Wong v. Di Grazia

386 P.2d 817, 60 Cal. 2d 525, 35 Cal. Rptr. 241, 1963 Cal. LEXIS 260
CourtCalifornia Supreme Court
DecidedNovember 21, 1963
DocketS. F. 21344
StatusPublished
Cited by75 cases

This text of 386 P.2d 817 (Wong v. Di Grazia) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wong v. Di Grazia, 386 P.2d 817, 60 Cal. 2d 525, 35 Cal. Rptr. 241, 1963 Cal. LEXIS 260 (Cal. 1963).

Opinions

TOBRINER, J.

We hold here that an agreement which provided that the lease of a building to commence “upon completion of said building” does not violate the rule [528]*528against perpetuities. (Civ. Code, § 715.2.)1 The nature of the circumstances of the transaction shows that the contemplated building was to be completed within a reasonable time and that such reasonable time was less than 21 years. Hence the interest would either vest or fail within the statutory period. As to the remaining issues upon appeal we believe the trial court property held that the duty of installation of a sprinkler system fell upon the lessees and that their refusal to perform that obligation constituted a breach. We therefore affirm the judgment in favor of the lessors except as to a minor matter of damages awarded them, which we remand to the trial court for clarification.

The factual background which produced this action is neither complicated nor disputed. On July 11, 1958, plaintiffs and defendants entered into a written agreement in which defendants agreed to lease to plaintiffs for a period of 10 years a building to be constructed by defendants. The contract required defendants to construct only the shell of the building, exclusive of toilet facilities, lighting installations, and other improvements.

Paragraph 27 of the agreement provided: “Lessor [defendants] shall forthwith commence the construction of a building upon the herein demised premises, in accordance with plans and specifications noted thereon, a copy of which is attached hereto and made a part hereof. . . . Said plans and specifications are complete, and the Lessor shall not be required to provide or pay for any additional construction. . . . Construction shall commence forthwith upon approval of completed plans and specifications and shall continue expeditiously until said building is completed, subject to material and/or labor shortages, strikes, lockouts, governmental actions and all causes beyond the control of Lessor. Said building shall be completed within ninety (90) days after a building permit has been secured from the City and County of San Francisco of said plans and specifications, subject to the contingencies above mentioned, and Lessee shall not delay [529]*529or impede said construction by making changes or alterations therein, it being understood that the time consumed in effecting any such changes shall be added to the time for the completion of said building. . . . Upon completion of said building ... Lessor shall forthwith cause a Notice of Completion to be recorded, and the term of this lease shall commence upon the recording of said Notice of Completion____”

Plaintiffs paid $7,875 to defendants as an advance rental payment upon the execution of the lease. Later plaintiffs learned that the San Francisco building code required as a prerequisite to issuance of a building permit the installation of a sprinkler system costing approximately $9,500. Plaintiffs insisted that defendants pay the cost of this sprinkler system; defendants refused, contending that plaintiffs should bear this burden.

After fruitless negotiations between the parties, plaintiffs notified defendants that their refusal to proceed with the installation of the system and construction of the building effected a breach of the agreement. Plaintiffs then filed a complaint seeking rescission and the return of the $7,875 paid to defendants. Defendants cross-complained, alleging plaintiffs’ breach. After a trial without a jury, the court rendered judgment for defendants, awarding them damages on the cross-complaint of $9,500.14 plus counsel fees of $1,250. The court credited plaintiffs with the $7,875 deposit, fixing the net amount owed under the judgment as $2,875.14 Both parties appealed.

The ease raises as its major issue the validity of the agreement under the rule against perpetuities. If the agreement survives this attack, we must determine if the court properly held plaintiffs liable for its breach and correctly fixed damages.

Turning to the first point, we note that in an “on completion” lease, such as the present agreement, the question of the application of the rule arises from the fact that the lease term commences upon completion of the building, an event expected to occur in the near future but subject to delay from various contingencies. If the lease were construed to postpone the “vesting” of the lessee’s interest until such commencement of the term, vesting might possibly be delayed longer than 21 years from the execution of the lease, thus purportedly rendering the lease invalid under the rule against perpetuities.

Since “on completion” leases represent a relatively new [530]*530commercial development, the question of their validity has been raised, so far as we have found, in only five cases. Two cases, Haggerty v. City of Oakland (1958) 161 Cal.App.2d 407 [326 P.2d 957], and Southern Airways Co. v. De Kalb County (1960) 101 Ga.App. 689 [115 S.E.2d 207], have held such leases to be in violation of the rule against perpetuities; the latter case, however, was reversed upon the ground that the agreement did not constitute a lease but a management contract. (Southern Airways Co. v. De Kalb County (1960) 216 Ga. 358 [116 S.E. 2d 602].) Three cases, Isen v. Giant Food, Inc. (D.C. Cir. 1961) 295 F.2d 136, City of Santa Cruz v. MacGregor (1960) 178 Cal.App.2d 45 [2 Cal.Rptr. 727], and Halifax v. Vaughn Constr. Co. (Sup.Ct. Nova Scotia, 1957) 9 D.L.R.2d 431, rev. on other grounds (Sup.Ct. Nova Scotia, in bank, 1958) 12 D.L.R.2d 159, have upheld such leases but advanced somewhat different reasons for doing so.2

The rule has been the subject of great debate among scholars and writers; some have suggested basic changes in its application.3 The rule has also been subjected in some states to sweeping statutory reform.4 As we point out infra, it has [531]*531been corroded by many exceptions.5 Learned writers have questioned whether the concepts of vested and contingent [532]*532interests may properly be applied to leases at all.6 The majority have affirmed the legality of “on completion” leases under the rule.7

Many factors militate against a rigid mechanistic operation of the rule in the present case. Thus in drafting the lease the parties themselves did not anticipate the application of the rule; otherwise they would have avoided its impact by formalistic provision.8 Indeed, the attention of the parties and their attorneys to its possible application was first drawn at the appellate level by the District Court of Appeal.9 A noted authority in this field of law has pointed out that “. . . the esoteric learning of the Rule against perpetuities is, apart from dim memories from student days, a monopoly of lawyers who deal in trusts and estates. Those members of the bar who specialize in corporate matters, including commercial leases, are not intimately familiar with it or alerted to its caprices.” (Leach,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Platzner v. Oliver CA2/2
California Court of Appeal, 2025
Tufeld Corp. v. Beverly Hills Gateway, L.P.
California Court of Appeal, 2022
JD Holdings, L.L.C.
Court of Chancery of Delaware, 2014
Malad, Inc. v. Miller
199 P.3d 623 (Court of Appeals of Arizona, 2008)
Bortolotti v. Hayden
449 Mass. 193 (Massachusetts Supreme Judicial Court, 2007)
WOODWARD PARK HOMEOWNERS v. City of Fresno
58 Cal. Rptr. 3d 102 (California Court of Appeal, 2007)
Coulter & Smith, Ltd. v. Russell
966 P.2d 852 (Utah Supreme Court, 1998)
Coulter & Smith, Ltd. v. Russell
925 P.2d 1258 (Court of Appeals of Utah, 1996)
Shaver v. Clanton
26 Cal. App. 4th 568 (California Court of Appeal, 1994)
Tull v. United States
848 F. Supp. 1466 (E.D. California, 1994)
In Re Marilyn H
851 P.2d 826 (California Supreme Court, 1993)
Title Insurance. Co. v. State Board of Equalization
842 P.2d 121 (California Supreme Court, 1992)
Village of Pinehurst v. Regional Investments of Moore, Inc.
412 S.E.2d 645 (Supreme Court of North Carolina, 1992)
Eagle-Picher Industries, Inc. v. Balbos
578 A.2d 228 (Court of Special Appeals of Maryland, 1990)
State Farm Fire & Casualty Co. v. Tan
691 F. Supp. 1271 (S.D. California, 1988)
Otter Creek Development Co. v. Friesenhahn
748 S.W.2d 344 (Supreme Court of Arkansas, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
386 P.2d 817, 60 Cal. 2d 525, 35 Cal. Rptr. 241, 1963 Cal. LEXIS 260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wong-v-di-grazia-cal-1963.