Brackenridge Construction Inc. v. Lakeville DPP

Superior Court of Pennsylvania·Decided June 9, 2020·No. 2611 EDA 2019·Unpublished

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

BRACKENRIDGE CONSTRUCTION : IN THE SUPERIOR COURT OF COMPANY INC. : PENNSYLVANIA :

Appellant :

:

:

v. :

:

: No. 2611 EDA 2019

LAKEVILLE DPP, LLC, :

Appeal from the Order Entered July 30, 2019 In the Court of Common Pleas of Wayne County Civil Division at No(s):

No. 90-MLD-2017

BEFORE: BOWES, J., SHOGAN, J., and PELLEGRINI, J.* MEMORANDUM BY PELLEGRINI, J.: FILED JUNE 9, 2020 Brackenridge Construction Company, Inc. (Brackenridge) appeals from the order entered in the Court of Common Pleas of Wayne County (trial court) sustaining the preliminary objections of Lakeville DPP, LCC (Lakeville) and striking Brackenridge’s mechanics’ lien claim. The trial court found that Brackenridge was precluded from enforcing its lien because it had already prevailed at arbitration on claims for unpaid labor. After review, we reverse and remand for further proceedings.

I.

In April 2016, Brackenridge entered into a master construction contract with Dollar Texas Properties XV, LLC c/o GBT Realty Corporation (GBT) to build

* Retired Senior Judge assigned to the Superior Court.

two Dollar General Stores in Pennsylvania. One would be built in Wayne County, which is the subject project in this appeal; the other would be built in Franklin County. Under the contract, GBT would assign all of its rights to a special purpose entity created to finance and own each respective project. Lakeville is the assignee of the Wayne County project and owner of the subject property.

The contract also contained dispute resolution provisions requiring all disputes to be settled by binding arbitration. Section 12.4 of the contract entitled “BINDING DISPUTE RESOLUTION” provided:

If the matter is unresolved after submission of the matter to a mitigation procedure or to mediation, the Parties shall submit the matter to the binding dispute resolution procedures selected below.

***

Arbitration using the current Construction Industry Arbitration Rules of the AAA [American Arbitration Association] or the Parties may mutually agree to select another set of arbitration rules. The administration of the arbitration shall be as mutually agreed by the Parties. If the Parties cannot agree, then it shall be administered by AAA.

The dispute resolution provisions also addressed Brackenridge’s lien rights under Section 12.6 entitled “LIEN RIGHTS.” That section provided that “[n]othing in this article shall limit any rights or remedies not expressly waived by the Contractor that the Contractor may have under lien laws.”

After completing both projects, Brackenridge disputed how much it had been paid for its work, claiming that it was still owed $102,480.73 for the

Wayne County project and $76,707.49 for the Franklin County project. Consequently, in December 2017, Brackenridge timely filed in each county a statement of mechanics’ lien claims pursuant to the Mechanics’ Lien Law of 1963 (Mechanics’ Lien Law), 49 P.S. §§ 1101-1902.1 As required by the contract, Brackenridge’s unpaid labor claims were submitted to arbitration. On March 11, 2019, the Arbitrator issued an award in favor of Brackenridge for the full amount of its unpaid labor claims on both projects totaling $179,188.21 plus interest.2 That amount, however, was

1Contractors are required to file a claim within six months after completion of work. See 49 P.S. § 1502(a)(1).

2 An arbitrator’s authority is restricted to the powers the parties have granted him [or her] in the arbitration agreement. A common law arbitration award “may be corrected if the arbitrator exceeds the scope of his authority.” Com. ex rel. Kane v. Philip Morris USA, Inc., 114 A.3d 37, 56 (Pa. Cmwlth. 2015) (citations and internal quotation marks omitted.) The Arbitrator listed the six separate claims and counterclaims that were submitted to him to decide as:

1. A claim by Claimant for the unpaid balances due for work performed under the Agreement and Amendments.

2. A claim by Claimant for interest on the unpaid balance referenced in claim 1 above.

3. A claim by Claimant for penalties and legal fees under Pennsylvania’s Contractor and Subcontractors Payment Act.

4. A counterclaim by Respondent that Claimant owes liquidated damages to Respondent for failure to complete the work on the Projects on time.

offset by a $70,000 credit awarded to GBT for paving work on the Franklin County project because it was already included in its original bid. Accordingly, excluding costs and attorneys’ fees, Brackenridge’s final award was $109,188.21 plus interest. Both parties sought modification with Brackenridge seeking to decrease the $70,000 offset while GBT wanted language added that the award also settled any derivative lien claims arising out of the contract. The Arbitrator, however, declined both requests.

In the weeks after the arbitration, Brackenridge and GBT reached an impasse over payment of the award. GBT claims that it tried to pay but Brackenridge rejected any payment that did not also include the $70,000 offset. Believing that Brackenridge was using its mechanics’ liens as a vehicle to recover payment beyond that awarded, GBT refused to pay any part of the arbitration award until Brackenridge released its mechanics liens against the properties.

5. A counterclaim by Respondent that Claimant owes Respondent money for performing paving work that was in Claimant’s scope of work for the Lakeville Project.

6. A counterclaim by Respondent for punch list work not performed by Claimant.

(Reproduced Record at 141).

In May 2019, Brackenridge filed complaints in both counties to enforce its mechanics’ lien claims against the properties.3 Lakeville, as owner of the Wayne County property, responded in the trial court by filing preliminary objections in the nature of a motion to strike. Relying on res judiciata and collateral estoppel, Lakeville asserted that the complaint was legally insufficient under Pa.R.C.P. 1028(a)(4) because the underlying basis for the lien—the unpaid labor claims—had already been litigated and decided at the arbitration.4 Brackenridge countered that its lien rights were not submitted in the arbitration and were preserved by Section 12.6 of the contract’s dispute resolution provisions. On July 30, 2019, the trial court sustained Lakeville’s preliminary objections and struck Brackenridge’s complaint with prejudice,

3 49 P.S. § 1701(a) provides that “[t]he practice and procedure to obtain judgment upon a claim filed shall be governed by the Rules of Civil Procedure promulgated by the Supreme Court.”

4 Pa.R.C.P. 1028(a)(6) also provides that preliminary objections may be filed based on the “pendency of a prior action or agreement for alternative dispute resolution.” We also note that Pa.R.C.P 1030(a) provides that “all affirmative defenses including but not limited to the defenses of accord and satisfaction, arbitration and award, consent, discharge in bankruptcy, duress, estoppel, failure of consideration, fair comment, fraud, illegality, immunity from suit, impossibility of performance, justification, laches, license, payment, privilege, release, res judicata, statute of frauds, statute of limitations, truth and waiver shall be pleaded in a responsive pleading [Answer] under the heading ‘New Matter.’ A party may set forth as new matter any other material facts which are not merely denials of the averments of the preceding pleading.” (Emphasis added).

stating that it did not “have the appropriate authority to revisit or reconsider the issues decided at the arbitration.”5 After dismissal of its complaint, Brackenridge filed a notice of appeal.6 In its court-ordered Pa.R.A.P. 1925(b) statement of errors complained of on appeal, Brackenridge contended that the trial court erred in finding that the prior arbitration precluded enforcement of its mechanics’ lien.7

Free access — add to your briefcase to read the full text and ask questions with AI

Brackenridge Construction Inc. v. Lakeville DPP, (Pa. Ct. App. 2020).

Brackenridge Construction Inc. v. Lakeville DPP (Brackenridge Construction Inc. v. Lakeville DPP) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Toy v. Metropolitan Life Insurance
863 A.2d 1 (Superior Court of Pennsylvania, 2004)
Clark v. Troutman
502 A.2d 137 (Supreme Court of Pennsylvania, 1985)
Matternas v. Stehman
642 A.2d 1120 (Superior Court of Pennsylvania, 1994)
Shaffer v. Smith
673 A.2d 872 (Supreme Court of Pennsylvania, 1996)
Philadelphia Marine Trade Ass'n v. International Longshoremen's Ass'n
308 A.2d 98 (Supreme Court of Pennsylvania, 1973)
Wyatt Inc. v. CITIZENS BANK OF PA
976 A.2d 557 (Superior Court of Pennsylvania, 2009)
Mellon Bank v. Rafsky
535 A.2d 1090 (Supreme Court of Pennsylvania, 1987)
Nagy v. Best Home Services, Inc.
829 A.2d 1166 (Superior Court of Pennsylvania, 2003)
City of Pittsburgh v. Zoning Board of Adjustment
559 A.2d 896 (Supreme Court of Pennsylvania, 1989)
Khawaja, H. v. Re/Max Central
151 A.3d 626 (Superior Court of Pennsylvania, 2016)
Artsmith Development Group, Inc. v. Updegraff
868 A.2d 495 (Superior Court of Pennsylvania, 2005)
Halowich v. Amminiti
154 A.2d 406 (Superior Court of Pennsylvania, 1959)