Terra Firma Builders v. King, W., Aplts.

CourtSupreme Court of Pennsylvania
DecidedApril 29, 2021
Docket15 MAP 2020
StatusPublished

This text of Terra Firma Builders v. King, W., Aplts. (Terra Firma Builders v. King, W., Aplts.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Terra Firma Builders v. King, W., Aplts., (Pa. 2021).

Opinion

[J-88-2020] [MO: Dougherty, J.] IN THE SUPREME COURT OF PENNSYLVANIA MIDDLE DISTRICT

TERRA FIRMA BUILDERS, LLC, : No. 15 MAP 2020 : Appellee : Appeal from the Order of the : Superior Court at No. 2593 EDA : 2018 dated July 19, 2019, v. : Reconsideration Denied September : 19, 2019, Reversing the Order of the : Delaware County Court of Common WILLIAM KING A/K/A BILLY M. KING AND : Pleas, Civil Division, at No. CV- MELANIE L. KING A/K/A MELANIE L. : 2015-001536 dated August 21, FRANTZ, : 2018, entered August 22, 2018 : Appellants : ARGUED: October 21, 2020

DISSENTING OPINION

JUSTICE DONOHUE DECIDED: April 29, 2021

In this appeal we are asked to interpret the portions of the Mechanics’ Lien Law

that govern a property owner’s challenge to the validity of a mechanics’ lien. Performing

its analysis, the Majority focuses on Sections 502 and 505 of the Mechanics’ Lien Law

and discerns an intent on the part of the General Assembly to provide property owners

with a virtually timeless ability to counter the “powerful statutory tool” that is a mechanics’

lien. See Maj. Op. at 16-17. In so doing, the Majority does not grapple with the entirety

of the Mechanics’ Lien Law or the specific issue before us. As a result, in my view, the

Majority countenances an absurd result that is unsupported by the statute.

The operative facts are undisputed. In 2013, Terra Firma Builders, LLC (“Terra

Firma”) filed a mechanics’ lien against the Kings in an amount exceeding $130,000. In

connection with its mechanics’ lien, Terra Firma filed the required affidavit of service in conformance with Section 502 of the Mechanics’ Lien Law.1 Terra Firma subsequently

discontinued the mechanics’ lien claim. Within a week, it filed another mechanics’ lien.

This lien was identical to the first but assigned a different docket number. Terra Firma

did not file the requisite affidavit of service in connection with this mechanics’ lien claim.

In 2015, Terra Firma filed a complaint to enforce the lien and an action alleging

breach of contract. The Kings did not file preliminary objections challenging Terra Firma’s

failure to file the affidavit of service, but filed an answer and asserted a counterclaim for

breach of contract. In 2017, the trial court consolidated all claims and the matter

proceeded to a bench trial. The trial court found for the Kings, awarding them a portion

of their claimed monetary damages. Both parties filed post-trial motions. While the

motions were pending, the Kings filed a petition to strike the mechanics’ lien, arguing that

the lien was invalid because Terra Firma failed to file the requisite affidavit of service.

The trial court granted post-trial motions but subsequently granted the petition to strike

the lien. The Superior Court reversed, finding that although there is no explicit limitation

on the time for a property owner to contest a lien in the Mechanics’ Lien Law, such a

challenge must be made during the enforcement action on the lien or be deemed to have

been waived. Terra Firma Builders, LLC v. King, 215 A.3d 1002, 1005 (Pa. Super. 2019),

reargument denied (Sept. 19, 2019), appeal granted, 226 A.3d 971 (Pa. 2020).

This Court granted the Kings’ petition for allowance of appeal to address the

following issue:

Is a property owner who seeks to challenge the perfection of a mechanics’ lien required to file preliminary objections before or during the enforcement proceeding of the lien?

1 Section 502 is set forth in full infra.

[J-88-2020] [MO: Dougherty, J.] - 2 Terra Firma Builders, LLC v. King, 226 A.3d 971 (Pa. 2020) (per curiam). Although this

issue asks whether a challenge to the perfection of mechanics’ lien must be raised prior

to or during the enforcement action, the Majority does not answer this question. The

Majority shifts the focus of the issue before us, as it does not consider whether the

challenge must be raised within the enforcement action but only whether the Kings’ raised

their objection in an untimely manner. See Majority Op. at 11(stating the issue presented

in this appeal as “whether the Kings … were required to assert their objection to the lien

much earlier than they did.”). From this altered premise focusing on timing instead of

procedural posture, the Majority veers off course in its analysis.

The question before the Court is one of statutory interpretation, over which our

standard of review is de novo and our scope of review is plenary. SEDA-COG Joint Rail

Auth. v. Carload Express, Inc., 238 A.3d 1225, 1232 (Pa. 2020). As we undertake this

analysis, we are mindful that our objective is to discern the intent of our General

Assembly. 1 Pa.C.S. § 1921(a). When determining legislative intent, individual statutory

provisions must be construed with reference to the entire statute of which they are a part.

Fletcher v. Pa. Prop. & Cas. Ins. Guar. Ass'n, 985 A.2d 678, 684 (Pa. 2009); Rossi v.

Commonwealth, 860 A.2d 64, 66 (Pa. 2004). As recognized by the Majority, mechanics’

liens are remedies created wholly by statute in degradation of the common law. See

Denlinger, Inc. v. Agresta, 714 A.2d 1048, 1052 (Pa. Super. 1998). As such, courts

employ a strict construction of the terms of the Mechanics’ Lien Law. Id.; see also

Artsmith Dev. Grp., Inc. v. Updegraff, 868 A.2d 495, 497 (Pa. Super. 2005).

Mechanics’ liens are “extraordinary remed[ies]” that “provide[] an expeditious

method to obtain a lien at very little cost to the claimant[.]” Phila. Const. Servs., LLC v.

[J-88-2020] [MO: Dougherty, J.] - 3 Domb, 903 A.2d 1262, 1267 (Pa. Super. 2006). The filing of a claim for a lien against

property by a contractor or subcontractor creates a lien claim. See 49 P.S. § 1201(6).

Article V of the Mechanics’ Lien Law sets forth the procedure for the filing and perfection

of a lien claim. Section 502(a) provides as follows:

(a) Perfection of Lien. To perfect a lien, every claimant must:

(1) file a claim with the prothonotary as provided by this act within six (6) months after the completion of his work; and

(2) serve written notice of such filing upon the owner within one (1) month after filing, giving the court, term and number and date of filing of the claim. An affidavit of service of notice, or the acceptance of service, shall be filed within twenty (20) days after service setting forth the date and manner of service. Failure to serve such notice or to file the affidavit or acceptance of service within the times specified shall be sufficient ground for striking off the claim.

49 P.S. § 1502(a)(1)-(2). Section 505 establishes a procedure for a property owner to

challenge a mechanics’ lien claim, which is the focus of this appeal. It provides that

[a]ny party may preliminarily object to a claim upon a showing of exemption or immunity of the property from lien, or for lack of conformity with this act. The court shall determine all preliminary objections. If an issue of fact is raised in such objections, the court may take evidence by deposition or otherwise.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Philadelphia Construction Services, LLC v. Domb
903 A.2d 1262 (Superior Court of Pennsylvania, 2006)
Daly v. Hemphill
191 A.2d 835 (Supreme Court of Pennsylvania, 1963)
Strickler v. United Elevator Co., Inc.
391 A.2d 614 (Superior Court of Pennsylvania, 1978)
Fletcher v. Pennsylvania Property & Casualty Insurance Guaranty Ass'n
985 A.2d 678 (Supreme Court of Pennsylvania, 2009)
Pennsylvania Labor Relations Board v. Uniontown Hospital Ass'n
247 A.2d 621 (Supreme Court of Pennsylvania, 1968)
Rossi v. Commonwealth
860 A.2d 64 (Supreme Court of Pennsylvania, 2004)
Denlinger, Inc. v. Agresta
714 A.2d 1048 (Superior Court of Pennsylvania, 1998)
Artsmith Development Group, Inc. v. Updegraff
868 A.2d 495 (Superior Court of Pennsylvania, 2005)
Hearst Television, Inc. v. Norris
54 A.3d 23 (Supreme Court of Pennsylvania, 2012)
Titusville Iron Works v. Keystone Oil Co.
18 A. 739 (Supreme Court of Pennsylvania, 1889)
Linden Steel Co. v. Imperial Ref. Co.
20 A. 867 (Supreme Court of Pennsylvania, 1890)
Klinefelter v. Baum
33 A. 582 (Supreme Court of Pennsylvania, 1896)
Rosenberg v. Cupersmith
87 A. 570 (Supreme Court of Pennsylvania, 1913)
Mesta Machine Co. v. Dunbar Furnace Co.
95 A. 585 (Supreme Court of Pennsylvania, 1915)
Day & Zimmermann, Inc. v. Blocked Iron Corp. of America
147 A.2d 332 (Supreme Court of Pennsylvania, 1959)
Crane Co. v. Rogers
60 Pa. Super. 305 (Superior Court of Pennsylvania, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
Terra Firma Builders v. King, W., Aplts., Counsel Stack Legal Research, https://law.counselstack.com/opinion/terra-firma-builders-v-king-w-aplts-pa-2021.