Bellwood Discount Corp. v. Empire Steel Buildings Co.

346 P.2d 467, 175 Cal. App. 2d 432, 1959 Cal. App. LEXIS 1356
CourtCalifornia Court of Appeal
DecidedNovember 19, 1959
DocketCiv. 23911
StatusPublished
Cited by9 cases

This text of 346 P.2d 467 (Bellwood Discount Corp. v. Empire Steel Buildings Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bellwood Discount Corp. v. Empire Steel Buildings Co., 346 P.2d 467, 175 Cal. App. 2d 432, 1959 Cal. App. LEXIS 1356 (Cal. Ct. App. 1959).

Opinion

FOX, P. J.

Plaintiff, referred to herein as Bellwood, seeks (1) to rescind a building contract that it had entered into with defendant, referred to herein as Empire, and (2) to recover its initial payment under said contract.

By the terms of this contract, entered into in March, 1956, Empire agreed to furnish all labor and materials to construct a tapered girder steel panel building on a parcel of land, owned by plaintiff, in the city of Indio, and “. . . to furnish necessary engineering of structural steel and concrete block walls and foundation drawings only.” (Emphasis added.) Under the heading Work not included was the following:

“Any item not specifically mentioned, electrical, plumbing, concrete work, reinforcing steel, painting, or interior partitions.” The contract also stated that the contractor “. . . will obtain necessary permits covering the work set forth in this contract at the expense of the owner.” (Emphasis added.) The contract price was $34,000, and the final 10 per cent was payable “upon completion of Empire’s portion of the work. ...” (Emphasis added.)

This building was to be the repair shop portion of a structure that Bellwood was erecting for use as an automobile agency. Bellwood’s own architect was to design the showroom and the other facilities which comprised this development.

After the contract was signed, Empire prepared a set of plans for submission to the Building Department of Indio covering the structural details of the contemplated building and the concrete walls and foundations. These plans were *435 submitted to and approved by Bellwood and then filed with the building department, Bellwood paying the filing fee. The building department returned the plans along with a “plan correction sheet’’ specifying certain additional information which had to be furnished before a building permit could be issued. Included were such items as plumbing, electrical facilities, an exhaust system, and other ordinary fixtures. Also listed were certain items required by the fire prevention provisions of the building code relating to the use of the structure as an automotive repair shop, which required either installation of automatic sprinklers or the division of the building into two parts by a proper fire resistant wall. The subject of a sprinkling system was not discussed between the parties prior to making the contract. Interior walls were not contemplated by the contract and Bellwood had expressly stated to Empire that no interior walls were to be used in the design of the building. After the building department pointed out the need for one or the other of these items, Bellwood served notice of rescission on Empire and demanded the return of its initial payment of $6,800, which had been made pursuant to the contract. Bellwood based its right to rescind the contract on the ground of mistake.

The trial court rendered judgment for Empire on the •complaint, 1 ruling that Bellwood had no right to rescind. Further, the court held that Bellwood was not entitled to a return of any portion of the initial payment and awarded Empire attorney’s fees in the sum of $1,500. From this judgment Bellwood has appealed.

Mistake, either of law or fact, as grounds for rescission of contract, must affect the execution and material elements of the contract and not merely some collateral matter. (Civ. Code, §§ 1577, 1578; Hannah v. Steinman, 159 Cal. 142 [112 P. 1094]; Vickerson v. Frey, 100 Cal.App.2d 621 [224 P.2d 126].)

The trial court found, inter alia, upon substantial evidence, that: “It was never intended by the parties that the contract was to cover the entire project. The contract so provides. Work by others was intended. Defendant was to receive final payment upon completion of defendant’s portion of the work. The contract expressly excludes ‘any item not specifically mentioned, electrical, plumbing, or interior partitions.’ De *436 fendant had no right or power to deal with any matter other than the building shell and the engineering thereof and the foundation drawings. All other matters were left to plaintiff. Plaintiff never sought from defendant and defendant never offered advice regarding any phase of the project except that expressly covered by the contract. Defendant had no such duty. If plaintiff failed to consider the need for automatic sprinklers, partition walls, plumbing, ventilating or other matters not expressly covered by the contract it was of no concern of defendant and was a collateral matter.” (Emphasis added.)

From the foregoing it is apparent that no provision for either a sprinkling system or a fire resistant interior wall was included in the contract and that Empire owed Bellwood no duty with respect thereto. These items were collateral to the agreement of the parties. Therefore, the court correctly held that plaintiff had no right to rescind on the ground of mistake. (Civ. Code, §§ 1577, 1578; Hannah v. Steinman, supra; Vickerson v. Frey, supra.)

Bellwood also contends that it had a right to rescind the contract on the grounds of fraud, illegality and impossibility of performance. On the issue of fraud, the trial court in a memorandum opinion stated: “Because the terms of the contract placed no duty upon Empire to advise Bellwood regarding phases of the project not covered by the contract, Empire had no duty to speak on those subjects, and its failure so to do cannot amount to fraud.” We agree with this conclusion which is in harmony with the findings. Furthermore, the court upon sufficient evidence held that failure to obtain the necessary permits and to proceed further with the work under the contract was due entirely to the refusal of Bellwood to supply the necessary additional information to the building department. Therefore, performance by Empire would have been neither illegal nor impossible if Bellwood had met its obligations under the contract. Bellwood’s further contention, that the contract was illegal in that Empire did not perform the required engineering services as a registered engineer, is answered by the direct evidence that Empire’s Chief Engineer, Mr. Karp, was a registered civil and structural engineer and personally drew the plans. (Bus. & Prof. Code, § 6738, subd. (a) (1).)

Bellwood also complains of the trial court’s decision that it was not entitled to the return of any portion of the *437 $6,800 initial payment made by it to Empire. Bellwood principally relies on Civil Code, section 3275 and the case of Freedman v. Rector, 37 Cal.2d 16 [230 P.2d 629, 31 A.L.R.2d 1], in support of its argument- that it was entitled to restitution under its second cause of action for “money had and received.” Civil Code, section 3275, reads: “Relief in Case of Forfeiture.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mollasgo v. Tills (In Re Tills)
419 B.R. 444 (S.D. California, 2009)
Interstate Industrial Uniform Rental Service, Inc. v. Couri Pontiac, Inc.
355 A.2d 913 (Supreme Judicial Court of Maine, 1976)
Guthrie v. Times-Mirror Co.
51 Cal. App. 3d 879 (California Court of Appeal, 1975)
American National Insurance v. Continental Parking Corp.
42 Cal. App. 3d 260 (California Court of Appeal, 1974)
Wood v. Kalbaugh
39 Cal. App. 3d 926 (California Court of Appeal, 1974)
Wong v. Di Grazia
386 P.2d 817 (California Supreme Court, 1963)
Independent Iron Works, Inc. v. County of Tulare
207 Cal. App. 2d 164 (California Court of Appeal, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
346 P.2d 467, 175 Cal. App. 2d 432, 1959 Cal. App. LEXIS 1356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bellwood-discount-corp-v-empire-steel-buildings-co-calctapp-1959.