Woodward Governor Co. v. Curtiss-Wright Flight Systems, Inc.

164 F.3d 123, 42 Cont. Cas. Fed. 77,414, 1999 U.S. App. LEXIS 215, 1999 WL 6944
CourtCourt of Appeals for the Second Circuit
DecidedJanuary 8, 1999
DocketDocket 98-7910
StatusPublished
Cited by33 cases

This text of 164 F.3d 123 (Woodward Governor Co. v. Curtiss-Wright Flight Systems, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Woodward Governor Co. v. Curtiss-Wright Flight Systems, Inc., 164 F.3d 123, 42 Cont. Cas. Fed. 77,414, 1999 U.S. App. LEXIS 215, 1999 WL 6944 (2d Cir. 1999).

Opinion

MeLAUGHLIN, Circuit Judge:

BACKGROUND

In 1990, the United States contracted-with the Lockheed Corporation (“Lockheed”), for the design and manufacture of a new fighter plane, the F-22 “Raptor.” As is typical in such eases, a series of subcontracts ensued. Lockheed subcontracted the weapons bay doors to Curtiss-Wright Flight Systems, Inc. (“Curtiss-Wright”). Curtiss-Wright, in turn, chose the plaintiff, Woodward Governor Co. (“Woodward”), to produce “test stands” that would allow the bay doors to be tested before they were actually installed in the F-22. It is this latter subcontract that generated this litigation.

The subcontract between Curtiss-Wright and Woodward set a price of $1.5 million for the test stands. It provided that the subcontract was governed by New Jersey law unless New Jersey law was “not dispositive,” in which case the “federal common law of government contracts” governed. The subcontract also contained provisions relating to the rights and responsibilities of the parties vis á vis the federal government.

In January 1994, Woodward began work on the test stands. The work quickly fell behind schedule, however, because Curtiss-Wright had not yet finished designing the weapons bay doors. In late 1995, Curtiss-Wright ordered Woodward to bring the unfinished test stands to Curtiss-Wright’s facility in New Jersey, even though under the subcontract delivery of the test stands by Woodward to Curtiss-Wright was not yet due. To meet this demand, Woodward was forced to transport its materials and employees to New Jersey to continue work on the test stands at Curtiss-Wright’s facility. This, of course, caused further delay and added expense.

Throughout 1995, Curtiss-Wright remained unable to provide Woodward with prototypes of the weapons bay doors. In exasperation, Woodward demanded that Cur-tiss-Wright provide the weapons bay doors by January 1996, at the latest. Curtiss-Wright responded that it could not provide the bay doors until May 1996. In the end, Curtiss-Wright never provided Woodward with a prototype.

By August 2, 1996, Curtiss-Wright had paid Woodward all the progress payments called for by the subcontract, with only the last $317,000 progress payment still due. *126 However, as a result of the substantial delays and the need to work on the test stands at Curtiss-Wright’s facility, Woodward concluded that construction of the test stands would cost substantially more than the $1.5 million originally agreed upon. Woodward thus sought to re-negotiate the terms of the subcontract. After a flurry of correspondence about who would pay for the cost over-runs, Curtiss-Wright broke off the negotiations by informing Woodward that it considered Woodward to have defaulted on the subcontract. Curtiss-Wright then engaged another company to complete construction of the test stands.

In December 1997, Woodward filed suit in the United States District Court for the District of Connecticut (Covello, Judge), seeking damages and declaratory relief for Curtiss-Wright’s alleged breach of the subcontract. Subject matter jurisdiction was premised on a federal question under 28 U.S.C. § 1331. It is undisputed that there is no diversity under 28 U.S.C. § 1332.

Curtiss-Wright moved to dismiss the complaint, arguing that there is no federal question because none of Woodward’s claims is governed by federal law. Woodward countered that federal common law governs because its claims arise out of the breach of a subcontract relating to defense procurement. Judge Covello concluded that federal common law does not apply and dismissed the complaint under Fed.R.Civ.P. 12(b)(1) for lack of subject matter jurisdiction.

Woodward now appeals, advancing three main arguments for its position: (1) the nature of the subcontract requires that this case be governed by federal common law; (2) the parties elected to be governed by federal common law; and (3) Woodward’s claim for equitable relief under federal law requires the application of federal common law.

DISCUSSION

The sole issue is whether the district court had subject matter jurisdiction. We review the factual findings of the district court on a motion to dismiss for lack of subject matter jurisdiction for clear error, while we review the district court’s legal conclusions de novo. See Wake v. United States, 89 F.3d 53, 57 (2d Cir.1996). We conclude that Curtiss-Wright is correct, and federal common law does not apply in this breach of contract suit. Because there is no other basis for federal subject matter jurisdiction, we affirm Judge Covello’s dismissal of the complaint.

It is beyond dispute that if federal common law governs a case, that case presents a federal question within the subject matter jurisdiction of the federal courts, just as if the case were governed by a federal statute. See 28 U.S.C. § 1331; Illinois v. City of Milwaukee, 406 U.S. 91, 100, 92 S.Ct. 1385, 31 L.Ed.2d 712 (1972).

Although “there is no federal general common law,” federal common law sometimes controls certain issues and certain types of cases. Erie R.R. Co. v. Tompkins, 304 U.S. 64, 78, 58 S.Ct. 817, 82 L.Ed. 1188 (1938) (emphasis added). For example, questions about privilege in federal question cases are resolved by the federal common law. See Fed.R.Evid. 501. Similarly, suits involving maritime claims are governed by the venerable federal common law of admiralty. See, e.g., Southern Pac. Co. v. Jensen, 244 U.S. 205, 215, 37 S.Ct. 524, 61 L.Ed. 1086 (1917).

However, the various bailiwicks of federal common law are limited in number. See O’Melveny & Myers v. FDIC, 512 U.S. 79, 87, 114 S.Ct. 2048, 129 L.Ed.2d 67 (1994) (“cases in which judicial creation of a special federal rule would be justified ... are ... ‘few and restricted’” (quoting Wheeldin v. Wheeler, 373 U.S. 647, 651, 83 S.Ct. 1441, 10 L.Ed.2d 605 (1963))). Woodward asserts that this is one of those rare cases where federal common law controls, because it involves a subcontract on a government project that relates to national defense.

In recent years, the Supreme Court has sought to clarify when federal common law enters the picture. See Atherton v. FDIC, 519 U.S. 213, 117 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harris v. Tioga County
N.D. New York, 2021
Burns v. Rovella
D. Connecticut, 2019
Aegis Defense Services, LLC v. Chenega-Patriot Group, LLC
141 F. Supp. 3d 479 (E.D. Virginia, 2015)
L-3 Communications Corp. v. Serco Inc.
39 F. Supp. 3d 740 (E.D. Virginia, 2014)
Torres v. Toback, Bernstein & Reiss LLP
278 F.R.D. 321 (E.D. New York, 2012)
Washington Consulting Group, Inc. v. Raytheon Technical Services Co.
760 F. Supp. 2d 94 (District of Columbia, 2011)
New York v. Salazar
701 F. Supp. 2d 224 (N.D. New York, 2010)
In re Wellbutrin XL Antitrust Litigation
260 F.R.D. 143 (E.D. Pennsylvania, 2009)
Kormendi/Gardner Partners v. Surplus Acquisition Venture, LLC
606 F. Supp. 2d 114 (District of Columbia, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
164 F.3d 123, 42 Cont. Cas. Fed. 77,414, 1999 U.S. App. LEXIS 215, 1999 WL 6944, Counsel Stack Legal Research, https://law.counselstack.com/opinion/woodward-governor-co-v-curtiss-wright-flight-systems-inc-ca2-1999.