pennsylvania, 2018

Cite This Page — Counsel Stack

Bluebook (online)
976 A.2d 557, 2009 Pa. Super. 107, 2009 Pa. Super. LEXIS 1008, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wyatt-inc-v-citizens-bank-of-pa-pasuperct-2009.