Terra Firma Builders v. King, W., Aplts.

Supreme Court of Pennsylvania·Decided April 29, 2021·No. 15 MAP 2020·Published

Opinion

[J-88-2020] IN THE SUPREME COURT OF PENNSYLVANIA MIDDLE DISTRICT

BAER, C.J., SAYLOR, TODD, DONOHUE, DOUGHERTY, WECHT, MUNDY, JJ.

TERRA FIRMA BUILDERS, LLC, : No. 15 MAP 2020 : Appellee : Appeal from the Order of Superior : Court dated 07/19/2019 at No. 2593 v. : EDA 2018, reversing the 8/21/2018 : Order of the Court of Common : Pleas, Delaware County, at No. CV- WILLIAM KING, a/k/a BILLY M. KING, AND : 2015-001536. MELANIE L. KING, a/k/a MELANIE L. : FRANTZ : ARGUED: October 21, 2020 : Appellants : :

OPINION

JUSTICE DOUGHERTY DECIDED: April 29, 2021 We consider whether the failure of a mechanics’ lien claimant to comply with

express statutory requirements results in an unperfected lien such that the property

owner’s late objection to the lien’s defect does not constitute waiver. We conclude the

Superior Court erred in determining that the owner’s objection to the defect was waived

in this case, and we therefore reverse.

Appellants, William King a/k/a Billy M. King, and Melanie L. King a/k/a Melanie L.

Frantz (the Kings), hired appellee Terra Firma Builders, LLC (TF) to perform construction

work in the backyard of their home. The construction began on June 25, 2012 pursuant

to a written contract. In December 2012, TF was removed from the project before its

completion due to a dispute about the work performed up to that point. On February 20, 2013, TF commenced two lawsuits in the court of common pleas of Delaware County: 1)

a civil action seeking damages for breach of contract and unjust enrichment; and 2) a

mechanics’ lien claim for alleged unpaid labor and materials in the amount of

$131,123.24, pursuant to the Mechanics’ Lien Law of 1963, 49 P.S. §§1101-1902 (the

Law). TF effectuated service of the mechanics’ lien on the Kings by sheriff on March 18,

2013, and filed an affidavit of service with the court on March 22, 2013, as required by

Section 502 of the Law.1 However, on April 23, 2013, TF filed a praecipe for voluntary

discontinuance of the mechanics’ lien claim.

Shortly thereafter, on April 29, 2013, TF filed another mechanics’ lien claim against

the Kings for the same dollar amount as the discontinued lien; this lien was assigned a

new docket number. TF did not file the required affidavit of service for this lien claim. On

May 17, 2013, the Kings filed an answer to the lien claim with a counterclaim alleging

breach of contract. The Kings did not challenge TF’s failure to file an affidavit of service

at this time.

Almost two years later, on February 19, 2015, TF filed a complaint to enforce and

obtain judgment on its lien pursuant to Section 701 of the Law.2 The Kings apparently

1 As further discussed, infra, Section 502 provides, in pertinent part, as follows: (a) Perfection of Lien. To perfect a lien, every claimant must: (1) file a claim with the prothonotary as provided by this act within six (6) months after the completion of his work; and (2) serve written notice of such filing upon the owner within one (1) month after filing, giving the court, term and number and date of filing of the claim. An affidavit of service of notice, or the acceptance of service, shall be filed within twenty (20) days after service setting forth the date and manner of service. Failure to serve such notice or to file the affidavit or acceptance of service within the times specified shall be sufficient ground for striking off the claim. 49 P.S. §1502. 2 Section 701, entitled “Procedure to obtain judgment,” provides:

[J-88-2020] - 2 did not file preliminary objections or otherwise raise TF’s failure to file an affidavit of

service at this time. Almost three more years passed, and on December 8, 2017, the

common pleas court consolidated TF’s mechanics’ lien and breach of contract actions.

The consolidated matters proceeded to a bench trial before the Honorable Spiros E.

Angelos. At trial, the parties agreed that TF failed to complete the project but disputed

the amount of work remaining unfinished and the quality of the work completed. Findings

(a) Practice and Procedure. The practice and procedure to obtain judgment upon a claim filed shall be governed by the Rules of Civil Procedure promulgated by the Supreme Court. (b) Time for Commencing Action. An action to obtain judgment upon a claim filed shall be commenced within two (2) years from the date of filing unless the time be extended in writing by the owner. (c) Venue; Property in More Than One County. Where a claim has been filed in more than one county as provided by section 502(b), proceedings to obtain judgment upon all the claims may be commenced in any of the counties and the judgment shall be res adjudicata as to the merits of the claims properly filed in the other counties. The judgment may be transferred to such other county by filing of record a certified copy of the docket entries in the action and a certification of the judgment and amount, if any. The prothonotary of the court to which the judgment has been transferred shall forthwith index it upon the judgment index and enter it upon the mechanics' lien docket. (d) Limitation on Time of Obtaining Judgment. A verdict must be recovered or judgment entered within five (5) years from the date of filing of the claim. Final judgment must be entered on a verdict within five (5) years. If a claim is not prosecuted to verdict or judgment, as provided above, the claim shall be wholly lost: Provided, however, That in either case, if a complaint has been or shall be filed in the cause and if the cause has been or shall be at issue, all time theretofore or thereafter consumed in the presentation and disposition of all motions and petitions of defendants, substituted defendants and intervenors in the cause, and in any appeal or appeals from any order in the cause, from the date of perfection of such appeal to the date of return of the certiorari from the appellate court to the court of common pleas, shall be excluded in the computation of the five (5) year period herein provided. (e) Defense to Action on Claim. A setoff arising from the same transaction or occurrence from which the claim arose may be pleaded but may not be made the basis of a counterclaim. 49 P.S. §1701 (internal footnote omitted).

[J-88-2020] - 3 of Fact and Conclusions of Law at 11. Judge Angelos found in favor of the Kings on all

claims, including the Kings’ counterclaim, and awarded the Kings monetary damages. TF

filed a motion for a new trial, which was ultimately granted. At the conclusion of the

second trial, the court again found in favor of the Kings on the merits, but did not award

any damages. The parties filed post-trial motions. In June 2018, while the post-trial motions were pending, the Kings filed a petition

to strike the mechanics’ lien on the basis of TF’s failure to file an affidavit of service to

perfect the lien, as required by Section 502 of the Law. TF opposed the petition, arguing

the Kings had waived their right to object to the five-year old lien when they accepted

service of the complaint to enforce, never filed preliminary objections pursuant to Section

505 of the Law, and appeared in court to defend the action.3 Plaintiff’s Memorandum of

Law in Opposition to Defendants’ Petition to Strike Mechanics’ Lien at 3.

The trial court granted the petition to strike on the basis of TF’s failure to file an

affidavit of service and thus perfect its lien, pursuant to Section 502 of the Law. See Trial

Ct. Op. at 6, citing Regency Invs., Inc. v. Inlander Ltd., 855 A.2d. 75, 77 (Pa. Super. 2004)

(“Service requirements under Pennsylvania’s Mechanics’ Lien law are strictly construed

Free access — add to your briefcase to read the full text and ask questions with AI

Terra Firma Builders v. King, W., Aplts., (Pa. 2021).

Terra Firma Builders v. King, W., Aplts. (Terra Firma Builders v. King, W., Aplts.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Philadelphia Construction Services, LLC v. Domb
903 A.2d 1262 (Superior Court of Pennsylvania, 2006)
McCarthy v. Reed Terrace, Inc.
218 A.2d 229 (Supreme Court of Pennsylvania, 1966)
Wyatt Inc. v. CITIZENS BANK OF PA
976 A.2d 557 (Superior Court of Pennsylvania, 2009)
McCarthy v. Reese
215 A.2d 257 (Supreme Court of Pennsylvania, 1965)
Regency Investments, Inc. v. Inlander Ltd.
855 A.2d 75 (Superior Court of Pennsylvania, 2004)
Rees, Weaver & Co. v. M.B.C. Paper Mill Corp.
406 A.2d 562 (Superior Court of Pennsylvania, 1979)
M & P Management, L.P. v. Williams
937 A.2d 398 (Supreme Court of Pennsylvania, 2007)
Freedom Medical Supply, Inc. v. State Farm Fire & Casualty Co.
131 A.3d 977 (Supreme Court of Pennsylvania, 2016)
A. Scott Enterprises v. City of Allentown, Aplt.
142 A.3d 779 (Supreme Court of Pennsylvania, 2016)
Stoke & Co. v. McCullough
107 Pa. 39 (Supreme Court of Pennsylvania, 1884)
O'Kane v. Murray
97 A. 94 (Supreme Court of Pennsylvania, 1916)
Day & Zimmermann, Inc. v. Blocked Iron Corp. of America
147 A.2d 332 (Supreme Court of Pennsylvania, 1959)
Samango v. Hobbs
75 A.2d 17 (Superior Court of Pennsylvania, 1950)
Keely v. Jones
35 Pa. Super. 642 (Superior Court of Pennsylvania, 1908)